City fee lines from the Washington permit pages, computed for your project. Sourced, verified Nov 2026.
Verified Nov 2026Calculator
This calculator applies the fee lines quoted on the Washington permit pages: the city's own plan review, permit and surcharge figures, as published by the Department of Buildings. Pick a project, change the inputs, and the breakdown shows each line and how it is computed. 9 of 10 project types have a computable formula on their page; the rest show the page's own figure.
DOB prices alteration and repair permits (decks, remodels, roof work that needs a permit) at $30 plus 2% of the construction cost for jobs over $1,000 ($36.30 under $500, $71.50 from $501 to $1,000), and adds a 10% technology fee to every permit line.
For building permits, half of the permit fee is paid as the filing fee when you apply (instant trade permits are applied for, paid and issued online) and the balance at issuance; the calculator shows the whole fee.
The pages work from the 2017 DC Building Code (12-A DCMR); in a historic district or on a landmark, 105.2.5 removes the exemptions (in-kind reroof, small shed, prefab pool, fence repair), and DC's fee rule lists historic-only permits at $33 ($36.30 with the 10%), a line DOB's online schedule does not show.
One- and two-family homes apply through DOB's Permit Wizard, which estimates the fee; trade permits (electrical, plumbing, gas, mechanical) are pulled only by DC-licensed master tradespeople, through Citizen Access or the Permit Wizard, and supplemental permits cannot be issued online in a historic or fine arts district.
Washington shed permit fee
A new shed over 50 sq ft (or 10 ft or taller, or a second small shed on the lot) pays DOB's flat $65 new-shed fee plus the 10% technology fee, $71.50; a single shed up to 50 sq ft and under 10 ft needs no permit outside historic districts and flood hazard areas.
Exempt: No permit for a single garden storage shed of 50 sq ft or less, under 10 ft in overall height, accessory to a one- or two-family home, with no other exempted shed on the lot; the exemption does not apply in a historic district, on a landmark or in a flood hazard area (12-A DCMR 105.2 item 8).
$71.50estimated city fees at the inputs above
Line
How it is computed
Amount
New shed fee
flat
$65
Technology fee (10%)
10% of $65
$6.50
The page's own example: “Anything larger needs a shed permit from the Department of Buildings, which costs $71.50 with the technology fee.”
Not included: Shed repairs (no flat line; priced on the alteration and repair rates), the electrical permit for wiring or lights, and any Green Building Fee, which the page says is not published for sheds.
Source: DOB fee schedule, new garage or new shed line. Read the Washington shed permit page, which quotes the rule and records when it was last verified (Nov 2026).
Washington fence permit fee
Every new fence on private property, whatever its height, pays DOB's $33 fence fee plus the 10% technology fee, $36.30; only repair in kind outside a historic district needs no permit.
$36.30estimated city fees at the inputs above
Line
How it is computed
Amount
Fence on private property
flat
$33
Technology fee (10%)
10% of $33
$3.30
The page's own example: “the fee schedule prices a fence on private property, installation or repair, at $33 plus the 10% technology fee: $36.30.”
Not included: A fence in public space in front of the house is a separate DDOT public space permit; the surveyor's plat.
Source: DOB fee schedule, fence on private property line. Read the Washington fence permit page, which quotes the rule and records when it was last verified (Nov 2026).
Washington deck permit fee
Every deck, at any height, pays the alteration and repair rates on its construction cost, $30 plus 2% plus the 10% technology fee, $363 on a $15,000 deck.
$363estimated city fees at the inputs above
Line
How it is computed
Amount
Alteration and repair base fee
flat
$30
2% of the construction cost
2% of $15,000
$300
Technology fee (10%)
10% of $330
$33
The page's own example: “a $15,000 deck pays ($30 + $300) x 1.10 = $363”
Not included: The electrical permit for deck outlets or lights; the surveyor's plat and any design professional.
Source: DOB fee schedule, Alteration and Repair lines, plus the 10% technology fee. Read the Washington deck permit page, which quotes the rule and records when it was last verified (Nov 2026).
Washington pool permit fee
A pool up to 15,000 gallons pays DOB's $260 swimming pool permit plus the 10% technology fee, $286; only a prefab pool under 24 in deep, 1,000 gallons or less, entirely above ground with no circulation system is exempt, and not on a historic property or in a flood hazard area.
