City fee lines from the Minneapolis permit pages, computed for your project. Sourced, verified Oct 2026.
Verified Oct 2026Calculator
This calculator applies the fee lines quoted on the Minneapolis permit pages: the city's own plan review, permit and surcharge figures, as published by the City of Minneapolis Community Planning and Economic Development. Pick a project, change the inputs, and the breakdown shows each line and how it is computed. 10 of 10 project types have a computable formula on their page; the rest show the page's own figure.
Building permits are valuation-based (labor and materials), plus a plan review fee of 65% of the permit fee when plans are reviewed and a state surcharge of 0.0005 times the value.
Electrical permits are issued by the Minnesota Department of Labor and Industry (DLI), not the city.
Minneapolis shed permit fee
A shed over 200 sq ft, or two stories, pays the valuation-based building permit ($104.20 for the first $2,000 plus $20.60 per additional $1,000), 65% plan review when plans are reviewed, and the state surcharge.
Exempt: No building permit for a one-story shed of 200 sq ft or less (Minnesota Rules 1300.0120); zoning still applies.
$310.89estimated city fees at the inputs above
Line
How it is computed
Amount
Building permit fee
$104.20 + 4 × $20.60 per 1,000 above 2,000
$186.60
Plan review (65% of permit fee) optional
65% of $186.60
$121.29
State surcharge (0.0005 x value)
6,000 $ × $0
$3
The page's own example: “A 240 sq ft shed valued at $6,000 works out to $104.20 + 4 x $20.60 = $186.60, plan review $121.29 and surcharge $3.00, for $310.89.”
Not included: A DLI electrical permit for any wiring; a $240 zoning application for a taller shed or large accessory footprint.
Source: Minneapolis building permit fee schedule (Chapter 91). Read the Minneapolis shed permit page, which quotes the rule and records when it was last verified (Oct 2026).
Minneapolis fence permit fee
A fence up to 7 ft needs no building permit (zoning approval only); a fence over 7 ft or a pool barrier pays the valuation-based building permit plus 65% plan review and the state surcharge.
$207.42estimated city fees at the inputs above
Line
How it is computed
Amount
Building permit fee
$104.20 + 1 × $20.60 per 1,000 above 2,000
$124.80
Plan review (65% of permit fee)
65% of $124.80
$81.12
State surcharge (0.0005 x value)
3,000 $ × $0
$1.50
The page's own example: “A $3,000 fence over 7 feet comes to $104.20 + $20.60 = $124.80, plus $81.12 plan review and $1.50 surcharge, for $207.42.”
Not included: Fences of 7 ft or less pay no building permit fee; the zoning fee table lists no fence fee.
Source: Minneapolis building permit fee schedule (Chapter 91). Read the Minneapolis fence permit page, which quotes the rule and records when it was last verified (Oct 2026).
Minneapolis deck permit fee
A deck more than 30 in above grade, attached to the house or on an accessible route pays the valuation-based building permit plus 65% plan review and the state surcharge.
$379.87estimated city fees at the inputs above
Line
How it is computed
Amount
Building permit fee
$104.20 + 6 × $20.60 per 1,000 above 2,000
$227.80
Plan review (65% of permit fee)
65% of $227.80
$148.07
State surcharge (0.0005 x value)
8,000 $ × $0
$4
The page's own example: “An $8,000 deck: $104.20 + 6 x $20.60 = $227.80, plus $148.07 plan review and $4.00 surcharge = $379.87.”
Not included: A freestanding platform 30 in or lower, not at the main entrance, is exempt; the city may double fees for work started before the permit.
Source: Minneapolis building permit fee schedule (Chapter 91). Read the Minneapolis deck permit page, which quotes the rule and records when it was last verified (Oct 2026).
Minneapolis pool permit fee
A pool 2 ft deep or more (other than a small prefab above-ground pool) pays the valuation-based building permit plus 65% plan review and the state surcharge.
