Permit Required? Required
Typical Fee Range $100–$250 Standard trade permit fee based on panel amperage.
Fee Method Flat fee

What's Required in New Orleans

  • Electrical permit required for any panel upgrade or replacement.
  • Work must meet current National Electrical Code (NEC) standards.
  • Panel must be accessible with 36 inches of front clearance.
  • Service disconnect must be clearly identified.
  • Grounding and bonding to water/gas lines must be verified.
  • Circuit directory must be permanently and clearly labeled.

How to Get a Electrical Panel Permit in New Orleans

1

Step 1: Hire Electrician

Ensure your contractor is licensed by the City of New Orleans.

2

Step 2: Online Permit

Contractor pulls the permit through the One Stop App.

3

Step 3: Utility Cut-off

Coordinate with Entergy for service disconnect and reconnect.

4

Step 4: Installation

Upgrade the panel and transfer circuits per code.

5

Step 5: Inspection

Inspector verifies safety before Entergy restores power.

Frequently Asked Questions

Only if you sign an owner-builder affidavit and pass a competency review.
Residential panel upgrades typically cost $100–$150.
Connecting the electrical system to metallic pipes for safety.