City fee lines from the New Orleans permit pages, computed for your project. Sourced, verified Nov 2026.
Verified Nov 2026Calculator
This calculator applies the fee lines quoted on the New Orleans permit pages: the city's own plan review, permit and surcharge figures, as published by the Department of Safety and Permits. Pick a project, change the inputs, and the breakdown shows each line and how it is computed. 9 of 10 project types have a computable formula on their page; the rest show the page's own figure.
Building, accessory structure and pool permits cost $60 plus $5 per $1,000 of the work's market value; plan review, when plans are required, adds $1 per $1,000 with a minimum of $60 on the fee schedule and Guide ($120 on the city's estimator page).
The city's sources write the historic-district surcharge three ways: 50% of all fees on the fee schedule, 50% of the permit fee on the permit pages, and job value x .0025 added to the fees in the Guide to Building Permits.
Electrical, mechanical and gas permits are pulled only by city Class A licensed contractors; plumbing permits come from the Sewerage and Water Board, whose fee the city pages do not publish.
The pages say $5 and $1 'per $1,000' without saying whether a part-thousand is charged in full; the calculator charges each started $1,000.
New Orleans shed permit fee
Every shed needs an Accessory Structure permit (the city publishes no size exemption), priced at $60 plus $5 per $1,000 of the shed's market value, labor and materials included.
$100estimated city fees at the inputs above
Line
How it is computed
Amount
Building permit ($60 + $5 per $1,000)
$60 + 8 × $5 per 1,000 above 0
$100
The page's own example: “an $8,000 site-built shed costs $60 + $40 = $100”
Not included: Electrical and SWBNO plumbing permits for wiring or water lines; building first adds a penalty of 200% of all fees. The historic-district surcharge is shown at the fee schedule's reading (50% of all fees); the permit pages read it as 50% of the permit fee and the Guide to Building Permits as job value x .0025 added to the fees, so confirm the total when you apply. Plan review is $60 minimum on the fee schedule and $120 on the city's estimator page.
Source: City of New Orleans building permit fee schedule (Accessory Structure permit). Read the New Orleans shed permit page, which quotes the rule and records when it was last verified (Nov 2026).
New Orleans fence permit fee
Fences up to 7 ft that meet zoning (masonry walls up to 3 ft) need no building permit; a taller fence or wall pays $60 plus $5 per $1,000 of the work's value.
$110estimated city fees at the inputs above
Line
How it is computed
Amount
Building permit ($60 + $5 per $1,000)
$60 + 10 × $5 per 1,000 above 0
$110
The page's own example: “so a $10,000 masonry wall costs $60 + $50 = $110 before any historic-district surcharge”
Not included: Height and material are not calculator inputs: a fence within the exemption costs nothing at Safety and Permits; building a permit-required wall without one adds a penalty of 200% of all fees. The historic-district surcharge is shown at the fee schedule's reading (50% of all fees); the permit pages read it as 50% of the permit fee and the Guide to Building Permits as job value x .0025 added to the fees, so confirm the total when you apply.
Source: City of New Orleans building permit fee schedule; amended Building Code section 105.2 exemptions. Read the New Orleans fence permit page, which quotes the rule and records when it was last verified (Nov 2026).
New Orleans deck permit fee
A deck that is attached, over 200 sq ft, over 30 inches high or serves an exit door needs a building permit at $60 plus $5 per $1,000 of its market value, plus plan review if plans are required.
$135estimated city fees at the inputs above
Line
How it is computed
Amount
Building permit ($60 + $5 per $1,000)
$60 + 15 × $5 per 1,000 above 0
$135
The page's own example: “A $15,000 deck costs $60 + $75 = $135.”
Not included: Plan review is charged only when the department requires plans; the $60 minimum is the fee schedule's and Guide's, while the city's estimator page lists $120. Building first adds a penalty of 200% of all fees; the historic surcharge has two other readings (50% of the permit fee; job value x .0025).
Source: City of New Orleans building permit fee schedule; Guide to Building Permits. Read the New Orleans deck permit page, which quotes the rule and records when it was last verified (Nov 2026).
New Orleans pool permit fee
Any type of swimming pool needs a Swimming Pool permit, priced on the building permit formula of $60 plus $5 per $1,000 of the work's value.
$260estimated city fees at the inputs above
Line
How it is computed
Amount
Building permit ($60 + $5 per $1,000)
$60 + 40 × $5 per 1,000 above 0
$260
The page's own example: “A $40,000 in-ground pool costs $60 + $200 = $260”
Not included: The separate electrical permit ($40 plus $3 per new circuit plus $0.30 per amp of service), the Gasfitting permit for a gas heater and the SWBNO plumbing permit; starting without a permit adds a penalty of 200% of all fees. The historic-district surcharge is shown at the fee schedule's reading (50% of all fees); the permit pages read it as 50% of the permit fee and the Guide to Building Permits as job value x .0025 added to the fees, so confirm the total when you apply.
Source: City of New Orleans building permit fee schedule (Swimming Pool permit). Read the New Orleans pool permit page, which quotes the rule and records when it was last verified (Nov 2026).
New Orleans roof replacement permit fee
Replacing 50% or more of a one- or two-family home's roof needs a Re-Roofing permit at a flat $60, plus $30 in HDLC or Vieux Carre districts, with no per-$1,000 charge.
$60estimated city fees at the inputs above
Line
How it is computed
Amount
Re-Roofing permit base fee
flat
$60
The page's own example: “The Re-Roofing permit has a $60 base fee.”
Not included: Replacing less than 50% of the roofing or gutters is exempt; buildings with three or more units and businesses file a renovation permit priced on job value instead.
Construction inside the home needs a Renovation permit at $60 plus $5 per $1,000 of the job's market value, and any fixture change also needs a Sewerage and Water Board plumbing permit.
