This calculator applies the fee lines quoted on the Miami permit pages: the city's own plan review, permit and surcharge figures, as published by the City of Miami Building Dept.. Pick a project, change the inputs, and the breakdown shows each line and how it is computed. 10 of 10 project types have a computable formula on their page; the rest show the page's own figure.
- Every residential permit, master or trade, is 0.5% of its scope's estimated cost with a $110 minimum (a flat $45 under $2,500), plus a $40 application fee and state surcharges of 1% and 1.5% (at least $2 each).
- Master permits pay the solid waste surcharge ($0.22 per $100, $26 minimum, $600 maximum); trade permits, roofing and sheds do not.
- The up-front fee of $2.80 per $1,000 collected at filing is 80% credited to the permit fee, and a Miami-Dade County code-compliance surcharge of unstated rate applies; neither is modeled.
Miami shed permit fee
Every shed needs a building permit at 0.5% of cost with a $110 minimum, plus the $40 application fee and two state surcharges; sheds skip the solid waste surcharge.
| Line | How it is computed | Amount |
|---|---|---|
| Permit fee (0.5% of cost) | 0.5% of $6,000 (minimum $110) | $110 |
| Application fee | flat | $40 |
| State DBPR surcharge (1%) | 1% of $110 (minimum $2) | $2 |
| State BCAI surcharge (1.5%) | 1.5% of $110 (minimum $2) | $2 |
Miami fence permit fee
Every fence needs a building permit at 0.5% of cost with a $110 minimum, plus the $40 application fee, the solid waste surcharge and two state surcharges.
| Line | How it is computed | Amount |
|---|---|---|
| Permit fee (0.5% of cost) | 0.5% of $6,000 (minimum $110) | $110 |
| Application fee | flat | $40 |
| Solid waste surcharge | 60 × $0.22 per 100 $ or fraction (minimum $26) | $26 |
| State DBPR surcharge (1%) | 1% of $110 (minimum $2) | $2 |
| State BCAI surcharge (1.5%) | 1.5% of $110 (minimum $2) | $2 |
Miami deck permit fee
Every deck needs a building permit at 0.5% of cost with a $110 minimum, plus the $40 application fee, the solid waste surcharge and two state surcharges.
| Line | How it is computed | Amount |
|---|---|---|
| Permit fee (0.5% of cost) | 0.5% of $12,000 (minimum $110) | $110 |
| Application fee | flat | $40 |
| Solid waste surcharge | 120 × $0.22 per 100 $ or fraction | $26.40 |
| State DBPR surcharge (1%) | 1% of $110 (minimum $2) | $2 |
| State BCAI surcharge (1.5%) | 1.5% of $110 (minimum $2) | $2 |
Miami pool permit fee
An in-ground pool is a master building permit at 0.5% of cost (with the solid waste and state surcharges) plus electrical and plumbing trade permits at $154 each at the minimum.
| Line | How it is computed | Amount |
|---|---|---|
| Permit fee (0.5% of cost) | 0.5% of $60,000 | $300 |
| Application fee | flat | $40 |
| Solid waste surcharge | 600 × $0.22 per 100 $ or fraction | $132 |
| State DBPR surcharge (1%) | 1% of $300 | $3 |
| State BCAI surcharge (1.5%) | 1.5% of $300 | $4.50 |
| Electrical trade permit (at the $110 minimum) optional | flat | $154 |
| Plumbing trade permit (at the $110 minimum) optional | flat | $154 |
Miami roof replacement permit fee
A reroof is a permit at 0.5% of cost with a $110 minimum plus the $40 application fee and two state surcharges; roofing is exempt from the solid waste surcharge.
| Line | How it is computed | Amount |
|---|---|---|
| Permit fee (0.5% of cost) | 0.5% of $20,000 (minimum $110) | $110 |
| Application fee | flat | $40 |
| State DBPR surcharge (1%) | 1% of $110 (minimum $2) | $2 |
| State BCAI surcharge (1.5%) | 1.5% of $110 (minimum $2) | $2 |
Miami bathroom remodel permit fee
Cosmetic work is exempt; a remodel that opens a wall is a master building permit at 0.5% of cost with solid waste and state surcharges, plus plumbing and electrical trade permits at $154 each at the minimum.