$1,593.33estimated city fees at the inputs above
Line
How it is computed
Amount
Building permit fee
$578 + 25 × $14.90 per 1,000 above 25,000
$950.50
Plan review (65% of permit fee)
65% of $950.50
$617.83
State surcharge (0.0005 x value)
50,000 $ × $0
$25
The page's own example: “A $50,000 in-ground pool: $578.00 + 25 x $14.90 = $950.50, plus $617.83 plan review and $25.00 surcharge = $1,593.33.”
Not included: The DLI electrical permit ($25 permit fee) and its $35 per bonding inspection.
Source: MCO 89.140; Chapter 91 building permit fee schedule. Read the Minneapolis pool permit page, which quotes the rule and records when it was last verified (Oct 2026).
Minneapolis roof replacement permit fee
All re-roofing beyond one bundle of shingles needs a building permit priced on job value ($104.20 for the first $2,000 plus $20.60 per additional $1,000) plus the state surcharge; no plan review applies.
$231.80estimated city fees at the inputs above
Line
How it is computed
Amount
Building permit fee
$104.20 + 6 × $20.60 per 1,000 above 2,000
$227.80
State surcharge (0.0005 x value)
8,000 $ × $0
$4
The page's own example: “An $8,000 reroof: $104.20 + 6 x $20.60 = $227.80, plus a $4.00 surcharge = $231.80.”
Not included: A separate permit for rafter or truss repairs; the city may double fees if work starts first.
Bathroom plumbing is $41.40 per fixture with an $85.20 minimum including the $1 state surcharge; opening walls adds a valuation-based building permit with 65% plan review and the state surcharge.
$746.50estimated city fees at the inputs above
Line
How it is computed
Amount
Plumbing fixtures
3 fixtures × $41.40
$124.20
Plumbing state surcharge
flat
$1
Building permit fee optional
$104.20 + 13 × $20.60 per 1,000 above 2,000
$372
Plan review (65% of permit fee) optional
65% of $372
$241.80
State surcharge (0.0005 x value) optional
15,000 $ × $0
$7.50
The page's own example: “plus plumbing 3 x $41.40 + $1 = $125.20, for $746.50”
Not included: The DLI electrical permit for new lights or circuits ($12 per circuit, $55 per inspection minimum, $25 permit fee, $1 surcharge).
Moving or adding kitchen fixtures is a plumbing permit at $41.40 per fixture ($85.20 minimum); opening walls adds a valuation-based building permit with 65% plan review and the state surcharge.
$1,176.83estimated city fees at the inputs above
Line
How it is computed
Amount
Plumbing fixtures
2 fixtures × $41.40
$82.80
Plumbing state surcharge
flat
$1
Plumbing permit minimum
brings the total up to the $85.20 minimum
$1.40
Building permit fee optional
$578 + 5 × $14.90 per 1,000 above 25,000
$652.50
Plan review (65% of permit fee) optional
65% of $652.50
$424.13
State surcharge (0.0005 x value) optional
30,000 $ × $0
$15
The page's own example: “A $30,000 remodel that opens walls: building permit $578.00 + 5 x $14.90 = $652.50, plan review $424.13, surcharge $15.00, plus the $85.20 plumbing permit = $1,176.83.”
Not included: The DLI electrical permit for new circuits (four circuits with rough-in and final come to $136); licensed gas work on its own permit.
Panel permits come from the state (DLI): the greater of the $55 per-trip minimum or the itemized fee ($35 for a service up to 400 A plus $2 per reconnected circuit), plus a $25 permit fee and $1 surcharge.
$101estimated city fees at the inputs above
Line
How it is computed
Amount
Service up to 400 A
flat
$35
Reconnected circuits
20 circuits × $2
$40
DLI permit fee
flat
$25
State surcharge
flat
$1
The page's own example: “Upgrading to a 200-amp service and moving 20 circuits into the new panel, final inspection only: $35 + 20 x $2 = $75, which beats the $55 minimum, plus $26 = $101.”
Not included: New circuits ($12 each when fewer than 15) are not modeled; a reinspection can add $55.
