This calculator applies the fee lines quoted on the Seattle permit pages: the city's own plan review, permit and surcharge figures, as published by the Seattle Dept. of Construction & Inspections. Pick a project, change the inputs, and the breakdown shows each line and how it is computed. 9 of 10 project types have a computable formula on their page; the rest show the page's own figure.
- SDCI construction permits are value-based through Table D-1 of the 2026 Fee Subtitle (the Development Fee Index); for new structures SDCI sets the value from its own valuation table (Director's Rule 5-2025), not the contractor's bid.
- STFI permits pay 100 percent of the index plus 40 percent plan review (minimum $116.75), then a 5 percent technology fee and the $6.50 state surcharge; plumbing and gas permits come from Public Health Seattle and King County ($137 plus $27 per fixture or outlet).
- Table D-1 is stated on the pages only in pieces: $325 for the first $1,000, $1.60 per $100 to $25,000, $709 plus $1.55 per $100 from $25,000 (shown to $40,000), and isolated rows at $75,000 and $175,000; the calculator stops at $40,000 of value.
Seattle shed permit fee
Sheds with a projected roof area of 120 sq ft or less need no permit; a larger shed gets a value-based STFI permit from Table D-1 on SDCI's $72.18 per sq ft valuation, plus 40 percent plan review, 5 percent technology fee and the $6.50 state surcharge.
| Line | How it is computed | Amount |
|---|---|---|
| Permit fee (Development Fee Index) | $325 + 129 × $1.60 per 100 above 1,000 | $531.40 |
| STFI plan review (40%) | 40% of $531.40 | $212.56 |
| Technology fee (5%) | 5% of $743.96 | $37.20 |
| State surcharge | flat | $6.50 |
Seattle fence permit fee
Fences up to 8 ft with no masonry above 6 ft need no permit; a taller fence gets a value-based STFI permit from Table D-1, plus 40 percent plan review, 5 percent technology fee and the $6.50 state surcharge.
| Line | How it is computed | Amount |
|---|---|---|
| Permit fee (Development Fee Index) | $325 + 50 × $1.60 per 100 above 1,000 | $405 |
| STFI plan review (40%) | 40% of $405 | $162 |
| Technology fee (5%) | 5% of $567 | $28.35 |
| State surcharge | flat | $6.50 |
Seattle deck permit fee
Decks more than 18 in above the ground usually get a value-based STFI permit from Table D-1 on SDCI's $36.09 per sq ft deck valuation, plus 40 percent plan review, 5 percent technology fee and the $6.50 state surcharge.
| Line | How it is computed | Amount |
|---|---|---|
| Permit fee (Development Fee Index) | $325 + 60 × $1.60 per 100 above 1,000 | $421 |
| STFI plan review (40%) | 40% of $421 | $168.40 |
| Technology fee (5%) | 5% of $589.40 | $29.47 |
| State surcharge | flat | $6.50 |
Seattle pool permit fee
An in-ground pool at a house pays a flat 4 times the $292 base fee plus 5 percent technology fee and the $6.50 state surcharge, plus an SDCI electrical permit and a Public Health plumbing permit.
| Line | How it is computed | Amount |
|---|---|---|
| Building permit, in-ground pool (4 x base fee) | flat × 4 | $1,168 |
| Building technology fee (5%) | 5% of $1,168 | $58.40 |
| State surcharge | flat | $6.50 |
| Electrical: 30-50 amp circuit optional | flat | $43.80 |
| Electrical: pump motor optional | flat | $32.12 |
| Electrical administrative fee optional | flat | $55.48 |
| Electrical technology fee (5%) optional | 5% of $131.40 | $6.57 |
| Public Health plumbing permit optional | flat | $137 |
| Plumbing fixtures optional | 2 fixtures × $27 | $54 |
Seattle roof replacement permit fee
A house re-roof with the envelope unchanged needs no permit; replacing sheathing makes it a value-based STFI construction permit from Table D-1, plus 40 percent plan review, 5 percent technology fee and the $6.50 state surcharge.
| Line | How it is computed | Amount |
|---|---|---|
| Permit fee (Development Fee Index) | $325 + 170 × $1.60 per 100 above 1,000 | $597 |
| STFI plan review (40%) | 40% of $597 | $238.80 |
| Technology fee (5%) | 5% of $835.80 | $41.79 |
| State surcharge | flat | $6.50 |
Seattle bathroom remodel permit fee
Surface work needs no permit; a layout change over $6,000 takes a value-based STFI permit, plus a Public Health plumbing permit ($137 plus $27 per fixture) and an SDCI electrical permit for new circuits.
