City fee lines from the Nashville permit pages, computed for your project. Sourced, verified Nov 2026.
Verified Nov 2026Calculator
This calculator applies the fee lines quoted on the Nashville permit pages: the city's own plan review, permit and surcharge figures, as published by the Metro Nashville Department of Codes and Building Safety. Pick a project, change the inputs, and the breakdown shows each line and how it is computed. 9 of 10 project types have a computable formula on their page; the rest show the page's own figure.
Residential building permits are $5.00 per $1,000 of value plus a codes tech fee of 10% of that and a $25 zoning examination fee; one- and two-family permits pay no plan review fee.
Electrical, plumbing and gas/mechanical permits are separate filings, each with a $75 minimum; re-inspections are $50.
Nashville shed permit fee
A storage building of 100 sq ft or more needs a residential building permit at $5.00 per $1,000 of value, a 10% codes tech fee and a $25 zoning examination fee; Metro does not say a smaller shed is exempt, so ask the Zoning Help Desk.
$47estimated city fees at the inputs above
Line
How it is computed
Amount
Building fee ($5.00 per $1,000)
0.5% of $4,000
$20
Codes tech fee (10%)
10% of $20
$2
Zoning examination fee
flat
$25
The page's own example: “$4,000 prefab shed: $20 building fee + $2 tech fee + $25 zoning fee = $47.”
Not included: Re-inspections ($50 each); whether a shed under 100 sq ft needs a permit, which Metro's permit list does not address; trade permits are priced at their $75 minimum. The valuation is assumed to be the job's cost; Metro bills new residential structures on valuation figures, so ask the Zoning Help Desk how yours will be valued.
Source: Metro Code fee schedule (building fees; 16.12.220 plumbing, 16.16.400 gas/mechanical, 16.20.250 electrical). Read the Nashville shed permit page, which quotes the rule and records when it was last verified (Nov 2026).
Nashville fence permit fee
BL2025-1115 (2026) requires a permit for a new opaque fence, but Metro has published no fence permit fee; open fences need no permit.
No city fee figure on the page: The page says there is no published figure: the ordinance leaves the fee to the Department of Codes Administration and the fee schedule has no fence line.
Every new or replacement deck is a residential building permit at $5.00 per $1,000 of value plus a 10% codes tech fee and a $25 zoning examination fee.
$80estimated city fees at the inputs above
Line
How it is computed
Amount
Building fee ($5.00 per $1,000)
0.5% of $10,000
$50
Codes tech fee (10%)
10% of $50
$5
Zoning examination fee
flat
$25
The page's own example: “$10,000 deck: $50 building fee + $5 tech fee + $25 zoning fee = $80.”
Not included: Re-inspections after a failed inspection ($50 each); no separate plan review fee for one- and two-family permits. The valuation is assumed to be the job's cost; Metro bills new residential structures on valuation figures, so ask the Zoning Help Desk how yours will be valued.
Source: Metro Code fee schedule (building fees; 16.12.220 plumbing, 16.16.400 gas/mechanical, 16.20.250 electrical). Read the Nashville deck permit page, which quotes the rule and records when it was last verified (Nov 2026).
Nashville pool permit fee
Every above- or in-ground pool is a residential building permit at $5.00 per $1,000 of value plus a 10% codes tech fee and a $25 zoning fee; electrical, plumbing and gas heater permits are separate, each with a $75 minimum.
$465estimated city fees at the inputs above
Line
How it is computed
Amount
Building fee ($5.00 per $1,000)
0.5% of $80,000
$400
Codes tech fee (10%)
10% of $400
$40
Zoning examination fee
flat
$25
The page's own example: “$80,000 in-ground pool: $400 + $40 + $25 = $465.”
Not included: Re-inspections ($50 each); trade permits are priced here at their $75 minimum, the page gives no itemized pool trade fees. The valuation is assumed to be the job's cost; Metro bills new residential structures on valuation figures, so ask the Zoning Help Desk how yours will be valued.
Source: Metro Code fee schedule (building fees; 16.12.220 plumbing, 16.16.400 gas/mechanical, 16.20.250 electrical). Read the Nashville pool permit page, which quotes the rule and records when it was last verified (Nov 2026).
Nashville roof replacement permit fee
A new roofing layer or replacing more than a third of the roof is a building permit at $5.00 per $1,000 of the job's value plus a 10% codes tech fee and a $25 zoning fee; Metro's documents conflict on whether a reroof needs a permit (a 2022 list says no, BL2025-898 drops the 33 percent repair cap), so confirm with the Zoning Help Desk.