$135estimated city fees at the inputs above
Line
How it is computed
Amount
Building permit ($60 + $5 per $1,000)
$60 + 15 × $5 per 1,000 above 0
$135
The page's own example: “A $15,000 bathroom costs $60 + $75 = $135”
Not included: The SWBNO plumbing permit (fee not published on the city pages) and the electrical permit ($40 plus $3 per new circuit plus $0.30 per amp of service). Plan review is charged only when the department requires plans; the $60 minimum is the fee schedule's and Guide's, while the city's estimator page lists $120. The historic-district surcharge has two other readings (50% of the permit fee; job value x .0025).
Source: City of New Orleans building permit fee schedule (Renovation permit). Read the New Orleans bathroom remodel permit page, which quotes the rule and records when it was last verified (Nov 2026).
New Orleans kitchen remodel permit fee
A kitchen remodel beyond a cabinet and countertop swap needs a Renovation permit at $60 plus $5 per $1,000 of the job's market value, plus plan review if plans are required and separate trade permits.
$210estimated city fees at the inputs above
Line
How it is computed
Amount
Building permit ($60 + $5 per $1,000)
$60 + 30 × $5 per 1,000 above 0
$210
The page's own example: “A $30,000 remodel costs $60 + $150 = $210.”
Not included: Trade permits: electrical at $40 plus $3 per new circuit plus $0.30 per amp of service, and SWBNO plumbing (fee not published). Plan review is charged only when the department requires plans; the $60 minimum is the fee schedule's and Guide's, while the city's estimator page lists $120. The historic-district surcharge has two other readings (50% of the permit fee; job value x .0025).
Source: City of New Orleans building permit fee schedule (Renovation permit). Read the New Orleans kitchen remodel permit page, which quotes the rule and records when it was last verified (Nov 2026).
New Orleans electrical panel permit fee
Any panel swap or service change needs an electrical permit pulled by a city Class A electrician: $40 plus $3 per new circuit plus $0.30 per amp of service.
$100estimated city fees at the inputs above
Line
How it is computed
Amount
Electrical permit base
flat
$40
Per amp of service
200 amps × $0.30
$60
Per new circuit
0 circuits × $3
$0
The page's own example: “200-amp service: $40 + (200 x $0.30 = $60) = $100.”
Not included: The electrician's charges; a building permit if Permit Intake says the job needs one. The historic-district surcharge is not listed for electrical permits.
Any AC, heat pump, furnace or air handler replacement needs an HVAC permit filed by a Class A A/C contractor: a $30 application fee plus $15 per A/C unit, $3 per ton over 3 tons and $20 to $35 per air handler or furnace.
$73estimated city fees at the inputs above
Line
How it is computed
Amount
Application fee
flat
$30
A/C or heat pump unit
1 units × $15
$15
Per ton over 3 tons
1 tons × $3 (first 3 tons free)
$3
Air handler or furnace, 51K to 200K BTU optional
flat
$25
The page's own example: “A full system with a 4-ton condenser ($15 + $3) and a 60,000 BTU gas furnace ($25) is $43 + $30 = $73.”
Not included: Gasfitting and electrical permits, billed separately; the repair or alteration line ($35 through a $1,500 contract price, plus $10 per additional $1,000), which the page does not say applies to a replacement. The per-ton line is for one unit; tick one air handler box per air handler.
Source: Mechanical A/C Permit Application (Supplement D.1). Read the New Orleans hvac permit page, which quotes the rule and records when it was last verified (Nov 2026).
New Orleans adu permit fee
New Orleans zoning does not allow ADUs and no detached accessory structure may be lived in; the legal routes (a two-family dwelling where zoned, or an addition) pay $60 plus $5 per $1,000 plus plan review.
What the city page states: A $100,000 addition would cost $60 + $500 = $560, plus plan review of $100 to $120, for $660 to $680.
Not computed here: No ADU permit exists because the CZO does not list ADUs as a use; the page prices only the addition or two-family route by example, with a plan-review minimum the city states two ways and a historic surcharge it states three ways.
City fees only, on the ordinary residential path each page prices: the building or trade permit plus the mandatory lines the city adds to it. It leaves out whatever the page says is separate (a designer's fee, a contractor's licence, a utility connection) and anything the page does not price. Fee schedules change on the city's budget cycle; the month each page was last verified is Nov 2026, and the verification method explains how changes are caught.
Frequently asked questions
an $8,000 site-built shed costs $60 + $40 = $100. Every shed needs an Accessory Structure permit (the city publishes no size exemption), priced at $60 plus $5 per $1,000 of the shed's market value, labor and materials included.
so a $10,000 masonry wall costs $60 + $50 = $110 before any historic-district surcharge. Fences up to 7 ft that meet zoning (masonry walls up to 3 ft) need no building permit; a taller fence or wall pays $60 plus $5 per $1,000 of the work's value.
A $15,000 deck costs $60 + $75 = $135.. A deck that is attached, over 200 sq ft, over 30 inches high or serves an exit door needs a building permit at $60 plus $5 per $1,000 of its market value, plus plan review if plans are required.
A $40,000 in-ground pool costs $60 + $200 = $260. Any type of swimming pool needs a Swimming Pool permit, priced on the building permit formula of $60 plus $5 per $1,000 of the work's value.
The Re-Roofing permit has a $60 base fee.. Replacing 50% or more of a one- or two-family home's roof needs a Re-Roofing permit at a flat $60, plus $30 in HDLC or Vieux Carre districts, with no per-$1,000 charge.
Every line is read off the New Orleans permit pages on this site, which quote the city's own fee schedule, bulletin or ordinance and record the month the sources were last verified (Nov 2026). The calculator holds no fee of its own.