City fee lines from the Jacksonville permit pages, computed for your project. Sourced, verified Oct 2026.
Verified Oct 2026Calculator
This calculator applies the fee lines quoted on the Jacksonville permit pages: the city's own plan review, permit and surcharge figures, as published by the City of Jacksonville Public Works, Building Inspection Division. Pick a project, change the inputs, and the breakdown shows each line and how it is computed. 10 of 10 project types have a computable formula on their page; the rest show the page's own figure.
Fees come from Ordinance Code Section 320.409: BID, resource management, Development Services and debris lines per unit of area, cost or gallons, with minimums that usually set the total.
Florida's 1 percent and 1.5 percent building-code surcharges (each with a $2 minimum) apply on top and are not modeled.
Jacksonville shed permit fee
Every shed needs a permit; one of 150 sq ft or less (and under $5,000) pays a flat small-shed line, a larger one pays the BID, Development Services, debris and plan review minimums.
$85estimated city fees at the inputs above
Line
How it is computed
Amount
BID fee
$45
$45
Development Services fee
$15
$15
C&D debris fee
flat
$25
Plan review (larger sheds)
$NaN
$0
The page's own example: “Small shed, no final inspection (not over 150 square feet and $5,000): $45 + $15 + $25 = $85.”
Not included: The $125 one-inspection line for a small shed on a new slab; per-inspection BID minimums above three inspections; Florida's 1 percent and 1.5 percent building-code surcharges on permit fees; trade permits for wiring or plumbing.
Source: Ordinance Code Section 320.409, accessory-structure lines. Read the Jacksonville shed permit page, which quotes the rule and records when it was last verified (Oct 2026).
Jacksonville fence permit fee
Ordinary wood, vinyl and chain-link fences need no permit; a masonry or retaining wall is priced per $1,000 of cost under subsection (4), where the minimums usually decide the total.
$260.70estimated city fees at the inputs above
Line
How it is computed
Amount
BID fee
6 × $1.88 per 1,000 $ or fraction (minimum $112.50)
$112.50
Resource management
6 × $0.30 per 1,000 $ or fraction
$1.80
Landscape fee
12% of $112.50
$13.50
Development Services
6 × $0.63 per 1,000 $ or fraction (minimum $37.50)
$37.50
C&D debris
6 × $0.90 per 1,000 $ or fraction
$5.40
Plan review
67% of $112.50 (minimum $90)
$90
The page's own example: “A $6,000 block wall works out to $112.50 + $1.80 + $13.50 + $37.50 + $5.40 + $90 = about $261.”
Not included: Ordinary fences ($0, no permit); the $966 administrative deviation for a taller fence; Florida's 1 percent and 1.5 percent building-code surcharges on permit fees.
Source: Ordinance Code Section 320.409, subsection (4). Read the Jacksonville fence permit page, which quotes the rule and records when it was last verified (Oct 2026).
Jacksonville deck permit fee
Every deck needs a permit; it is priced per 100 sq ft of unenclosed area, but the BID, Development Services and plan review minimums set most of the total.
$280.23estimated city fees at the inputs above
Line
How it is computed
Amount
BID permit fee
3 × $0.75 per 100 sq ft or fraction (minimum $112.50)
$112.50
Resource management
3 × $0.16 per 100 sq ft or fraction
$0.48
Landscape fee (attached deck) optional
12% of $112.50
$13.50
Development Services
3 × $0.25 per 100 sq ft or fraction (minimum $37.50)
$37.50
C&D debris (residential rate)
3 × $8.75 per 100 sq ft or fraction
$26.25
Plan review
67% of $112.50 (minimum $90)
$90
The page's own example: “300 sq ft deck attached to the house: $112.50 BID + $0.48 resource + $13.50 landscape + $37.50 Development Services + $26.25 debris + $90 plan review = $280.23.”
Not included: Freestanding decks skip the landscape fee (untick it: $266.73 for 300 sq ft); per-inspection BID minimum at four or more inspections; electrical permit for lights; Florida's 1 percent and 1.5 percent building-code surcharges on permit fees.
Source: Ordinance Code Section 320.409, unenclosed area. Read the Jacksonville deck permit page, which quotes the rule and records when it was last verified (Oct 2026).
Jacksonville pool permit fee
An in-ground pool is billed per 1,000 gallons with BID, Development Services and plan review minimums plus a flat debris fee, and a separate $120 electrical permit.
