City fee lines from the Dallas permit pages, computed for your project. Sourced, verified Oct 2026.
Verified Oct 2026Calculator
This calculator applies the fee lines quoted on the Dallas permit pages: the city's own plan review, permit and surcharge figures, as published by the City of Dallas Planning and Development Department. Pick a project, change the inputs, and the breakdown shows each line and how it is computed. 10 of 10 project types have a computable formula on their page; the rest show the page's own figure.
Texas Local Government Code 214.907 bars value-based residential fees: new work is $1.07 per sq ft (Chapter 52 Table A-I, up to 700 sq ft), alterations and repairs a flat $181 per dwelling unit (Table B-II).
The fee schedule effective July 1, 2025 adds a $125 inspection fee per trade, a $15 technology fee, and when plans are checked a plan review fee of $0.046 per sq ft or $577, whichever is greater.
Planned development, specific-use-permit and deed-restricted areas add 10 percent of the permit fee.
Dallas shed permit fee
A one-story shed up to 200 sq ft needs no permit; a larger shed is priced at $1.07 per sq ft plus a $125 inspection fee and a $15 technology fee, with plan review if the examiner checks plans.
Exempt: No permit for a one-story detached shed up to 200 sq ft on a single-family or duplex lot (Chapter 52 Sec. 301.2.1).
$396.80estimated city fees at the inputs above
Line
How it is computed
Amount
Permit fee (Table A-I)
240 sq ft × $1.07
$256.80
Inspection fee (one trade)
flat
$125
Technology fee
flat
$15
The page's own example: “12x20 shed (240 sq ft): 240 x $1.07 = $256.80, plus $125 inspection and $15 technology = $396.80.”
Not included: An electrical permit for wiring; contractor fees.
Source: Dallas City Code Chapter 52 Table A-I; fee schedule effective July 1, 2025. Read the Dallas shed permit page, which quotes the rule and records when it was last verified (Oct 2026).
Dallas fence permit fee
Fences up to 4 ft in front yards and 6 ft elsewhere need no permit; a taller fence (up to 9 ft) is estimated at the $181 alteration base plus a $125 inspection fee and a $15 technology fee.
$321estimated city fees at the inputs above
Line
How it is computed
Amount
Base permit fee (Table B-II)
flat
$181
Inspection fee (one trade)
flat
$125
Technology fee
flat
$15
The page's own example: “A side-yard fence of 8 feet works out to about $181 + $125 + $15 = $321.”
Not included: A front-yard fence over 4 ft needs a Board of Adjustment special exception first ($600 or $900 filing); $30 application edits; contractor fees.
Source: Dallas City Code Chapter 52 Table B-II; fee schedule effective July 1, 2025. Read the Dallas fence permit page, which quotes the rule and records when it was last verified (Oct 2026).
Dallas deck permit fee
A deck that is attached, over 200 sq ft or over 30 in high needs a permit, estimated at $1.07 per sq ft plus a $125 inspection fee and a $15 technology fee, with plan review if charged.
$461estimated city fees at the inputs above
Line
How it is computed
Amount
Permit fee, new deck (Table A-I)
300 sq ft × $1.07
$321
Inspection fee (one trade)
flat
$125
Technology fee
flat
$15
The page's own example: “New 300 sq ft deck: 300 x $1.07 = $321, plus $125 and $15 = $461.”
Not included: Contractor fees; the exemption (freestanding, 200 sq ft or less, 30 in or lower, not at the exit door) depends on more than area, so it is not an input.
Source: Dallas City Code Chapter 52 Table A-I; fee schedule effective July 1, 2025. Read the Dallas deck permit page, which quotes the rule and records when it was last verified (Oct 2026).
Dallas pool permit fee
A pool is estimated at $1.07 per sq ft plus plan review ($0.046 per sq ft, $577 minimum), a $125 inspection fee per trade (building, electrical, plumbing) and a $15 technology fee.