$91estimated city fees at the inputs above
Line
How it is computed
Amount
Building fee ($5.00 per $1,000)
0.5% of $12,000
$60
Codes tech fee (10%)
10% of $60
$6
Zoning examination fee
flat
$25
The page's own example: “$12,000 shingle tear-off: $60 + $6 + $25 = $91.”
Not included: Repairs to up to 33 percent of the roof (normal maintenance, though the page notes two Metro documents point the other way); decking over 64 sq ft or any structural member is also a building permit; re-inspections ($50 each); the contractor's permit bond.
Source: Metro Code fee schedule (building fees; 16.12.220 plumbing, 16.16.400 gas/mechanical, 16.20.250 electrical). Read the Nashville roof replacement permit page, which quotes the rule and records when it was last verified (Nov 2026).
Nashville bathroom remodel permit fee
A new shower, moved fixtures or a removed wall need a rehab permit at $5.00 per $1,000 of value plus a 10% tech fee and $25 zoning fee, plus separate trade permits with a $75 minimum each (plumbing fixtures $11 each).
$257.50estimated city fees at the inputs above
Line
How it is computed
Amount
Building fee ($5.00 per $1,000)
0.5% of $15,000
$75
Codes tech fee (10%)
10% of $75
$7.50
Zoning examination fee
flat
$25
Plumbing permit ($11 per fixture, $75 minimum) optional
3 fixtures × $11 (minimum $75)
$75
Electrical permit ($75 minimum) optional
flat
$75
The page's own example: “$15,000 remodel, shower and vanity moved: $75 + $7.50 + $25 = $107.50 building, plus $75 plumbing and $75 electrical = $257.50.”
Not included: A new water heater ($43 on the plumbing permit); re-inspections ($50 each). Tile, flooring, paint and an in-place vanity need no permit. Whether a homeowner may pull the trade permits is unconfirmed: Metro says a licensed subcontractor can obtain them after the building permit, and Permit Issuance answers who may pull them.
Source: Metro Code fee schedule (building fees; 16.12.220 plumbing, 16.16.400 gas/mechanical, 16.20.250 electrical). Read the Nashville bathroom remodel permit page, which quotes the rule and records when it was last verified (Nov 2026).
Nashville kitchen remodel permit fee
Moving outlets, the sink or a wall needs a rehab permit at $5.00 per $1,000 of value plus a 10% tech fee and $25 zoning fee, plus electrical, plumbing and (for a cooktop, countertop unit or exhaust fan) gas/mechanical permits with a $75 minimum each.
$312.50estimated city fees at the inputs above
Line
How it is computed
Amount
Building fee ($5.00 per $1,000)
0.5% of $25,000
$125
Codes tech fee (10%)
10% of $125
$12.50
Zoning examination fee
flat
$25
Electrical permit ($75 minimum) optional
flat
$75
Plumbing permit ($11 per fixture, $75 minimum) optional
1 fixtures × $11 (minimum $75)
$75
The page's own example: “$25,000 remodel, sink and outlets moved: $125 + $12.50 + $25 = $162.50 building, plus $75 electrical and $75 plumbing = $312.50.”
Not included: Electrical work started before a permit is issued costs triple; outlets beyond the first ten (the page gives $6 only for the first ten); re-inspections. Whether a homeowner may pull the trade permits is unconfirmed: Metro says a licensed subcontractor can obtain them after the building permit, and Permit Issuance answers who may pull them.
Source: Metro Code fee schedule (building fees; 16.12.220 plumbing, 16.16.400 gas/mechanical, 16.20.250 electrical). Read the Nashville kitchen remodel permit page, which quotes the rule and records when it was last verified (Nov 2026).
Nashville electrical panel permit fee
A panel swap or service upgrade is a Metro electrical permit itemized at $12 per service meter plus $10 or $20 per panel, raised to the $75 minimum, plus a $75 service release where Permit Issuance charges one.
$75estimated city fees at the inputs above
Line
How it is computed
Amount
Service, new, increased or relocated (per meter)
flat
$12
Panel up to 200 amps
flat
$10
Electrical permit minimum
brings the total up to the $75 minimum
$53
The page's own example: “200-amp panel and service upgrade: $12 + $10 = $22, which is below the minimum, so the permit is $75.”