$286estimated city fees at the inputs above
Line
How it is computed
Amount
Swimming pool permit (up to 15,000 gallons)
flat
$260
Technology fee (10%)
10% of $260
$26
The page's own example: “$286 for a pool up to 15,000 gallons: the $260 fee plus DC's 10% technology fee.”
Not included: Pools over 15,000 gallons ($260 plus $33 per 1,000 gallons, but the page says the schedule does not say which gallons count, so take the Permit Wizard's estimate); the electrical and plumbing permits for the pump, lights and water connection.
Source: DOB fee schedule, swimming pool line. Read the Washington pool permit page, which quotes the rule and records when it was last verified (Nov 2026).
Washington roof replacement permit fee
A reroof in kind outside a historic district, landmark or flood hazard area needs no permit; roof work that does is priced on the alteration and repair lines, $30 plus 2% of the cost plus the 10% technology fee, $363 on a $15,000 job.
$363estimated city fees at the inputs above
Line
How it is computed
Amount
Alteration and repair base fee
flat
$30
2% of the construction cost
2% of $15,000
$300
Technology fee (10%)
10% of $330
$33
The page's own example: “A $15,000 roof job pays ($30 + $300) x 1.10 = $363”
Not included: Roof-mounted solar (a $250 Instant Permit) and electrical work on the roof; historic-only permits, which DC's fee rule lists at $33 but DOB's online schedule does not show.
Source: DOB fee schedule, Alteration and Repair lines (no roofing line), plus the 10% technology fee. Read the Washington roof replacement permit page, which quotes the rule and records when it was last verified (Nov 2026).
Washington bathroom remodel permit fee
Tile, vanity and in-place toilet, sink or faucet swaps need no permit; a remodel that adds or moves fixtures, opens concealed piping or changes walls pays the alteration permit, $30 plus 2% of the cost plus the 10% technology fee, $583 on $25,000.
$583estimated city fees at the inputs above
Line
How it is computed
Amount
Alteration and repair base fee
flat
$30
2% of the construction cost
2% of $25,000
$500
Technology fee (10%)
10% of $530
$53
The page's own example: “a $25,000 bathroom pays ($30 + $500) x 1.10 = $583”
Not included: Plumbing permits ($28.60 for the first fixture and $22 for each additional, with the 10%) and electrical permits, pulled by licensed master tradespeople.
Source: DOB fee schedule, Alteration and Repair lines, plus the 10% technology fee. Read the Washington bathroom remodel permit page, which quotes the rule and records when it was last verified (Nov 2026).
Washington kitchen remodel permit fee
Cabinets, counters, tile and an in-place sink swap need no permit; a remodel that moves walls, plumbing, gas or wiring pays the alteration permit, $30 plus 2% of the cost plus the 10% technology fee, $913 on $40,000.
$913estimated city fees at the inputs above
Line
How it is computed
Amount
Alteration and repair base fee
flat
$30
2% of the construction cost
2% of $40,000
$800
Technology fee (10%)
10% of $830
$83
The page's own example: “a $40,000 kitchen pays ($30 + $800) x 1.10 = $913”
Not included: Trade permits priced per item (plumbing $28.60 for the first fixture and $22 each additional, electrical instant $22, gas appliance instant $28.60, with the 10%), pulled by licensed master tradespeople.
Source: DOB fee schedule, Alteration and Repair lines, plus the 10% technology fee. Read the Washington kitchen remodel permit page, which quotes the rule and records when it was last verified (Nov 2026).
Washington electrical panel permit fee
A panel replacement or service upgrade is an electrical permit pulled by a DC-licensed master electrician: $20 for one panel board, or the $59 Heavy-Up Instant Permit for an upgrade to a maximum of 200 amps, each plus the 10% technology fee.
$22estimated city fees at the inputs above
Line
How it is computed
Amount
Panel board or feeder replacement
flat
$20
Technology fee (10%)
10% of $20
$2
The page's own example: “A straight panel swap on an existing service therefore starts at $22, and a heavy-up to a maximum of 200 amps filed as an Instant Permit costs $64.90.”