$272.50estimated city fees at the inputs above
Line
How it is computed
Amount
BID permit fee
15 × $1.50 per 1,000 gallons or fraction (minimum $45)
$45
Resource management
15 × $0.50 per 1,000 gallons or fraction
$7.50
Development Services
15 × $0.50 per 1,000 gallons or fraction (minimum $15)
$15
C&D debris fee
flat
$25
Plan review
67% of $45 (minimum $60)
$60
Electrical permit, in-ground pool optional
flat
$120
The page's own example: “15,000-gallon pool: $45 BID (minimum) + $7.50 resource + $15 Development Services + $25 debris + $60 plan review = $152.50, plus $120 electrical = $272.50.”
Not included: Above-ground pools use a flat line ($75 + $25, plus $60 electrical = $160); a gas heater's mechanical permit; the landscape fee, from which single-family accessory structures are exempt; Florida's 1 percent and 1.5 percent building-code surcharges on permit fees.
Source: Ordinance Code Section 320.409, swimming pools. Read the Jacksonville pool permit page, which quotes the rule and records when it was last verified (Oct 2026).
Jacksonville roof replacement permit fee
A full reroof is $10 per 1,000 sq ft of roof with a $150 minimum when inspected ($80 for a small no-inspection reroof, $10 for a repair under 500 sq ft), plus a $17.50 debris fee.
$167.50estimated city fees at the inputs above
Line
How it is computed
Amount
BID roofing fee, inspected reroof
3 × $10 per 1,000 sq ft or fraction (minimum $150)
$150
C&D debris fee
flat
$17.50
The page's own example: “Full reroof of a 2,400 sq ft roof: 3 × $10 = $30, so the $150 minimum applies. $150 + $17.50 = $167.50.”
Not included: Florida's 1 percent and 1.5 percent building-code surcharges on permit fees; the Notice of Commencement recording for jobs over $5,000.
A remodel is an alteration charged per $1,000 of estimated cost with a $112.50 BID minimum and plan review, plus separate plumbing and electrical permits at a $60 minimum each.
$359.63estimated city fees at the inputs above
Line
How it is computed
Amount
BID fee
15 × $3 per 1,000 $ or fraction (minimum $112.50)
$112.50
Resource management
15 × $0.65 per 1,000 $ or fraction
$9.75
Landscape fee
12% of $112.50
$13.50
Development Services
15 × $1 per 1,000 $ or fraction
$15
C&D debris
15 × $0.90 per 1,000 $ or fraction
$13.50
Plan review
67% of $112.50
$75.38
Plumbing permit optional
3 fixtures × $11 (minimum $60)
$60
Electrical permit (minimum) optional
flat
$60
The page's own example: “Add the plumbing permit (3 × $11 = $33, so the $60 minimum) and an electrical permit at $60 for $359.63.”
Not included: Mechanical permits and the $80 gas piping line; single-trade jobs without a building permit ($60); Florida's 1 percent and 1.5 percent building-code surcharges on permit fees.
A remodel is an alteration charged per $1,000 of estimated cost with a $112.50 BID minimum and plan review, plus separate plumbing and electrical permits at a $60 minimum each.
$397.88estimated city fees at the inputs above
Line
How it is computed
Amount
BID fee
30 × $3 per 1,000 $ or fraction (minimum $112.50)
$112.50
Resource management
30 × $0.65 per 1,000 $ or fraction
$19.50
Landscape fee
12% of $112.50
$13.50
Development Services
30 × $1 per 1,000 $ or fraction
$30
C&D debris
30 × $0.90 per 1,000 $ or fraction
$27
Plan review
67% of $112.50
$75.38
Plumbing permit optional
3 fixtures × $11 (minimum $60)
$60
Electrical permit (minimum) optional
flat
$60
The page's own example: “With minimum plumbing and electrical permits ($60 each), the total is $397.88.”
Not included: Mechanical permits and the $80 gas piping line; single-trade jobs without a building permit ($60); Florida's 1 percent and 1.5 percent building-code surcharges on permit fees.
Electrical service permits are flat by amperage under the Residential Service Charge lines: $80 to 100 amps, $100 for 101-200 amps, and $20 per additional 50 amps.
$100estimated city fees at the inputs above
Line
How it is computed
Amount
Residential service charge
$100
$100
The page's own example: “101-200 amp service: $100. That covers the common upgrade to 200 amps.”
