City fee lines from the Tucson permit pages, computed for your project. Sourced, verified Oct 2026.
Verified Oct 2026Calculator
This calculator applies the fee lines quoted on the Tucson permit pages: the city's own plan review, permit and surcharge figures, as published by the Planning and Development Services Department. Pick a project, change the inputs, and the breakdown shows each line and how it is computed. 10 of 10 project types have a computable formula on their page; the rest show the page's own figure.
Every application pays a digital filing fee of 1% of the total, minimum $18.54.
Tucson shed permit fee
Every shed needs a permit; where a building permit fee applies it runs off the valuation table ($29.56 per sq ft for detached storage) plus 50% plan review and a 1% filing fee.
City valuation: 240 sq ft × $29.56 = $7,094.40
$359.26estimated city fees at the inputs above
Line
How it is computed
Amount
Building permit fee
$89.45 + 6 × $22.95 per 1,000 above 2,000
$227.15
Plan review (50% of permit fee)
$89.45 + 6 × $22.95 per 1,000 above 2,000 × 0.5
$113.57
Digital filing fee (1%, $18.54 minimum)
1% of $340.72 (minimum $18.54)
$18.54
The page's own example: “review $113.58; filing fee $18.54; about $359”
Not included: A site-plan-only shed (under 200 sq ft, no utilities) may cost less, but the city does not publish that figure; a DDO for setback relief is $278.07.
Source: PDSD fee schedule effective July 1, 2026. Read the Tucson shed permit page, which quotes the rule and records when it was last verified (Oct 2026).
Tucson fence permit fee
Every fence or wall needs a zoning permit priced on length (wood or metal) or wall face area (masonry), plus at least half an hour of review and the 1% filing fee.
$107.86estimated city fees at the inputs above
Line
How it is computed
Amount
Wood or metal fence
$28.08 + 2 × $5.62 per 100 above 0
$39.32
Plan review (half-hour minimum)
flat
$50
Digital filing fee (1%, $18.54 minimum)
1% of $89.32 (minimum $18.54)
$18.54
The page's own example: “150 ft wood fence: $28.08 + 2 × $5.62 = $39.32; review $50; filing $18.54; about $108.”
Not included: Review beyond half an hour ($100 an hour); building permit fees for engineered walls over 7 ft; NPZ review ($33.44) in preservation zones.
Source: PDSD fee schedule effective July 1, 2026. Read the Tucson fence permit page, which quotes the rule and records when it was last verified (Oct 2026).
Tucson deck permit fee
A deck over 30 in (or in a setback) pays a valuation-based building permit fee on the signed contract value, plus 50% plan review and the 1% filing fee.
$359.26estimated city fees at the inputs above
Line
How it is computed
Amount
Building permit fee
$89.45 + 6 × $22.95 per 1,000 above 2,000
$227.15
Plan review (50% of permit fee)
$89.45 + 6 × $22.95 per 1,000 above 2,000 × 0.5
$113.57
Digital filing fee (1%, $18.54 minimum)
1% of $340.72 (minimum $18.54)
$18.54
The page's own example: “$8,000 deck: $89.45 + 6 × $22.95 = $227.15; review $113.58; filing $18.54; about $359.”
Not included: Low decks of 30 in or under outside setbacks (and not over a floor below or part of an exit) need no permit; the penalty for starting without a permit.
Source: PDSD fee schedule effective July 1, 2026. Read the Tucson deck permit page, which quotes the rule and records when it was last verified (Oct 2026).
Tucson pool permit fee
A private residential pool is a flat $730.28 (a stand-alone spa $337.05) plus plan review at $100 an hour and the 1% filing fee.
$848.82estimated city fees at the inputs above
Line
How it is computed
Amount
Swimming pool permit
flat
$730.28
Plan review
1 hours × $100
$100
Digital filing fee (1%, $18.54 minimum)
1% of $830.28 (minimum $18.54)
$18.54
The page's own example: “Typical pool, one hour of review: $730.28 + $100 + $18.54 = about $849.”
Not included: Additional equipment trade items ($50 each); review beyond the hours entered; the pool barrier and cover.
Source: PDSD fee schedule effective July 1, 2026. Read the Tucson pool permit page, which quotes the rule and records when it was last verified (Oct 2026).
Tucson roof replacement permit fee
A same-material reroof needs no permit; structural roof work is priced on the signed contract value plus 50% plan review and the 1% filing fee.