$1,395estimated city fees at the inputs above
Line
How it is computed
Amount
Permit fee (Table A-I)
400 sq ft × $1.07
$428
Plan review
400 sq ft × $0.05 (minimum $577)
$577
Inspection fees
3 units × $125
$375
Technology fee
flat
$15
The page's own example: “Technology fee: $15. Total: about $1,395.”
Not included: The separate pool barrier (accessory structure) permit; contractor fees. Prefab pools under 24 in deep holding 5,000 gallons or less are exempt.
Source: Dallas City Code Chapter 52 Table A-I; fee schedule effective July 1, 2025. Read the Dallas pool permit page, which quotes the rule and records when it was last verified (Oct 2026).
Dallas roof replacement permit fee
Reroofing more than two roofing squares takes a Residential Roofing Permit: $181 base plus a $125 inspection fee and a $15 technology fee, whatever the roof costs.
$321estimated city fees at the inputs above
Line
How it is computed
Amount
Base permit fee (Table B-II)
flat
$181
Inspection fee (one trade)
flat
$125
Technology fee
flat
$15
The page's own example: “For a single-family home, Chapter 52 Table B-II sets a $181 base fee per dwelling unit, and the fee schedule adds a $125 inspection fee and a $15 technology fee, for $321.”
Not included: Repairs up to two roofing squares need no permit; $75 failed inspections; a third-party energy code provider if required.
Source: Dallas City Code Chapter 52 Table B-II; fee schedule effective July 1, 2025. Read the Dallas roof replacement permit page, which quotes the rule and records when it was last verified (Oct 2026).
Dallas bathroom remodel permit fee
A bathroom remodel that moves fixtures or adds circuits pays the flat $181 alteration base, a $125 inspection fee per trade and a $15 technology fee, plus a $577-minimum plan review when plans are checked.
$321estimated city fees at the inputs above
Line
How it is computed
Amount
Base permit fee (Table B-II)
flat
$181
Inspection fees
1 units × $125
$125
Technology fee
flat
$15
The page's own example: “Plumbing-only permit to move a drain: $181 + $125 + $15 = $321.”
Not included: In-kind fixture swaps and finish work need no permit; the possible $100 per additional trade on Table B-II.
Source: Dallas City Code Chapter 52 Table B-II; fee schedule effective July 1, 2025. Read the Dallas bathroom remodel permit page, which quotes the rule and records when it was last verified (Oct 2026).
Dallas kitchen remodel permit fee
A kitchen remodel that moves plumbing, touches gas or alters a bearing wall pays the flat $181 alteration base, a $125 inspection fee per trade and a $15 technology fee, plus a $577-minimum plan review when plans are checked.
$321estimated city fees at the inputs above
Line
How it is computed
Amount
Base permit fee (Table B-II)
flat
$181
Inspection fees
1 units × $125
$125
Technology fee
flat
$15
The page's own example: “A single stand-alone trade permit, such as plumbing to move the sink: $181 + $125 + $15 = $321.”
Not included: Finish work, non-load-bearing interior changes and small electrical additions need no permit; the possible $100 per additional trade on Table B-II.
Source: Dallas City Code Chapter 52 Table B-II; fee schedule effective July 1, 2025. Read the Dallas kitchen remodel permit page, which quotes the rule and records when it was last verified (Oct 2026).
Dallas electrical panel permit fee
Every panel or service change needs a Residential Electrical Permit at a flat $181 base, a $125 inspection fee and a $15 technology fee, whatever the amperage.
$321estimated city fees at the inputs above
Line
How it is computed
Amount
Base permit fee (Table B-II)
flat
$181
Inspection fee (electrical)
flat
$125
Technology fee
flat
$15
The page's own example: “Total: $321, or $339.10 in a planned development”
Not included: $75 failed inspections and $50 after-hours utility releases; the electrician's labor.