| Line | How it is computed | Amount |
|---|---|---|
| Permit fee (Development Fee Index) | $325 + 190 × $1.60 per 100 above 1,000 | $629 |
| STFI plan review (40%) | 40% of $629 | $251.60 |
| Technology fee (5%) | 5% of $880.60 | $44.03 |
| State surcharge | flat | $6.50 |
| Public Health plumbing permit optional | flat | $137 |
| Plumbing fixtures optional | 3 fixtures × $27 | $81 |
| Electrical permit (circuits, $105.12 minimum) optional | 2 circuits × $26.28 (minimum $105.12) | $105.12 |
| Electrical administrative fee optional | flat | $55.48 |
| Electrical technology fee (5%) optional | 5% of $160.60 | $8.03 |
Seattle kitchen remodel permit fee
Same-layout cabinets and finishes need no permit; a layout change over $6,000 takes a value-based STFI permit, plus a Public Health plumbing permit ($137 plus $27 per fixture) and an SDCI electrical permit for new circuits.
| Line | How it is computed | Amount |
|---|---|---|
| Permit fee (Development Fee Index) | $709 + 50 × $1.55 per 100 above 25,000 | $786.50 |
| STFI plan review (40%) | 40% of $786.50 | $314.60 |
| Technology fee (5%) | 5% of $1,101.10 | $55.06 |
| State surcharge | flat | $6.50 |
| Public Health plumbing permit optional | flat | $137 |
| Plumbing fixtures optional | 2 fixtures × $27 | $54 |
| Electrical permit (circuits, $105.12 minimum) optional | 4 circuits × $26.28 | $105.12 |
| Electrical administrative fee optional | flat | $55.48 |
| Electrical technology fee (5%) optional | 5% of $160.60 | $8.03 |
Seattle electrical panel permit fee
A panel or service change is a flat online electrical permit by service size ($146 up to 125 A, $292 for 150-200 A, $365 for 225-350 A), plus a $55.48 administrative fee and the 5 percent technology fee.
| Line | How it is computed | Amount |
|---|---|---|
| Service fee by amperage | $292 | $292 |
| Administrative fee | flat | $55.48 |
| Technology fee (5%) | 5% of $347.48 | $17.37 |
Seattle hvac permit fee
A furnace or heat pump needs an SDCI mechanical permit at $60.35 per unit plus 5 percent; a new circuit adds an SDCI electrical permit and new gas piping a Public Health gas permit.
| Line | How it is computed | Amount |
|---|---|---|
| Mechanical permit per unit | 1 units × $60.35 | $60.35 |
| Mechanical technology fee (5%) | 5% of $60.35 | $3.02 |
Seattle adu permit fee
Every ADU needs an addition/alteration permit with plan review; permit and plan review fees are each 100 percent of the Table D-1 index on SDCI's $186.29 per sq ft valuation, plus 5 percent technology fee and the $6.50 state surcharge.
What the city page states: SDCI's own 2026 example is a 500 sq ft DADU valued at $93,145 paying $3,453 in plan review and permit fees
What the estimate covers
City fees only, on the ordinary residential path each page prices: the building or trade permit plus the mandatory lines the city adds to it. It leaves out whatever the page says is separate (a designer's fee, a contractor's licence, a utility connection) and anything the page does not price. Fee schedules change on the city's budget cycle; the month each page was last verified is Sep 2026, and the verification method explains how changes are caught.
Frequently asked questions
Other city calculators
- Albuquerque, NM
- Baltimore, MD
- Charlotte, NC
- Chicago, IL
- Cincinnati, OH
- Dallas, TX
- Fort Worth, TX
- Houston, TX
- Indianapolis, IN
- Jacksonville, FL
- Kansas City, MO
- Long Beach, CA
- Los Angeles, CA
- Louisville, KY
- Miami, FL
- Milwaukee, WI
- Minneapolis, MN
- New York City, NY
- Philadelphia, PA
- Phoenix, AZ
- Pittsburgh, PA
- Portland, OR
- Sacramento, CA
- San Antonio, TX
- San Diego, CA
- San Francisco, CA
- San Jose, CA
- St. Louis, MO
- Tucson, AZ
Related: All cities · Research: fees compared across 30 cities · Seattle permit guide