What's Required in Tampa
- Electrical permit mandatory for panel replacements or service upgrades
- Work must comply with the 2026 Florida Electrical Code/NEC
- Proper grounding and bonding is required for all service replacements
- Notice of Commencement required if project value exceeds $2,500
- Electrical 'Release' from CSD is required before TECO can restore power
- Final electrical inspection required to close the permit and authorize power
Do You Need a Permit to Upgrade an Electrical Panel in Tampa?
Yes — panel work is one of the least optional permits in Tampa. Replacing or upgrading an electrical panel involves the service equipment for the whole house, so the city wants an inspection on the other side of it. Permit fees typically run $175–$250 through the City of Tampa Construction Services Division. An unpermitted panel is also one of the first things home inspectors and insurers flag, so the permit protects the resale, not just the wiring.
Upgrading From 100 to 200 Amps in Tampa
The classic project is moving from a 100-amp to a 200-amp service to feed an EV charger, heat pump, or induction range. In Tampa that's a permitted service upgrade like any panel change: permit, inspection, and a licensed electrician doing the work. Because the utility's service connection is involved, plan for coordination with your power company on disconnect and reconnect timing. Inspectors typically verify grounding and bonding, working clearances around the panel, and a properly labeled circuit directory before signing off.
How to Get a Electrical Panel Permit in Tampa
Step 1: Portal Login
Access Accela Citizen Access and select 'Electrical Residential'.
Step 2: Detail Service
Specify amperage (e.g. 200 Amp) and current TECO service details.
Step 3: Fee Payment
Pay the total permit fee ($175 minimum) online.
Step 4: Installation
Complete the work according to 2026 NEC standards.
Step 5: Inspection & Release
Schedule inspection; CSD notifies TECO for service restoration after passing.