Jacksonville Permit Fee Calculator

City fee lines from the Jacksonville permit pages, computed for your project. Sourced, verified Oct 2026.

Verified Oct 2026Calculator

This calculator applies the fee lines quoted on the Jacksonville permit pages: the city's own plan review, permit and surcharge figures, as published by the City of Jacksonville Public Works, Building Inspection Division. Pick a project, change the inputs, and the breakdown shows each line and how it is computed. 10 of 10 project types have a computable formula on their page; the rest show the page's own figure.

  • Fees come from Ordinance Code Section 320.409: BID, resource management, Development Services and debris lines per unit of area, cost or gallons, with minimums that usually set the total.
  • Florida's 1 percent and 1.5 percent building-code surcharges (each with a $2 minimum) apply on top and are not modeled.

What the estimate covers

City fees only, on the ordinary residential path each page prices: the building or trade permit plus the mandatory lines the city adds to it. It leaves out whatever the page says is separate (a designer's fee, a contractor's licence, a utility connection) and anything the page does not price. Fee schedules change on the city's budget cycle; the month each page was last verified is Oct 2026, and the verification method explains how changes are caught.

Frequently asked questions

Small shed, no final inspection (not over 150 square feet and $5,000): $45 + $15 + $25 = $85.. Every shed needs a permit; one of 150 sq ft or less (and under $5,000) pays a flat small-shed line, a larger one pays the BID, Development Services, debris and plan review minimums.
A $6,000 block wall works out to $112.50 + $1.80 + $13.50 + $37.50 + $5.40 + $90 = about $261.. Ordinary wood, vinyl and chain-link fences need no permit; a masonry or retaining wall is priced per $1,000 of cost under subsection (4), where the minimums usually decide the total.
300 sq ft deck attached to the house: $112.50 BID + $0.48 resource + $13.50 landscape + $37.50 Development Services + $26.25 debris + $90 plan review = $280.23.. Every deck needs a permit; it is priced per 100 sq ft of unenclosed area, but the BID, Development Services and plan review minimums set most of the total.
15,000-gallon pool: $45 BID (minimum) + $7.50 resource + $15 Development Services + $25 debris + $60 plan review = $152.50, plus $120 electrical = $272.50.. An in-ground pool is billed per 1,000 gallons with BID, Development Services and plan review minimums plus a flat debris fee, and a separate $120 electrical permit.
Full reroof of a 2,400 sq ft roof: 3 × $10 = $30, so the $150 minimum applies. $150 + $17.50 = $167.50.. A full reroof is $10 per 1,000 sq ft of roof with a $150 minimum when inspected ($80 for a small no-inspection reroof, $10 for a repair under 500 sq ft), plus a $17.50 debris fee.
Every line is read off the Jacksonville permit pages on this site, which quote the city's own fee schedule, bulletin or ordinance and record the month the sources were last verified (Oct 2026). The calculator holds no fee of its own.

Other city calculators

Related: All cities · Research: fees compared across 30 cities · Jacksonville permit guide

Stay up to date
Get notified when we add new cities or update permit fees.