This calculator applies the fee lines quoted on the Baltimore permit pages: the city's own plan review, permit and surcharge figures, as published by the Baltimore City Department of Housing and Community Development. Pick a project, change the inputs, and the breakdown shows each line and how it is computed. 9 of 10 project types have a computable formula on their page; the rest show the page's own figure.
- Every permit carries the 5% Building Code Permit Tax, rounded up to the next dollar, plus a nonrefundable application fee: $25 for a one- or two-family dwelling without plan review, $125 with ePlans review.
- Trade permits (plumbing, electrical, HVACR) are issued only to city-licensed contractors; there is no homeowner trade permit.
Baltimore shed permit fee
A shed over 120 sq ft pays the flat $50 accessory-structure fee, the 5% permit tax rounded up and the $25 application fee, about $78.
| Line | How it is computed | Amount |
|---|---|---|
| Accessory structure fee (over 100 sq ft) | flat | $50 |
| Building Code Permit Tax (5%) | 5% of $50, rounded up to the dollar | $3 |
| Application fee | flat | $25 |
Baltimore fence permit fee
Every new fence needs a permit at $10 per 100 linear ft or fraction, read with the code's $25 minimum, plus the 5% tax and the $25 application fee.
| Line | How it is computed | Amount |
|---|---|---|
| Fence fee ($10 per 100 ft, $25 minimum) | 2 × $10 per 100 linear ft or fraction (minimum $25) | $25 |
| Building Code Permit Tax (5%) | 5% of $25, rounded up to the dollar | $2 |
| Application fee | flat | $25 |
Baltimore deck permit fee
Every deck needs a permit, read under the exterior-alteration rate of $10 per $1,000 of estimated cost ($50 minimum), plus the 5% tax and the $25 application fee.
| Line | How it is computed | Amount |
|---|---|---|
| Exterior alteration fee ($10 per $1,000, $50 minimum) | 15 × $10 per 1,000 $ or fraction | $150 |
| Building Code Permit Tax (5%) | 5% of $150, rounded up to the dollar | $8 |
| Application fee | flat | $25 |
Baltimore pool permit fee
A pool deeper than 24 in pays the flat $50 pool fee, $30 if connected to water and sewer and $6 per new circuit, plus the 5% tax and the $125 plan-review application fee.
| Line | How it is computed | Amount |
|---|---|---|
| Swimming pool fee | flat | $50 |
| Water and sewer connection optional | flat | $30 |
| Electrical circuits | 3 circuits × $6 | $18 |
| Building Code Permit Tax (5%) | 5% of $98, rounded up to the dollar | $5 |
| Plan-review application fee | flat | $125 |
Baltimore roof replacement permit fee
Replacing shingles or re-tarring needs no permit; structural roof work is an exterior alteration at $10 per $1,000 of estimated cost ($50 minimum), plus the 5% tax and the $25 application fee.
| Line | How it is computed | Amount |
|---|---|---|
| Exterior alteration fee ($10 per $1,000, $50 minimum) | 8 × $10 per 1,000 $ or fraction | $80 |
| Building Code Permit Tax (5%) | 5% of $80, rounded up to the dollar | $4 |
| Application fee | flat | $25 |
Baltimore bathroom remodel permit fee
Bathroom permits are itemized: $5 per plumbing fixture, $6 per circuit, a $30 minimum for a ducted exhaust fan and, when the layout changes, $0.30 per sq ft with a $50 minimum, plus the 5% tax and the $25 application fee.
| Line | How it is computed | Amount |
|---|---|---|
| Building alteration fee ($0.30 per sq ft, $50 minimum) optional | 60 sq ft × $0.30 (minimum $50) | $50 |
| Plumbing fixtures | 4 fixtures × $5 | $20 |
| Electrical circuits | 2 circuits × $6 | $12 |
| Ducted exhaust fan ($30 minimum) optional | flat | $30 |
| Building Code Permit Tax (5%) | 5% of $112, rounded up to the dollar | $6 |
| Application fee | flat | $25 |
Baltimore kitchen remodel permit fee
Kitchen permits are itemized: the building alteration at $0.30 per sq ft of affected area ($50 minimum), $5 per plumbing fixture, $6 per circuit and $25 for gas piping, plus the 5% tax and the $25 application fee.
| Line | How it is computed | Amount |
|---|---|---|
| Building alteration fee ($0.30 per sq ft, $50 minimum) optional | 250 sq ft × $0.30 | $75 |
| Electrical circuits | 6 circuits × $6 | $36 |
| Plumbing fixtures | 3 fixtures × $5 | $15 |
| Gas piping optional | flat | $25 |
| Building Code Permit Tax (5%) | 5% of $151, rounded up to the dollar | $8 |
| Application fee | flat | $25 |
Baltimore electrical panel permit fee
A panel or service change is priced by rating, $25 up to 100 A, $30 over 100 to 200 A and $40 over 200 to 400 A, plus $6 per new or replaced circuit, the 5% tax and the $25 application fee.
| Line | How it is computed | Amount |
|---|---|---|
| Service fee by rating | $30 | $30 |
| Branch circuits | 0 circuits × $6 | $0 |
| Building Code Permit Tax (5%) | 5% of $30, rounded up to the dollar | $2 |
| Application fee | flat | $25 |
Baltimore hvac permit fee
A mechanical permit charges $30 per furnace, $5 a ton for air conditioning ($30 minimum) and $25 for a new duct system, plus the 5% tax and the $25 application fee; replacements are charged as new.
| Line | How it is computed | Amount |
|---|---|---|
| Furnace (fuel-burning, up to 200,000 Btu/h) optional | flat | $30 |
| Air conditioning ($5 a ton, $30 minimum) optional | 3 tons × $5 (minimum $30) | $30 |
| New duct system optional | flat | $25 |
| Building Code Permit Tax (5%) | 5% of $85, rounded up to the dollar | $5 |
| Application fee | flat | $25 |
Baltimore adu permit fee
Baltimore has no ADU law yet (Council Bill 26-0195 is back in committee); a unit is priced from the alteration or new-building lines, trade lines, a $45 occupancy permit, the $125 plan-review fee and the 5% tax.
What the city page states: Interior example: $150 alteration, $40 plumbing, $60 for ten circuits, $55 mechanical and $45 occupancy make $493 with tax and application.
What the estimate covers
City fees only, on the ordinary residential path each page prices: the building or trade permit plus the mandatory lines the city adds to it. It leaves out whatever the page says is separate (a designer's fee, a contractor's licence, a utility connection) and anything the page does not price. Fee schedules change on the city's budget cycle; the month each page was last verified is Oct 2026, and the verification method explains how changes are caught.
Frequently asked questions
Other city calculators
- Albuquerque, NM
- Charlotte, NC
- Chicago, IL
- Cincinnati, OH
- Dallas, TX
- Fort Worth, TX
- Houston, TX
- Indianapolis, IN
- Jacksonville, FL
- Kansas City, MO
- Long Beach, CA
- Los Angeles, CA
- Louisville, KY
- Miami, FL
- Milwaukee, WI
- Minneapolis, MN
- New York City, NY
- Philadelphia, PA
- Phoenix, AZ
- Pittsburgh, PA
- Portland, OR
- Sacramento, CA
- San Antonio, TX
- San Diego, CA
- San Francisco, CA
- San Jose, CA
- Seattle, WA
- St. Louis, MO
- Tucson, AZ
Related: All cities · Research: fees compared across 30 cities · Baltimore permit guide