Existing one- and two-family homes pay a flat mechanical fee by level, each plus a $1 state surcharge: Level 1 (AC or heat pump, vents) $84.20, Level 2 (furnace or boiler change-out, with any Level 1 work) $132.40, Level 3 (whole new system) $216.60.
$133.40estimated city fees at the inputs above
Line
How it is computed
Amount
Mechanical permit, Level 2
flat
$132.40
State surcharge
flat
$1
The page's own example: “So a furnace and AC swapped together is Level 2 at $133.40, because Level 2 includes Level 1 work.”
Not included: Gas piping and venting by a licensed gas installer on a separate permit; new homes and additions are priced at 1.99% of the mechanical contract value instead.
Source: Minneapolis mechanical permit application, existing 1-2 family homes. Read the Minneapolis hvac permit page, which quotes the rule and records when it was last verified (Oct 2026).
Minneapolis adu permit fee
An ADU pays the valuation-based building permit, 65% plan review, the state surcharge of 0.0005 times the value and the $325 administrative zoning fee.
$2,098.23estimated city fees at the inputs above
Line
How it is computed
Amount
Building permit fee
$950.50 + 10 × $10.60 per 1,000 above 50,000
$1,056.50
Plan review (65% of permit fee)
65% of $1,056.50
$686.73
State surcharge (0.0005 x value)
60,000 $ × $0
$30
Administrative ADU zoning application
flat
$325
The page's own example: “A $60,000 basement ADU: $950.50 + 10 x $10.60 = $1,056.50, plan review $686.73, surcharge $30.00, zoning $325 = $2,098.23.”
Not included: Plumbing ($41.40 per fixture), mechanical and DLI electrical permits; a Metropolitan Council SAC charge ($2,485 per unit in 2026) may apply.
Source: Chapter 91 building permit fee schedule; Table 525-1. Read the Minneapolis adu permit page, which quotes the rule and records when it was last verified (Oct 2026).
What the estimate covers
City fees only, on the ordinary residential path each page prices: the building or trade permit plus the mandatory lines the city adds to it. It leaves out whatever the page says is separate (a designer's fee, a contractor's licence, a utility connection) and anything the page does not price. Fee schedules change on the city's budget cycle; the month each page was last verified is Oct 2026, and the verification method explains how changes are caught.
Frequently asked questions
A 240 sq ft shed valued at $6,000 works out to $104.20 + 4 x $20.60 = $186.60, plan review $121.29 and surcharge $3.00, for $310.89.. A shed over 200 sq ft, or two stories, pays the valuation-based building permit ($104.20 for the first $2,000 plus $20.60 per additional $1,000), 65% plan review when plans are reviewed, and the state surcharge.
A $3,000 fence over 7 feet comes to $104.20 + $20.60 = $124.80, plus $81.12 plan review and $1.50 surcharge, for $207.42.. A fence up to 7 ft needs no building permit (zoning approval only); a fence over 7 ft or a pool barrier pays the valuation-based building permit plus 65% plan review and the state surcharge.
An $8,000 deck: $104.20 + 6 x $20.60 = $227.80, plus $148.07 plan review and $4.00 surcharge = $379.87.. A deck more than 30 in above grade, attached to the house or on an accessible route pays the valuation-based building permit plus 65% plan review and the state surcharge.
A $50,000 in-ground pool: $578.00 + 25 x $14.90 = $950.50, plus $617.83 plan review and $25.00 surcharge = $1,593.33.. A pool 2 ft deep or more (other than a small prefab above-ground pool) pays the valuation-based building permit plus 65% plan review and the state surcharge.
An $8,000 reroof: $104.20 + 6 x $20.60 = $227.80, plus a $4.00 surcharge = $231.80.. All re-roofing beyond one bundle of shingles needs a building permit priced on job value ($104.20 for the first $2,000 plus $20.60 per additional $1,000) plus the state surcharge; no plan review applies.
Every line is read off the Minneapolis permit pages on this site, which quote the city's own fee schedule, bulletin or ordinance and record the month the sources were last verified (Oct 2026). The calculator holds no fee of its own.