This calculator applies the fee lines quoted on the Virginia Beach permit pages: the city's own plan review, permit and surcharge figures, as published by the Planning & Community Development - Building Permits and Inspections. Pick a project, change the inputs, and the breakdown shows each line and how it is computed. 10 of 10 project types have a computable formula on their page; the rest show the page's own figure.
- Permits and Inspections prices by area for new space (non-heated $50 + $4 per 100 sq ft, heated $50 + $7 per 100 sq ft), by value for alterations, roofing, mechanical and pools ($50 + $5 per $1,000), and per item for trades (plumbing $50 + $6 per fixture, electrical $50 + $5 per circuit, gas $50 + $4 per outlet).
- Every permit adds a 2% state levy and a $10 technology fee. The fee sheet does not say whether the levy covers the plan review line; the pages, and these models, apply it to the permit fees only (a levy on plan review would add 50 cents on $25 or $2 on $100).
- Plan review is $25 at the counter (500 sq ft or less, plan set of five pages or less; any uncovered deck) or $100 online. Fences within 30 ft of a right-of-way take a flat $61 zoning permit.
Virginia Beach shed permit fee
A shed over 256 sq ft (or more than one story) pays the non-heated rate of $50 plus $4 per 100 sq ft or fraction, the 2% state levy on that fee, the $10 technology fee and plan review ($25 at the counter for 500 sq ft or less with five pages or less, else $100).
| Line | How it is computed | Amount |
|---|---|---|
| Building permit (non-heated rate) | $50 + 3 × $4 per 100 above 0 | $62 |
| Technology fee (building permit) | flat | $10 |
| Counter plan review ($25; 500 sq ft or less, plan set of five pages or less) | flat | $25 |
| State levy (2% of the permit fees) | 2% of $62 | $1.24 |
Virginia Beach fence permit fee
A fence or wall within 30 ft of a public right-of-way needs a flat $61 zoning permit per lot (no inspection); one farther back needs none, and a pool barrier fence takes a building permit listed at $60.60 instead.
| Line | How it is computed | Amount |
|---|---|---|
| Zoning fence permit (within 30 ft of a right-of-way) | flat | $61 |
Virginia Beach deck permit fee
Every deck needs a building permit at the non-heated rate of $50 plus $4 per 100 sq ft or fraction, plus the 2% state levy on that fee, the $10 technology fee and plan review ($25 at the counter for an uncovered deck with five pages or less, else $100).
| Line | How it is computed | Amount |
|---|---|---|
| Building permit (non-heated rate) | $50 + 3 × $4 per 100 above 0 | $62 |
| Technology fee (building permit) | flat | $10 |
| Counter plan review ($25; uncovered deck of any size, plan set of five pages or less) | flat | $25 |
| State levy (2% of the permit fees) | 2% of $62 | $1.24 |
Virginia Beach pool permit fee
A pool, hot tub or spa that can hold at least 24 inches of water pays $50 plus $5 per $1,000 of construction value, the 2% state levy and the $10 technology fee; in-ground pools add a $35 right-of-way fee and a new barrier fence is a separate $60.60 permit.
| Line | How it is computed | Amount |
|---|---|---|
| Pool building permit ($50 + $5 per $1,000) | $50 + 45 × $5 per 1,000 above 0 | $275 |
| Technology fee (pool permit) | flat | $10 |
| Right-of-way fee (in-ground pools) optional | flat | $35 |
| Pool barrier fence permit (levy and technology fee included) optional | flat | $60.60 |
| No plan review | flat | $0 |
| State levy (2% of the permit fees) | 2% of $275 | $5.50 |
Virginia Beach roof replacement permit fee
A reroof (tear-off or nail-over) pays $50 plus $5 per $1,000 of construction value or fraction, the 2% state levy and the $10 technology fee, with no plan review; repairs of 100 sq ft or less of covering are exempt.
| Line | How it is computed | Amount |
|---|---|---|
| Roofing and siding permit ($50 + $5 per $1,000) | $50 + 9 × $5 per 1,000 above 0 | $95 |
| Technology fee | flat | $10 |
| State levy (2% of the permit fees) | 2% of $95 | $1.90 |
Virginia Beach bathroom remodel permit fee
Same-spot fixture swaps, retiling and paint need no permit; adding or moving fixtures takes a plumbing permit ($50 + $6 per fixture or drain), new circuits an electrical permit ($50 + $5 per circuit) and moving walls a building alteration permit ($50 + $5 per $1,000 plus plan review), each with the 2% levy and a $10 technology fee.
| Line | How it is computed | Amount |
|---|---|---|
| Building alteration permit ($50 + $5 per $1,000) optional | $50 + 6 × $5 per 1,000 above 0 | $80 |
| Technology fee (building permit; tick with the building alteration) optional | flat | $10 |
| Counter plan review | flat | $25 |
| Plumbing permit ($50 + $6 per fixture or drain) optional | $50 + 3 × $6 per 1 above 0 | $68 |
| Technology fee (plumbing permit) optional | flat | $10 |
| Electrical permit ($50 + $5 per circuit) optional | $50 + 2 × $5 per 1 above 0 | $60 |
| Technology fee (electrical permit) optional | flat | $10 |
| State levy (2% of the permit fees) | 2% of $208 | $4.16 |
Virginia Beach kitchen remodel permit fee
Cabinets, flooring, paint and in-place sink swaps need no permit; altering a wall takes a building alteration permit ($50 + $5 per $1,000 plus plan review), moved or added fixtures a plumbing permit ($50 + $6 each), new circuits an electrical permit ($50 + $5 each) and gas lines a gas permit ($50 + $4 per outlet), each with the 2% levy and $10.
