What's Required in St. Paul
- New, replaced or relocated plumbing fixtures and piping need a plumbing permit.
- Tile, paint, cabinets, countertops and similar finish work need no building permit.
- Non-maintenance alterations over $500, such as moving walls, need a general building permit.
- New or altered electrical circuits need an electrical permit with an $85 minimum.
- Bath exhaust ductwork falls under the ventilation permit at 1 percent of value, $85 minimum.
- Owner plumbing permits go only to owner-occupants of one- or two-family homes who do the work.
- Owners must keep one working bathroom, kitchen-type sink and bedroom during the work.
- All piping must be inspected before it is concealed and pass a final test before use.
Do you need a permit to remodel a bathroom in St. Paul?
Usually you need at least a plumbing permit. The Department of Safety and Inspections (DSI) requires a plumbing permit whenever you install new, alter, replace, repair, relocate or reinstall waste, vent, water or gas piping, and its fee schedule charges for each fixture whether set, roughed in or replaced. Swapping a toilet, vanity sink or tub is plumbing permit work by that reading. DSI has no page that names a like-for-like toilet swap; its fee schedule charges per fixture whether set, roughed in or replaced and its plumbing plan-review sheet treats a water closet installation in existing facilities as a permitted minor remodel. If you are only replacing a fixture on existing connections, confirm with the plumbing inspectors (651-266-9005). Tiling, painting, cabinets, countertops and similar finish work need no building permit. A general building permit comes in when the remodel goes beyond finish work and normal maintenance and is worth more than $500 in labor and materials, or when the state or city code requires one: moving walls, enlarging the room, adding a window, structural repairs.
Which permits does a bathroom remodel need?
- Plumbing permit for fixtures and piping, new or replaced.
- Electrical permit for new or altered circuits, such as a heated floor or new outlets.
- Ventilation permit for a new bath exhaust fan and its duct, priced as ventilation work.
- Building permit for walls, framing, windows or layout changes over $500.
How much do bathroom permits cost?
Plumbing under Legislative Code Section 33.04 is $92 per permit plus $36 for each fixture and $6 for each water supply fixture. Replacing one toilet starts at $92 + $36 = $128, plus $6 if the water supply counts, plus $1. A full set of toilet, sink and tub: $92 + 3 x $36 = $200, before the water supply items. Electrical is $15 per circuit with an $85 minimum. Bath exhaust ductwork is 1 percent of its value with an $85 minimum per dwelling unit. A building permit follows Table A, plus 65 percent plan review and the state surcharge of 0.0005 times the value: a $15,000 remodel is $379 + $246.35 + $7.50 = $632.85. Plumbing, gas and electrical permits add a $1 state surcharge on DSI's fee pages; ventilation permits use 0.0005 times the value ($0.50 up to $1,000). DSI's schedule applies the 65 percent plan check to every valuation over $1,000; no DSI page names sheds or decks specifically, but its garage schedule shows it on a detached garage. Ten percent of the estimated plan review fee, at least $85 and at most $5,000, must be paid before review begins; the ordinance does not say how it is credited, so the totals above are the schedule's figures.
| What you are doing | City filing | Rule |
|---|---|---|
| New tile, vanity cabinet, paint | No building permit | Finish work is exempt |
| Replace a toilet or sink | Plumbing permit | $92 + $36 per fixture |
| Replace tub and shower valve | Plumbing permit | Inspected before walls close |
| New exhaust fan and duct | Ventilation permit | 1% of value, $85 minimum |
| New circuit or heated floor | Electrical permit | $15 per circuit, $85 minimum |
| Move a wall or enlarge the room | General building permit | Valuation fee + 65% plan review |
| Starting without a permit | Penalty fee | Equal to the permit fee |
Can you do your own bathroom plumbing?
Yes, if you own and actually live in a one- or two-family dwelling; for a building permit DSI issues owner permits to the homesteading owner of a one- or two-family home. DSI's homeowner plumbing permit requires that you do all the work yourself and that a plumbing inspector approve your application before the permit is issued. While the work goes on you must keep a functioning bathroom, one kitchen-type sink and one bedroom. All piping must be inspected before it is concealed, and the final test must pass before the fixtures are used. Homeowner electrical permits are limited to a homesteading owner of a single-family home or the owner's side of a side-by-side duplex or townhome with rated walls, who does the wiring personally; it is unlawful for owners to wire property that is rented or occupied by others.
Who else may pull the permits?
Licensed plumbing and gas fitting contractors can apply for plumbing permits. A remodeler handling two or more trades on a one- to four-unit home needs a Minnesota residential remodeler or building contractor license; single-skill contractors such as tile installers need a City of Saint Paul license. DSI's older pages still show paper drop-off and an email address for applications, but its PAULIE page says phone, email and mail applications are no longer accepted, so apply in PAULIE. A plumbing permit expires if work stops for 180 days.
How to Get a Bathroom Remodel Permit in St. Paul
Decide the scope
Separate finish work from fixture, wiring, ventilation and wall changes to see which permits apply.
Prepare the affidavits
If you do the work, complete DSI's homeowner plumbing and electrical affidavits; otherwise confirm your contractors' licenses.
Apply in PAULIE
Submit each permit application; a plumbing inspector must approve a homeowner plumbing application before it is issued.
Rough-in inspections
Call for plumbing and electrical inspections before any piping or wiring is covered by walls, floors or ceilings.
Final approval
Pass the plumbing final test and the electrical final before using the new fixtures.