San Jose Permit Fee Calculator

City fee lines from the San Jose permit pages, computed for your project. Sourced, verified Oct 2026.

Verified Oct 2026Calculator

This calculator applies the fee lines quoted on the San Jose permit pages: the city's own plan review, permit and surcharge figures, as published by the San José Department of Planning, Building and Code Enforcement. Pick a project, change the inputs, and the breakdown shows each line and how it is computed. 9 of 10 project types have a computable formula on their page; the rest show the page's own figure.

  • Fees come from the FY2026-27 Schedule of Fees and Charges (effective July 1, 2026): a one-hour processing line, a building permit at $315 per hour of inspection time in tiers of 40, 70, 130 or 250 minutes, and plan check at $325 per hour.
  • The Building Official sets the tier and may adjust the assessment to the actual scope, so modeled totals follow the pages' published arithmetic, not a quote.

What the estimate covers

City fees only, on the ordinary residential path each page prices: the building or trade permit plus the mandatory lines the city adds to it. It leaves out whatever the page says is separate (a designer's fee, a contractor's licence, a utility connection) and anything the page does not price. Fee schedules change on the city's budget cycle; the month each page was last verified is Oct 2026, and the verification method explains how changes are caught.

Frequently asked questions

A simple prefab shed that lands in Tier 1 therefore comes to about $211 + $210 + $162.50, roughly $585. A shed over 120 sq ft pays a $211 processing fee, a building permit at $315 per hour of inspection time in tiers, and plan check at $325 per hour with a 30-minute minimum.
A Tier 1 fence permit is therefore about $211 + $210 + $162.50, roughly $585. Fences up to 7 ft need no building permit; a taller fence pays $211 processing, a Tier 1 inspection fee at $315 per hour and a 30-minute plan check.
A small attached deck reviewed over the counter in Tier 1 is about $211 + $210 + $162.50, roughly $585. A deck that fails the four-part exemption pays $211 processing, a building permit at $315 per hour of inspection time in tiers, and plan check at $325 per hour.
A modest pool in Tier 2 with one electrical permit is about $211 + $367.50 + $325 + $315, roughly $1,220. A pool pays $211 processing, a building permit at $315 per hour of inspection time in tiers, a one-hour plan check, and separate trade permits at a $315 minimum each.
The city's schedule sets the residential Reroofing Permit at $236 for up to two inspections. Reroofing 25 percent or more of the roof in 12 months is a flat $236 residential permit covering two inspections; a $211 processing line can apply on counter filings.
Every line is read off the San Jose permit pages on this site, which quote the city's own fee schedule, bulletin or ordinance and record the month the sources were last verified (Oct 2026). The calculator holds no fee of its own.

Other city calculators

Related: All cities · Research: fees compared across 30 cities · San Jose permit guide