What's Required in Fresno

  • Get an electrical permit before replacing or upgrading a panel or service.
  • List the service size and equipment on the Permit Affidavit Form.
  • Contact PG&E about any service disconnect, meter or reconnect work.
  • Install or verify smoke and carbon monoxide alarms when the job exceeds $1,000 in value.
  • Book the electrical inspection in Accela Citizen Access or by Voice Permits.
  • Pay the permit fees when the permit is issued; Fresno collects them at issuance.
  • Start work within 180 days of issuance; an approved inspection extends the expiration to 180 days from that inspection.

Do You Need a Permit to Replace an Electrical Panel in Fresno?

Yes. Fresno quotes the building code rule that anyone who intends to install, alter, repair or replace any electrical system must obtain the required permit, and nothing electrical is on the city's list of exempt work. A main panel upgrade, a service change or a subpanel all go through the Building and Safety Services Division. The city's building permit application even has a line for adding an MPU (main panel upgrade) when a solar system is part of the job.

Fresno Panel Rules by Scenario

What you are doingCity filingRule
Replace or upgrade a service up to 400 ampsSimple electrical permitFee schedule: services up to 400 amperes
Service over 400 amps up to 1,000 ampsComplex electrical permitFee schedule line
Panel upgrade plus new circuitsOne simple combination permitSchedule note on combinations
Panel upgrade with a new solar systemBuilding permit application, MPU boxPermit application form
New service or meter setElectrical permit plus PG&ECity links PG&E for service
Panel job over $1,000Smoke and CO alarm verificationRetrofit form

How Much Does a Panel Permit Cost in Fresno?

The Master Fee Schedule effective July 1, 2026 lists services of 600 volts or less and not over 400 amperes as a simple electrical item at $111.50. Every stand-alone electrical, mechanical or plumbing permit adds an administrative permit issuance fee of $27.08, so a typical 200-amp panel swap starts at $138.58. The schedule says the simple permit covers any item or combination of items on its simple lists, so new circuits, outlets or lighting on the same job do not add a second simple fee. A service over 400 amperes up to 1,000 amperes is a complex item at $935.79 plus the $27.08 issuance fee, $962.87.

Fee example: a 200-amp main panel upgrade valued at $4,500. Base $111.50 + $27.08 = $138.58. Stand-alone trade permits also carry the schedule's 12.83% General Plan surcharge and a $23.79 technology surcharge; the schedule names no base for the 12.83%, and its trade-permit section lists no state valuation surcharge. That adds about $14 on the $111.50 permit fee (about $18 if the city also applies it to the $27.08 issuance fee) and $23.79, for about $177 to $180. The schedule also lists a workers' compensation insurance verification charge of $33.84 per transaction in the trade-permit section; ask whether it applies to your permit. Doing the work without a permit can cost up to 4 times the permit fee.

How Fast Can You Get It, and Who Can Pull It?

Fresno's Building and Safety page lists same-day express permits for electrical, mechanical and plumbing work among its in-person services at City Hall, booked with QLess; ask at the counter whether your job qualifies. You can also apply in Accela Citizen Access. For a trade permit you complete the Permit Affidavit Form with the equipment listed. Contact PG&E about the service work as well; the city's Building and Safety page sends customers to PG&E to have gas or electric service established.

Permitted work exceeding $1,000 in value requires smoke and carbon monoxide alarms in the house. The city's verification form is normally used for exterior electrical equipment change-outs: the owner or tenant and the contractor sign it instead of having the inspector come inside.

Who Can Pull the Permit?

You can, as an owner-builder, if you do the work yourself or with your own employees and the structure is not offered for sale within a year of completion; the city's permit affidavit cites Business and Professions Code 7044 for this. The owner-builder checklist the city posts adds that, for home improvements, the site must be your principal residence, occupied for 12 months before the work is finished, and the exemption cannot be used on more than two structures in any three-year period. When you sign as an owner-builder you take full responsibility for the job, and anyone who contracts for or bids on a project valued at $500 or more (labor and materials) must be licensed by the Contractors State License Board. Apply online through Accela Citizen Access, the city's portal, or with in-person submittal help at City Hall.

How to Get a Electrical Panel Permit in Fresno

1

Size the service

Confirm the new panel's rating; up to 400 amps is a simple item, larger services are billed as complex items.

2

Complete the affidavit

Fill in the Permit Affidavit Form with the panel and any circuits, and the license or owner-builder declaration.

3

Get the permit

Book a same-day express permit through QLess, or apply in Accela Citizen Access.

4

Contact PG&E

Ask PG&E how it handles the service disconnect and reconnect for your panel job, and line it up with the inspection.

5

Inspect

Book the inspection in Accela Citizen Access or by Voice Permits and sign the alarm verification if needed.

Frequently Asked Questions

For a service up to 400 amps, the fee schedule effective July 1, 2026 lists $111.50 plus a $27.08 permit issuance fee, $138.58. With the 12.83% General Plan surcharge and the $23.79 technology surcharge, a typical panel swap comes to about $177 to $180; the schedule names no base for the 12.83%. Services over 400 amps are $935.79 plus the issuance fee, $962.87.
Fresno's Building and Safety page lists same-day express permits for electrical, mechanical and plumbing work among its in-person services; ask at the counter whether your job qualifies. Appointments are booked through QLess, and you list the equipment on the Permit Affidavit Form.
Plan on it for any job that changes the service. Fresno issues and inspects the electrical permit, while its Building and Safety page sends customers to PG&E to have gas or electric service established. Ask PG&E early how it handles the disconnect and reconnect for your panel swap.
Not on the simple permit. Fresno's schedule says the $111.50 simple permit includes any item or combination of items on its simple mechanical, plumbing and electrical lists, which cover services up to 400 amps, outlets, lighting and appliances.
Yes, with limits. Fresno's permit affidavit lets the property owner sign as an owner-builder under Business and Professions Code 7044 when you do the work yourself or with your own employees and do not sell within a year. The city's owner-builder checklist adds that the site must be your principal residence of 12 months and the exemption cannot cover more than two structures in three years. You take full legal responsibility for the job.