| Line | How it is computed | Amount |
|---|---|---|
| Permit fee (0.5% of cost) | 0.5% of $20,000 (minimum $110) | $110 |
| Application fee | flat | $40 |
| Solid waste surcharge | 200 × $0.22 per 100 $ or fraction | $44 |
| State DBPR surcharge (1%) | 1% of $110 (minimum $2) | $2 |
| State BCAI surcharge (1.5%) | 1.5% of $110 (minimum $2) | $2 |
| Plumbing trade permit (at the $110 minimum) optional | flat | $154 |
| Electrical trade permit (at the $110 minimum) optional | flat | $154 |
Miami kitchen remodel permit fee
Cosmetic work is exempt; a remodel that opens a wall is a master building permit at 0.5% of cost with solid waste and state surcharges, plus plumbing and electrical trade permits at $154 each at the minimum.
| Line | How it is computed | Amount |
|---|---|---|
| Permit fee (0.5% of cost) | 0.5% of $30,000 | $150 |
| Application fee | flat | $40 |
| Solid waste surcharge | 300 × $0.22 per 100 $ or fraction | $66 |
| State DBPR surcharge (1%) | 1% of $150 (minimum $2) | $2 |
| State BCAI surcharge (1.5%) | 1.5% of $150 | $2.25 |
| Plumbing trade permit (at the $110 minimum) optional | flat | $154 |
| Electrical trade permit (at the $110 minimum) optional | flat | $154 |
Miami electrical panel permit fee
A panel or service change is a stand-alone electrical permit: a fixed $45 under $2,500, otherwise the $110 minimum, plus the $40 application fee, solid waste and state surcharges.
| Line | How it is computed | Amount |
|---|---|---|
| Permit fee | $45 | $45 |
| Application fee | flat | $40 |
| Solid waste surcharge | 20 × $0.22 per 100 $ or fraction (minimum $26) | $26 |
| State DBPR surcharge (1%) | 1% of $45 (minimum $2) | $2 |
| State BCAI surcharge (1.5%) | 1.5% of $45 (minimum $2) | $2 |
Miami hvac permit fee
Mechanical contracts up to $2,500 are exempt; a system change-out above that is a mechanical permit at 0.5% of cost with a $110 minimum plus the application fee and surcharges.
| Line | How it is computed | Amount |
|---|---|---|
| Permit fee (0.5% of cost) | 0.5% of $9,000 (minimum $110) | $110 |
| Application fee | flat | $40 |
| Solid waste surcharge | 90 × $0.22 per 100 $ or fraction (minimum $26) | $26 |
| State DBPR surcharge (1%) | 1% of $110 (minimum $2) | $2 |
| State BCAI surcharge (1.5%) | 1.5% of $110 (minimum $2) | $2 |
Miami adu permit fee
An ADU pays a master building permit at 0.5% of cost with solid waste, energy and state surcharges, three trade permits and a $105 certificate of occupancy; city and county impact fees come on top.
| Line | How it is computed | Amount |
|---|---|---|
| Permit fee (0.5% of cost) | 0.5% of $150,000 | $750 |
| Application fee | flat | $40 |
| Solid waste surcharge | 1,500 × $0.22 per 100 $ or fraction | $330 |
| Energy conservation surcharge | 600 sq ft × $0.11 | $66 |
| State DBPR surcharge (1%) | 1% of $750 | $7.50 |
| State BCAI surcharge (1.5%) | 1.5% of $750 | $11.25 |
| Electrical trade permit optional | flat | $154 |
| Plumbing trade permit optional | flat | $154 |
| Mechanical trade permit optional | flat | $154 |
| Certificate of occupancy | flat | $105 |
What the estimate covers
City fees only, on the ordinary residential path each page prices: the building or trade permit plus the mandatory lines the city adds to it. It leaves out whatever the page says is separate (a designer's fee, a contractor's licence, a utility connection) and anything the page does not price. Fee schedules change on the city's budget cycle; the month each page was last verified is Oct 2026, and the verification method explains how changes are caught.
Frequently asked questions
Other city calculators
- Albuquerque, NM
- Baltimore, MD
- Charlotte, NC
- Chicago, IL
- Cincinnati, OH
- Dallas, TX
- Fort Worth, TX
- Houston, TX
- Indianapolis, IN
- Jacksonville, FL
- Kansas City, MO
- Long Beach, CA
- Los Angeles, CA
- Louisville, KY
- Milwaukee, WI
- Minneapolis, MN
- New York City, NY
- Philadelphia, PA
- Phoenix, AZ
- Pittsburgh, PA
- Portland, OR
- Sacramento, CA
- San Antonio, TX
- San Diego, CA
- San Francisco, CA
- San Jose, CA
- Seattle, WA
- St. Louis, MO
- Tucson, AZ
Related: All cities · Research: fees compared across 30 cities · Miami permit guide