Not included: Additional panels ($8 each), itemized service and meter equipment ($39 up to 200 A, $52 for 201 to 400 A) and added circuits; any building permit the code official requires.
Source: DOB supplemental (electrical) permit schedule and Heavy-Up Instant Permit. Read the Washington electrical panel permit page, which quotes the rule and records when it was last verified (Nov 2026).
Washington hvac permit fee
Even a like-for-like swap needs trade permits pulled by licensed masters, priced per piece of equipment: the $46 Mechanical Instant Permit for one AC unit, the $26 Gas Fitting Instant Permit for one gas appliance, and an electrical permit if the electrician files one, each plus the 10% technology fee.
$79.20estimated city fees at the inputs above
Line
How it is computed
Amount
Mechanical Instant Permit (one AC unit up to 10 tons) optional
flat
$46
Gas Fitting Instant Permit (one gas appliance) optional
flat
$26
Technology fee (10%)
10% of $72
$7.20
The page's own example: “For scale only: a new 3-ton AC unit installed under the mechanical instant permit ($50.60) plus a gas furnace replacement under the gas instant permit ($28.60) is $79.20”
Not included: Ductwork repair or replacement (a $36.30 building Instant Permit), a building permit where the code official requires one, and new systems in an addition; window units and other self-contained systems with 10 pounds of refrigerant or less are exempt. The page prices only the first or a single unit; additional units are not priced on the page.
Source: DOB supplemental permit schedule and Mechanical and Gas Fitting Instant Permits. Read the Washington hvac permit page, which quotes the rule and records when it was last verified (Nov 2026).
Washington adu permit fee
DOB's fee schedule has no ADU line: a basement or attic conversion is priced as an alteration ($30 plus 2% of the cost plus 10%), while for a new garage apartment the page says which line applies (the $65 new-garage line or $0.03 per cubic foot, plus 10%) is not published.
What the city page states: A basement or attic conversion is an alteration: $30 plus 2% of the construction cost, plus 10%, so a $60,000 conversion pays ($30 + $1,200) x 1.10 = $1,353.
Not computed here: The page gives its figures for scale only: which line prices a garage apartment is not published, so the page sends readers to the Permit Wizard's estimate, and trade permits are added per item.
City fees only, on the ordinary residential path each page prices: the building or trade permit plus the mandatory lines the city adds to it. It leaves out whatever the page says is separate (a designer's fee, a contractor's licence, a utility connection) and anything the page does not price. Fee schedules change on the city's budget cycle; the month each page was last verified is Nov 2026, and the verification method explains how changes are caught.
Frequently asked questions
Anything larger needs a shed permit from the Department of Buildings, which costs $71.50 with the technology fee.. A new shed over 50 sq ft (or 10 ft or taller, or a second small shed on the lot) pays DOB's flat $65 new-shed fee plus the 10% technology fee, $71.50; a single shed up to 50 sq ft and under 10 ft needs no permit outside historic districts and flood hazard areas.
the fee schedule prices a fence on private property, installation or repair, at $33 plus the 10% technology fee: $36.30.. Every new fence on private property, whatever its height, pays DOB's $33 fence fee plus the 10% technology fee, $36.30; only repair in kind outside a historic district needs no permit.
a $15,000 deck pays ($30 + $300) x 1.10 = $363. Every deck, at any height, pays the alteration and repair rates on its construction cost, $30 plus 2% plus the 10% technology fee, $363 on a $15,000 deck.
$286 for a pool up to 15,000 gallons: the $260 fee plus DC's 10% technology fee.. A pool up to 15,000 gallons pays DOB's $260 swimming pool permit plus the 10% technology fee, $286; only a prefab pool under 24 in deep, 1,000 gallons or less, entirely above ground with no circulation system is exempt, and not on a historic property or in a flood hazard area.
A $15,000 roof job pays ($30 + $300) x 1.10 = $363. A reroof in kind outside a historic district, landmark or flood hazard area needs no permit; roof work that does is priced on the alteration and repair lines, $30 plus 2% of the cost plus the 10% technology fee, $363 on a $15,000 job.
Every line is read off the Washington permit pages on this site, which quote the city's own fee schedule, bulletin or ordinance and record the month the sources were last verified (Nov 2026). The calculator holds no fee of its own.