Not included: Re-inspections ($50 each); work started before the permit triples the electrical permit fees; the smoke alarms Metro requires with a service upgrade. Whether a homeowner may permit their own panel work is a question for Permit Issuance.
An AC, heat pump or furnace replacement is a gas/mechanical permit: $11 for each appliance beyond the first plus $32 per 100,000 Btuh or fraction of total input, with a $75 minimum.
$75estimated city fees at the inputs above
Line
How it is computed
Amount
Appliances beyond the first
1 units × $11 (first 1 units free)
$11
Capacity ($32 per 100,000 Btuh or fraction)
2 × $32 per 100,000 Btuh or fraction
$64
The page's own example: “Gas furnace (80,000 Btuh) and 3-ton AC condenser (36,000 Btuh): one extra appliance at $11 plus 116,000 Btuh rounded up to two blocks at $32 = $75, which is also the minimum: $75.”
Not included: Gas items ($11 gas meter connection, $50 underground fuel piping); a separate electrical permit for a new circuit or disconnect ($75 minimum); re-inspections ($50 each).
Source: Metro Code Section 16.16.400 gas/mechanical fee schedule. Read the Nashville hvac permit page, which quotes the rule and records when it was last verified (Nov 2026).
Nashville adu permit fee
A DADU's building permit is $5.00 per $1,000 of valuation plus a 10% codes tech fee and the $25 zoning fee, with three trade permits at $75 or more; the valuation of $169.09 per sq ft is the page's assumption from the ICC table, which Metro does not confirm for DADUs.
The page's own example: “700 sq ft DADU: 700 × $169.09 = $118,363 valuation; $591.82 + $59.18 + $25 = $676.00, plus electrical, plumbing and gas/mechanical permits at a $75 minimum each = $901.00.”
Not included: The valuation is an assumption Metro does not confirm for DADUs (ask the Zoning Help Desk how yours will be valued); trade fees above the minimums, water and sewer connections ($80 each) and Metro Water Services' fees.
Source: Metro fee schedule; valuation assumed from the ICC building valuation table (R-3, type VB). Read the Nashville adu permit page, which quotes the rule and records when it was last verified (Nov 2026).
What the estimate covers
City fees only, on the ordinary residential path each page prices: the building or trade permit plus the mandatory lines the city adds to it. It leaves out whatever the page says is separate (a designer's fee, a contractor's licence, a utility connection) and anything the page does not price. Fee schedules change on the city's budget cycle; the month each page was last verified is Nov 2026, and the verification method explains how changes are caught.
Frequently asked questions
$4,000 prefab shed: $20 building fee + $2 tech fee + $25 zoning fee = $47.. A storage building of 100 sq ft or more needs a residential building permit at $5.00 per $1,000 of value, a 10% codes tech fee and a $25 zoning examination fee; Metro does not say a smaller shed is exempt, so ask the Zoning Help Desk.
$10,000 deck: $50 building fee + $5 tech fee + $25 zoning fee = $80.. Every new or replacement deck is a residential building permit at $5.00 per $1,000 of value plus a 10% codes tech fee and a $25 zoning examination fee.
$80,000 in-ground pool: $400 + $40 + $25 = $465.. Every above- or in-ground pool is a residential building permit at $5.00 per $1,000 of value plus a 10% codes tech fee and a $25 zoning fee; electrical, plumbing and gas heater permits are separate, each with a $75 minimum.
$12,000 shingle tear-off: $60 + $6 + $25 = $91.. A new roofing layer or replacing more than a third of the roof is a building permit at $5.00 per $1,000 of the job's value plus a 10% codes tech fee and a $25 zoning fee; Metro's documents conflict on whether a reroof needs a permit (a 2022 list says no, BL2025-898 drops the 33 percent repair cap), so confirm with the Zoning Help Desk.
$15,000 remodel, shower and vanity moved: $75 + $7.50 + $25 = $107.50 building, plus $75 plumbing and $75 electrical = $257.50.. A new shower, moved fixtures or a removed wall need a rehab permit at $5.00 per $1,000 of value plus a 10% tech fee and $25 zoning fee, plus separate trade permits with a $75 minimum each (plumbing fixtures $11 each).
Every line is read off the Nashville permit pages on this site, which quote the city's own fee schedule, bulletin or ordinance and record the month the sources were last verified (Nov 2026). The calculator holds no fee of its own.