What's Required in Honolulu

  • Every panel, meter or service upgrade needs a permit; service equipment is never exempt.
  • A Hawaii-licensed electrical contractor must do the work and accept the project in HNL Build.
  • Houses outside flood zones with no DPP warning qualify for an instant online permit.
  • Townhome, apartment and flood-zone work needs a building permit with plans.
  • Request the electrical inspection by fax at least 48 hours ahead.
  • No more than one electric meter per legal dwelling unit.

Do You Need a Permit to Replace an Electrical Panel in Honolulu?

Yes. ROH 18-3.1(a) requires a building permit for any electrical work that is not exempted, and the one repair exemption that might help, for a licensed electrician's repairs valued at $2,500 or less in any 12-month period, does not apply to work that involves service entrance equipment. A panel, meter base or service upgrade is service entrance work, so it always needs a permit. In Honolulu the electrical work goes on a building permit issued by DPP.

For a single-family house or detached duplex, a Meter Replacement/Upgrade is on DPP's instant online permit list, as is a Rewire of Entire Structure. DPP's FAQ confirms that single-family dwellings are eligible for an instant online permit for an electrical meter upgrade, provided the property has no warning and is not in a flood zone. Otherwise a building permit with plans is required. DPP does not name a panel-only swap on its instant list; if the application is rejected as instant, file a permit with plans.

Honolulu Electrical Panel Work by Scenario

What you are doingCity filingRule
Service or meter upgrade at a houseInstant online permitOn DPP's instant list
Rewire the whole houseInstant online permitRewire of entire structure
Lot in a flood zone or with a DPP warningBuilding permit with plansInstant permit not allowed
Panel work in a townhome or apartmentBuilding permit with plansOnly fixture swaps and reroofs are instant
Small repair, no service equipmentNo permit up to $2,500 a yearLicensed electrician only
$3,000 panel and meter upgrade$7830 × $2.20 + $12
$6,000 service upgrade$14460 × $2.20 + $12

How Much Is an Electrical Panel Permit in Honolulu?

Honolulu prices the permit by the value of the work, labor and materials. From $1,000.01 to $20,000 the fee is $12 plus $2.20 for each $100, rounded up. A $3,000 panel and meter upgrade is 30 × $2.20 + $12 = $78; a $6,000 service upgrade is 60 × $2.20 + $12 = $144. An instant online permit needs no plans, so there is no plan review fee, and it is paid by credit or debit card in HNL Build. If the job needs a permit with plans, add 20% for plan review. A small job of $1,000 or less pays a flat $20 up to $500, or $8 plus $2.50 per $100 above that, so at most $33.

Who Can Pull the Permit?

Only a Hawaii-licensed electrical contractor can do the work. DPP's FAQ says all electrical and plumbing work must be performed by contractors licensed by the State under HRS Chapters 444 and 448E, and the owner-builder exemption in HRS 444-2.5 excludes electrical work unless the owner holds the license. HNL Build checks the contractor's classification and rejects an application whose contractor lacks it (its error message names Electrical C-13). The contractor must accept the project in HNL Build before the application can move forward.

Inspection and Hawaiian Electric

The electrician requests the inspection by faxing DPP's Electrical Inspection Request Form at least 48 hours (two working days) ahead. Hawaiian Electric's metering release is tied to a valid building permit: DPP notes it is not allowed on a special assignment inspection and may only be obtained after a permit is issued. Honolulu enforces the 2020 National Electrical Code, effective March 15, 2024 as an interim code, and allows no more than one electric meter per legal dwelling unit.

How to Get a Electrical Panel Permit in Honolulu

1

Hire a licensed electrician

Confirm the contractor's state license on the DCCA website; homeowners cannot do the work.

2

Check the property

Look up flood zone, warnings and zoning on DPP's Property Search to see if an instant permit is possible.

3

File in HNL Build

Apply for the instant online permit for a meter replacement or upgrade and pay by card; the permit issues at the end.

4

Do the work and inspect

The electrician faxes the Electrical Inspection Request Form at least two working days before the inspection.

5

Release and close

After approval Hawaiian Electric can set the meter, and the inspector closes the permit.

Frequently Asked Questions

Yes. Any electrical work needs a building permit unless exempt, and the small-repair exemption for licensed electricians (up to $2,500 in any 12-month period) excludes service entrance equipment. A house usually qualifies for an instant online permit for a meter replacement or upgrade.
No. DPP says all electrical work must be performed by contractors licensed by the State of Hawaii, and the owner-builder exemption in HRS 444-2.5 does not cover electrical work unless the owner is licensed for it.
It is based on the value of the job. A $3,000 upgrade costs $78 (30 x $2.20 plus $12) and a $6,000 service upgrade costs $144. Instant online permits carry no plan review fee and are paid by card.
DPP says the Hawaiian Electric metering release may only be obtained after a valid building permit has been issued, and it is not allowed on a special assignment inspection. Your electrician schedules the city inspection by fax at least 48 hours ahead.
DPP says the usual reason is that the property is in a flood zone, a special design district or cluster, or has a warning, advisory or violation. Those properties need a building permit with plans instead.