Utility Release: The notice a city inspector gives, or the homeowner passes along, that tells the electric utility a service or panel job passed inspection and the meter can be set or power restored. Some regions call it a cut-in card.
What a Utility Release Is
Changing a panel, meter base or service entrance usually means the utility has to shut off power and later turn it back on. It will not do the second part on trust. A utility release is the paper or electronic sign-off that says the city inspected the work and found it acceptable. It is separate from the permit itself, and from the final inspection card that ends the job.
Names differ by region. You may see it called a release to the utility, an energize authorization, a cut-in card or simply the green tag. Whatever the name, it connects two organizations that otherwise do not talk to each other: your building department and your power company.
How It Moves From the City to the Utility
In some cities the inspector sends the release electronically as soon as the inspection passes. In others the inspector leaves a card or tag on the panel and the electrician or homeowner has to call or upload it to the utility. A few utilities will not schedule a reconnection until they hold the release, and others require an application of their own for the meter work. Which process applies depends on both the city and the utility, and it can change, so ask each office how it expects to receive the release before the day of the inspection.
Why Power Sometimes Stays Off
The most common causes of delay are a failed inspection, an inspection that passed but was never reported to the utility, a permit still open because of an unrelated item, and the utility's own scheduling window. Homeowners often assume the passed inspection and the reconnection are one event. They are two. If the house has no power for a long stretch, the first call is to the inspection office to confirm the release went out, and the second is to the utility to confirm they have it.
Where It Comes Up on This Site
Releases come up on panel and service jobs, EV charger circuits and solar tie-ins. The overview is on the electrical panel permit page, and the city-by-city fee and eligibility comparison is in the electrical panel research. See also electrical service and final inspection for the sign-offs on either side of the release. Release rules are set by the city and the utility, not by a national code, so they vary. If your job involves a meter or service change, ask the permit office at application time how the release is sent, so it does not become the last surprise of the project.