Not included: Reinspection fees ($45); Florida's 1 percent and 1.5 percent building-code surcharges on permit fees.
Source: Ordinance Code Section 320.409, electrical Residential Service Charge. Read the Jacksonville electrical panel permit page, which quotes the rule and records when it was last verified (Oct 2026).
Jacksonville hvac permit fee
Mechanical permits are itemized: $11 per ton of air conditioning, $22 per furnace, $17 per duct system and $80 for gas piping, with a $60 minimum.
$60estimated city fees at the inputs above
Line
How it is computed
Amount
Air conditioning
3 tons × $11
$33
Minimum mechanical permit
brings the total up to the $60 minimum
$27
The page's own example: “3-ton heat pump change-out: 3 × $11 = $33, so the $60 minimum applies.”
Not included: Reinspection fees ($45); Florida's 1 percent and 1.5 percent building-code surcharges on permit fees.
Source: Ordinance Code Section 320.409, mechanical fees. Read the Jacksonville hvac permit page, which quotes the rule and records when it was last verified (Oct 2026).
Jacksonville adu permit fee
A new ADU is an accessory building priced per 100 sq ft of enclosed area, where the BID and Development Services minimums (raised per required inspection) govern, plus plan review and trade permits.
$528.10estimated city fees at the inputs above
Line
How it is computed
Amount
BID fee
3 units × $33.75 (minimum $112.50)
$112.50
Resource management
6 × $1.60 per 100 sq ft or fraction
$9.60
Development Services
3 units × $11.25 (minimum $37.50)
$37.50
C&D debris
6 × $8.75 per 100 sq ft or fraction
$52.50
Plan review
67% of $112.50 (minimum $90)
$90
Electrical permit (room-addition line)
flat
$100
Plumbing permit optional
6 fixtures × $11
$66
Mechanical permit (minimum) optional
flat
$60
The page's own example: “Add electrical $100, plumbing $66 (six fixtures) and mechanical $60 for $528.10.”
Not included: JEA water and sewer charges, mobility fees and the $28 De Minimis Concurrency and Mobility Fee Review; Florida's 1 percent and 1.5 percent building-code surcharges on permit fees.
Source: Ordinance Code Section 320.409, subsection (1), accessory buildings. Read the Jacksonville adu permit page, which quotes the rule and records when it was last verified (Oct 2026).
What the estimate covers
City fees only, on the ordinary residential path each page prices: the building or trade permit plus the mandatory lines the city adds to it. It leaves out whatever the page says is separate (a designer's fee, a contractor's licence, a utility connection) and anything the page does not price. Fee schedules change on the city's budget cycle; the month each page was last verified is Oct 2026, and the verification method explains how changes are caught.
Frequently asked questions
Small shed, no final inspection (not over 150 square feet and $5,000): $45 + $15 + $25 = $85.. Every shed needs a permit; one of 150 sq ft or less (and under $5,000) pays a flat small-shed line, a larger one pays the BID, Development Services, debris and plan review minimums.
A $6,000 block wall works out to $112.50 + $1.80 + $13.50 + $37.50 + $5.40 + $90 = about $261.. Ordinary wood, vinyl and chain-link fences need no permit; a masonry or retaining wall is priced per $1,000 of cost under subsection (4), where the minimums usually decide the total.
300 sq ft deck attached to the house: $112.50 BID + $0.48 resource + $13.50 landscape + $37.50 Development Services + $26.25 debris + $90 plan review = $280.23.. Every deck needs a permit; it is priced per 100 sq ft of unenclosed area, but the BID, Development Services and plan review minimums set most of the total.
15,000-gallon pool: $45 BID (minimum) + $7.50 resource + $15 Development Services + $25 debris + $60 plan review = $152.50, plus $120 electrical = $272.50.. An in-ground pool is billed per 1,000 gallons with BID, Development Services and plan review minimums plus a flat debris fee, and a separate $120 electrical permit.
Full reroof of a 2,400 sq ft roof: 3 × $10 = $30, so the $150 minimum applies. $150 + $17.50 = $167.50.. A full reroof is $10 per 1,000 sq ft of roof with a $150 minimum when inspected ($80 for a small no-inspection reroof, $10 for a repair under 500 sq ft), plus a $17.50 debris fee.
Every line is read off the Jacksonville permit pages on this site, which quote the city's own fee schedule, bulletin or ordinance and record the month the sources were last verified (Oct 2026). The calculator holds no fee of its own.