This calculator applies the fee lines quoted on the Long Beach permit pages: the city's own plan review, permit and surcharge figures, as published by the Development Services Department. Pick a project, change the inputs, and the breakdown shows each line and how it is computed. 10 of 10 project types have a computable formula on their page; the rest show the page's own figure.
- The pages price the schedule in force before October 1, 2026; the City Council approved a new fee schedule effective October 1, 2026.
Long Beach shed permit fee
A shed over 120 sq ft is valued at $71.07 per sq ft and pays the building permit fee, an 85% plan check, a zoning plan check, the $115 processing fee and small state and records fees.
| Line | How it is computed | Amount |
|---|---|---|
| Building permit fee | $149 + 9 × $16 per 1,000 above 2,000 | $293 |
| Plan check (85% of building fee) | 85% of $293 | $249.05 |
| Zoning plan check (capped at 95% of plan check) | 95% of $249.05 | $236.60 |
| Processing fee | flat | $115 |
| State seismic fee | 11 × $0.13 per 1,000 $ or fraction | $1.43 |
| Green-building fee | flat | $1 |
| Records fee (5%, $35 minimum) | 5% of $293 (minimum $35) | $35 |
Long Beach fence permit fee
A fence or wall over the exemption heights (6 ft 6 in wood, 4 ft masonry) is valued per lineal foot and pays the building permit fee, an 85% plan check, a zoning plan check, the $115 processing fee and small state and records fees.
| Line | How it is computed | Amount |
|---|---|---|
| Building permit fee | $149 + 10 × $16 per 1,000 above 2,000 | $309 |
| Plan check (85% of building fee) | 85% of $309 | $262.65 |
| Zoning plan check (capped at 95% of plan check) | 95% of $262.65 | $249.52 |
| Processing fee | flat | $115 |
| State seismic fee | 12 × $0.13 per 1,000 $ or fraction | $1.56 |
| Green-building fee | flat | $1 |
| Records fee (5%, $35 minimum) | 5% of $309 (minimum $35) | $35 |
Long Beach deck permit fee
A deck that fails any of the four exemption tests is valued at $47.70 per sq ft and pays the building permit fee, an 85% plan check, a zoning plan check, the $115 processing fee and small state and records fees.
| Line | How it is computed | Amount |
|---|---|---|
| Building permit fee | $149 + 8 × $16 per 1,000 above 2,000 | $277 |
| Plan check (85% of building fee) | 85% of $277 | $235.45 |
| Zoning plan check (capped at 95% of plan check) | 95% of $235.45 | $223.68 |
| Processing fee | flat | $115 |
| State seismic fee | 10 × $0.13 per 1,000 $ or fraction | $1.30 |
| Green-building fee | flat | $1 |
| Records fee (5%, $35 minimum) | 5% of $277 (minimum $35) | $35 |
Long Beach pool permit fee
A pool over 18 in deep gets a combination permit at 150% of the valuation-based building fee, plus an 85% plan check, a zoning plan check, NPDES stormwater fees, the $115 processing fee and state and records fees.
| Line | How it is computed | Amount |
|---|---|---|
| Combination permit (150% of building fee) | $786 + 10 × $10 per 1,000 above 50,000 × 1.5 | $1,329 |
| Plan check (85% of building fee) | $786 + 10 × $10 per 1,000 above 50,000 × 0.85 | $753.10 |
| Zoning plan check | 0.5% of $60,000 (minimum $310) | $310 |
| NPDES stormwater review | 60 × $2 per 1,000 $ or fraction | $120 |
| NPDES plan check | 75% of $120 | $90 |
| Processing fee | flat | $115 |
| State seismic fee | 60 × $0.13 per 1,000 $ or fraction | $7.80 |
| Green-building fee | 3 × $1 per 25,000 $ or fraction | $3 |
| Records fee (5%) | 5% of $1,329 | $66.45 |
Long Beach roof replacement permit fee
Every reroof beyond a 100 sq ft repair is an express permit priced on IB-077 valuation per roofing square, with the $115 processing fee and state fees and no plan check.
| Line | How it is computed | Amount |
|---|---|---|
| Building permit fee | $149 + 8 × $16 per 1,000 above 2,000 | $277 |
| Processing fee | flat | $115 |
| State seismic fee | 10 × $0.13 per 1,000 $ or fraction | $1.30 |
| Green-building fee | flat | $1 |
Long Beach bathroom remodel permit fee
A bathroom remodel is valued at $5,000 per plumbing fixture and issued as a combination permit at 150% of the building fee plus the $115 processing fee and state fees; relocations add an 85% plan check and a records fee.