| Line | How it is computed | Amount |
|---|---|---|
| Building alteration permit ($50 + $5 per $1,000) optional | $50 + 15 × $5 per 1,000 above 0 | $125 |
| Technology fee (building permit; tick with the building alteration) optional | flat | $10 |
| Counter plan review | flat | $25 |
| Plumbing permit ($50 + $6 per fixture or drain) optional | $50 + 2 × $6 per 1 above 0 | $62 |
| Technology fee (plumbing permit) optional | flat | $10 |
| Electrical permit ($50 + $5 per circuit) optional | $50 + 4 × $5 per 1 above 0 | $70 |
| Technology fee (electrical permit) optional | flat | $10 |
| State levy (2% of the permit fees) | 2% of $257 | $5.14 |
Virginia Beach electrical panel permit fee
A panel replacement or relocation is a $50 item; a change of single-phase service is half the new-service fee ($45 up to 100 A, $65 up to 200 A, $105 up to 400 A), plus $50 and $5 per circuit added, repaired or extended, the 2% state levy and the $10 technology fee.
| Line | How it is computed | Amount |
|---|---|---|
| Change of service, single phase (half of $50 + $20 per 50 amps) | $50 + 4 × $20 per 50 above 0 × 0.5 | $65 |
| Technology fee | flat | $10 |
| State levy (2% of the permit fees) | 2% of $65 | $1.30 |
Virginia Beach hvac permit fee
Like-for-like electric replacements on the same refrigerant need no permit; a refrigerant change, fuel-fired unit, new location or new ducts takes a mechanical permit at $50 plus $5 per $1,000 of construction value, and gas work a gas permit at $50 plus $4 per outlet or shutoff, each with the 2% levy and $10.
| Line | How it is computed | Amount |
|---|---|---|
| Mechanical permit ($50 + $5 per $1,000) | $50 + 12 × $5 per 1,000 above 0 | $110 |
| Technology fee (mechanical permit) | flat | $10 |
| Gas permit ($50 + $4 per outlet or shutoff; tick its technology fee with it) optional | $50 + 1 × $4 per 1 above 0 | $54 |
| Technology fee (gas permit; tick with it) optional | flat | $10 |
| State levy (2% of the permit fees) | 2% of $164 | $3.28 |
Virginia Beach adu permit fee
Per a third-party copy of the ordinance, zoning allows only a limited-use ADU on R-40 lots for family or an on-premise employee, with no rental (a state ADU law takes effect July 1, 2027); where allowed, new heated space pays $50 plus $7 per 100 sq ft or fraction, the 2% levy, the $10 technology fee and plan review.
| Line | How it is computed | Amount |
|---|---|---|
| Building permit (heated rate) | $50 + 4 × $7 per 100 above 0 | $78 |
| Technology fee | flat | $10 |
| Counter plan review ($25; 500 sq ft or less, plan set of five pages or less) | flat | $25 |
| State levy (2% of the permit fees) | 2% of $78 | $1.56 |
What the estimate covers
City fees only, on the ordinary residential path each page prices: the building or trade permit plus the mandatory lines the city adds to it. It leaves out whatever the page says is separate (a designer's fee, a contractor's licence, a utility connection) and anything the page does not price. Fee schedules change on the city's budget cycle; the month each page was last verified is Nov 2026, and the verification method explains how changes are caught.
Frequently asked questions
Other city calculators
- Albuquerque, NM
- Aurora, CO
- Austin, TX
- Baltimore, MD
- Boston, MA
- Charlotte, NC
- Chicago, IL
- Cincinnati, OH
- Colorado Springs, CO
- Corpus Christi, TX
- Dallas, TX
- Denver, CO
- El Paso, TX
- Fort Worth, TX
- Fresno, CA
- Honolulu, HI
- Houston, TX
- Indianapolis, IN
- Irvine, CA
- Jacksonville, FL
- Kansas City, MO
- Las Vegas, NV
- Long Beach, CA
- Los Angeles, CA
- Louisville, KY
- Miami, FL
- Milwaukee, WI
- Minneapolis, MN
- Nashville, TN
- New Orleans, LA
- New York City, NY
- Orlando, FL
- Philadelphia, PA
- Phoenix, AZ
- Pittsburgh, PA
- Portland, OR
- Raleigh, NC
- Riverside, CA
- Sacramento, CA
- San Antonio, TX
- San Diego, CA
- San Francisco, CA
- San Jose, CA
- Seattle, WA
- St. Louis, MO
- St. Paul, MN
- Stockton, CA
- Tampa, FL
- Tucson, AZ
- Tulsa, OK
- Washington, DC
- Wichita, KS
Related: All cities · Research: fees compared across 30 cities · Virginia Beach permit guide