$187.14estimated city fees at the inputs above
Line
How it is computed
Amount
Building permit fee
$89.45 + 1 × $22.95 per 1,000 above 2,000
$112.40
Plan review (50% of permit fee)
$89.45 + 1 × $22.95 per 1,000 above 2,000 × 0.5
$56.20
Digital filing fee (1%, $18.54 minimum)
1% of $168.60 (minimum $18.54)
$18.54
The page's own example: “$3,000 sheathing repair: $89.45 + $22.95 = $112.40; review $56.20; filing $18.54; about $187.”
Not included: Like-for-like reroofs need no permit and pay nothing.
Bathroom plumbing or electrical work is a trade permit ($150 first item, $50 each additional); moving walls takes a valuation-based alteration permit plus 50% plan review; both add the 1% filing fee.
$168.54estimated city fees at the inputs above
Line
How it is computed
Amount
Trade permit items
$150
$150
Digital filing fee (1%, $18.54 minimum)
1% of $150 (minimum $18.54)
$18.54
The page's own example: “One fixture on new piping: $150 + $18.54 = about $169.”
Not included: Same-spot toilet swaps and finish work need no permit; Pima County Wastewater review for a relocated toilet.
Trade-only kitchen work is $150 for the first item and $50 each additional; layout or structural remodels take a valuation-based alteration permit plus 50% plan review; both add the 1% filing fee.
$168.54estimated city fees at the inputs above
Line
How it is computed
Amount
Trade permit items
$150
$150
Digital filing fee (1%, $18.54 minimum)
1% of $150 (minimum $18.54)
$18.54
The page's own example: “A new dishwasher alone is about $169.”
Not included: Cabinets, counters and finishes need no permit; the penalty for starting before the permit.
An AC, furnace or heat pump replacement is a flat trade permit: $150 for the first item (up to two units) and $50 for each additional, plus the 1% filing fee.
$168.54estimated city fees at the inputs above
Line
How it is computed
Amount
Trade permit, first item
flat
$150
Each additional trade item
0 units × $50 (first 1 units free)
$0
Digital filing fee (1%, $18.54 minimum)
1% of $150 (minimum $18.54)
$18.54
The page's own example: “AC or furnace replacement, or both together: $150 + $18.54 = about $169.”
Not included: Full duct redesigns may be assigned a valuation instead; same-size swamp cooler swaps are exempt.
Source: PDSD fee schedule effective July 1, 2026. Read the Tucson hvac permit page, which quotes the rule and records when it was last verified (Oct 2026).
Tucson adu permit fee
A casita is valued at $170.80 per sq ft and pays the valuation-based building permit fee, 50% plan review (waived for a model plan) and the 1% filing fee.
The page's own example: “review $610.61; filing $18.54; about $1,850.”
Not included: Development impact fees for parks, streets and police (use the city's calculator).
Source: PDSD fee schedule effective July 1, 2026. Read the Tucson adu permit page, which quotes the rule and records when it was last verified (Oct 2026).
What the estimate covers
City fees only, on the ordinary residential path each page prices: the building or trade permit plus the mandatory lines the city adds to it. It leaves out whatever the page says is separate (a designer's fee, a contractor's licence, a utility connection) and anything the page does not price. Fee schedules change on the city's budget cycle; the month each page was last verified is Oct 2026, and the verification method explains how changes are caught.
Frequently asked questions
review $113.58; filing fee $18.54; about $359. Every shed needs a permit; where a building permit fee applies it runs off the valuation table ($29.56 per sq ft for detached storage) plus 50% plan review and a 1% filing fee.
150 ft wood fence: $28.08 + 2 × $5.62 = $39.32; review $50; filing $18.54; about $108.. Every fence or wall needs a zoning permit priced on length (wood or metal) or wall face area (masonry), plus at least half an hour of review and the 1% filing fee.
$8,000 deck: $89.45 + 6 × $22.95 = $227.15; review $113.58; filing $18.54; about $359.. A deck over 30 in (or in a setback) pays a valuation-based building permit fee on the signed contract value, plus 50% plan review and the 1% filing fee.
Typical pool, one hour of review: $730.28 + $100 + $18.54 = about $849.. A private residential pool is a flat $730.28 (a stand-alone spa $337.05) plus plan review at $100 an hour and the 1% filing fee.
$3,000 sheathing repair: $89.45 + $22.95 = $112.40; review $56.20; filing $18.54; about $187.. A same-material reroof needs no permit; structural roof work is priced on the signed contract value plus 50% plan review and the 1% filing fee.
Every line is read off the Tucson permit pages on this site, which quote the city's own fee schedule, bulletin or ordinance and record the month the sources were last verified (Oct 2026). The calculator holds no fee of its own.