| Line | How it is computed | Amount |
|---|---|---|
| Combination permit (150% of building fee) | $149 + 13 × $16 per 1,000 above 2,000 × 1.5 | $535.50 |
| Processing fee | flat | $115 |
| State seismic fee | 15 × $0.13 per 1,000 $ or fraction | $1.95 |
| Green-building fee | flat | $1 |
Long Beach kitchen remodel permit fee
A kitchen remodel is valued at $40,000 per 100 sq ft and issued as a combination permit at 150% of the building fee plus the $115 processing fee and state fees; layout changes add an 85% plan check and a records fee.
| Line | How it is computed | Amount |
|---|---|---|
| Combination permit (150% of building fee) | $441 + 28 × $11 per 1,000 above 20,000 × 1.5 | $1,123.50 |
| Processing fee | flat | $115 |
| State seismic fee | 48 × $0.13 per 1,000 $ or fraction | $6.24 |
| Green-building fee | 2 × $1 per 25,000 $ or fraction | $2 |
Long Beach electrical panel permit fee
A panel changeout or service upgrade is an itemized electrical permit ($23 service to 200 A or $34 to 400 A, plus $17 per panel) with a $100 minimum and the $115 processing fee; upgrades above 200 A add plan check.
| Line | How it is computed | Amount |
|---|---|---|
| Service | $23 | $23 |
| Panel | flat | $17 |
| Minimum permit fee | brings the total up to the $100 minimum | $60 |
| Processing fee | flat | $115 |
Long Beach hvac permit fee
An HVAC changeout is an itemized mechanical permit (forced-air unit $15, compressor $16, air handler $22) with a $100 minimum and the $115 processing fee; systems over 33,000 Btu/hr add plan check and energy review.
| Line | How it is computed | Amount |
|---|---|---|
| Forced-air unit optional | flat | $15 |
| Comfort-cooling compressor optional | flat | $16 |
| Air handler or fan coil optional | flat | $22 |
| Minimum permit fee | brings the total up to the $100 minimum | $47 |
| Processing fee | flat | $115 |
Long Beach adu permit fee
An ADU is one combination permit at 150% of the valuation-based building fee ($175.92 per sq ft new, $105 conversion), plus an 85% plan check, zoning plan check, NPDES fees, the $115 processing fee, records and C&D review fees.
| Line | How it is computed | Amount |
|---|---|---|
| Combination permit (150% of building fee) | $1,264 + 6 × $6 per 1,000 above 100,000 × 1.5 | $1,950 |
| Plan check (85% of building fee) | $1,264 + 6 × $6 per 1,000 above 100,000 × 0.85 | $1,105 |
| Zoning plan check | 0.5% of $105,552 | $527.76 |
| NPDES stormwater review optional | 106 × $2 per 1,000 $ or fraction | $212 |
| NPDES plan check optional | 75% of $212 | $159 |
| Processing fee | flat | $115 |
| Records fee (5%) | 5% of $1,950 | $97.50 |
| C&D program review (new construction) optional | flat | $230 |
What the estimate covers
City fees only, on the ordinary residential path each page prices: the building or trade permit plus the mandatory lines the city adds to it. It leaves out whatever the page says is separate (a designer's fee, a contractor's licence, a utility connection) and anything the page does not price. Fee schedules change on the city's budget cycle; the month each page was last verified is Sep 2026, and the verification method explains how changes are caught.
Frequently asked questions
Other city calculators
- Albuquerque, NM
- Baltimore, MD
- Charlotte, NC
- Chicago, IL
- Cincinnati, OH
- Dallas, TX
- Fort Worth, TX
- Houston, TX
- Indianapolis, IN
- Jacksonville, FL
- Kansas City, MO
- Los Angeles, CA
- Louisville, KY
- Miami, FL
- Milwaukee, WI
- Minneapolis, MN
- New York City, NY
- Philadelphia, PA
- Phoenix, AZ
- Pittsburgh, PA
- Portland, OR
- Sacramento, CA
- San Antonio, TX
- San Diego, CA
- San Francisco, CA
- San Jose, CA
- Seattle, WA
- St. Louis, MO
- Tucson, AZ
Related: All cities · Research: fees compared across 30 cities · Long Beach permit guide