Source: Dallas City Code Chapter 52 Table B-II; fee schedule effective July 1, 2025. Read the Dallas electrical panel permit page, which quotes the rule and records when it was last verified (Oct 2026).
Dallas hvac permit fee
Like-for-like electric AC or heat pump swaps need no permit; a gas furnace or new system pays the flat $181 base, a $125 inspection fee per trade and a $15 technology fee.
$321estimated city fees at the inputs above
Line
How it is computed
Amount
Base permit fee (Table B-II)
flat
$181
Inspection fees
1 units × $125
$125
Technology fee
flat
$15
The page's own example: “Mechanical permit for a gas furnace or new system: $181 + $125 + $15 = $321.”
Not included: A duct blaster test and third-party energy code provider for new systems (private costs).
Source: Dallas City Code Chapter 52 Table B-II; fee schedule effective July 1, 2025. Read the Dallas hvac permit page, which quotes the rule and records when it was last verified (Oct 2026).
Dallas adu permit fee
An ADU needs a $600 Board of Adjustment special exception, then a permit at $1.07 per sq ft plus plan review ($0.046 per sq ft, $577 minimum), $125 per trade inspected and a $15 technology fee.
$2,227estimated city fees at the inputs above
Line
How it is computed
Amount
Permit fee (Table A-I)
500 sq ft × $1.07
$535
Plan review
500 sq ft × $0.05 (minimum $577)
$577
Inspection fees
4 units × $125
$500
Technology fee
flat
$15
Board of Adjustment special exception
flat
$600
The page's own example: “500 sq ft ADU, four trades: $535 + $577 + $500 + $15 = $1,627 in permit fees; $2,227 with the $600 Board fee.”
Not included: $10 per notification sign; water and wastewater connection charges; contractor and design fees.
Source: Dallas City Code Chapter 52 Table A-I; fee schedule effective July 1, 2025. Read the Dallas adu permit page, which quotes the rule and records when it was last verified (Oct 2026).
What the estimate covers
City fees only, on the ordinary residential path each page prices: the building or trade permit plus the mandatory lines the city adds to it. It leaves out whatever the page says is separate (a designer's fee, a contractor's licence, a utility connection) and anything the page does not price. Fee schedules change on the city's budget cycle; the month each page was last verified is Oct 2026, and the verification method explains how changes are caught.
Frequently asked questions
12x20 shed (240 sq ft): 240 x $1.07 = $256.80, plus $125 inspection and $15 technology = $396.80.. A one-story shed up to 200 sq ft needs no permit; a larger shed is priced at $1.07 per sq ft plus a $125 inspection fee and a $15 technology fee, with plan review if the examiner checks plans.
A side-yard fence of 8 feet works out to about $181 + $125 + $15 = $321.. Fences up to 4 ft in front yards and 6 ft elsewhere need no permit; a taller fence (up to 9 ft) is estimated at the $181 alteration base plus a $125 inspection fee and a $15 technology fee.
New 300 sq ft deck: 300 x $1.07 = $321, plus $125 and $15 = $461.. A deck that is attached, over 200 sq ft or over 30 in high needs a permit, estimated at $1.07 per sq ft plus a $125 inspection fee and a $15 technology fee, with plan review if charged.
Technology fee: $15. Total: about $1,395.. A pool is estimated at $1.07 per sq ft plus plan review ($0.046 per sq ft, $577 minimum), a $125 inspection fee per trade (building, electrical, plumbing) and a $15 technology fee.
For a single-family home, Chapter 52 Table B-II sets a $181 base fee per dwelling unit, and the fee schedule adds a $125 inspection fee and a $15 technology fee, for $321.. Reroofing more than two roofing squares takes a Residential Roofing Permit: $181 base plus a $125 inspection fee and a $15 technology fee, whatever the roof costs.
Every line is read off the Dallas permit pages on this site, which quote the city's own fee schedule, bulletin or ordinance and record the month the sources were last verified (Oct 2026). The calculator holds no fee of its own.