What's Required in Honolulu

  • ADU floor area is capped at 500 sq ft on lots up to 4,999 sq ft and 1,000 sq ft on larger lots.
  • Only one ADU per zoning lot; none in cluster or planned development housing or on landlocked lots.
  • Get an approved ADU Pre-Check Form before applying; it is valid 210 days from first approval.
  • Record a restrictive covenant limiting the ADU to long-term rental and barring a condo split.
  • Provide one extra parking space unless a rail or bus stop waiver applies.
  • New structures need an approved sewer capacity analysis.
  • ADUs and ohana units must complete CivCheck before applying in HNL Build.

How Much Does an ADU Permit Cost in Honolulu?

The city's building permit and plan review fees on an ADU run from about $2,640 on a $150,000 unit to $4,440 on a $300,000 unit. Honolulu charges by the value of the work: from $100,000.01 to $500,000 the permit fee is $700 plus $10 for every $1,000. A $150,000 ADU is 150 × $10 + $700 = $2,200; a $300,000 ADU is 300 × $10 + $700 = $3,700. The plan review fee, 20% of the permit fee, is paid when the plans are accepted ($440 and $740). Sewer, water and other agency charges are separate and DPP's fee calculator does not include them. A two-year fee waiver signed in July 2016 ran for two years; DPP's pages we read show no current waiver.

What Are the ADU Rules in Honolulu?

ADUs are governed by the Land Use Ordinance, LUO 21-5.50-3(a), as amended through Ordinance 25-2. The total floor area may not exceed 500 square feet for zoning lots up to 4,999 square feet or 1,000 square feet for zoning lots 5,000 square feet or more. Only one ADU is allowed per zoning lot, and none on lots in planned development housing or cluster housing, or on landlocked lots. The ADU must meet the development standards of the main house's district, including the 0.7 floor area ratio and, in general, yards of 10 feet in front and 5 feet at the sides and rear, and there must be enough sewer, water, road and fire capacity to serve it. It can be a new detached or attached unit, or a conversion of a legal structure, attic or basement.

Honolulu ADU Steps and Limits

What you are doingCity filingRule
Lot up to 4,999 sq ftADU up to 500 sq ftLUO 21-5.50-3(a)(1)(B)
Lot 5,000 sq ft or moreADU up to 1,000 sq ftLUO 21-5.50-3(a)(1)(B)
Before applyingApproved ADU Pre-Check FormValid 210 days after first approval
Before applyingRecorded restrictive covenantLong-term rental only, no condo split
ParkingOne extra spaceWaived near rail and some bus stops
$150,000 ADU$2,200 + $440 plan reviewROH 18-6.1, 18-6.2
$300,000 ADU$3,700 + $740 plan reviewROH 18-6.1, 18-6.2

What Has to Happen Before the Building Permit?

DPP will reject or suspend an ADU application without its prior approvals. First, get the ADU Pre-Check Form approved by the infrastructure agencies; the approval is only valid for 210 days after the first agency signs. Second, record a declaration of restrictive covenants with the Bureau of Conveyances. The LUO says the covenant must state that the ADU is for long-term residential occupancy only, not a bed and breakfast or vacation rental, and that the lot may not be put into a condominium property regime to sell the ADU separately. A new structure also needs an approved sewer capacity analysis. Since September 1, 2026, DPP requires eligible residential projects, which include ADUs and ohana units along with new construction, additions and alterations of single-family, two-family and duplex homes, to pass its CivCheck pre-check before the permit application in HNL Build; fences, retaining walls, general electrical and plumbing work, solar and quick permits are excluded.

Parking, Plans and Who Builds It

An ADU needs one off-street parking space on top of the house's, except within 0.5 mile of a rail station; in the Primary Urban Center and Ewa plan areas the space is also waived within 800 feet of a city bus stop. Plans must be stamped by a licensed architect or engineer when work on a one-story residence exceeds $180,000 or a two-story residence exceeds $162,000. An owner-builder exemption is for your own or your family's use; under HRS 444-2.5 leasing the structure within one year of completion is treated as evidence the work was for lease, so most rental ADUs need a licensed contractor. Electrical and plumbing must be licensed in any case.

How to Get a ADU Permit in Honolulu

1

Confirm the lot qualifies

Check zoning, lot size, flood zone and access on DPP's Property Search to find your size cap and any bar on ADUs.

2

Get the pre-check approved

Submit the ADU Pre-Check Form to the infrastructure agencies; the approval lasts 210 days from the first sign-off.

3

Record the covenant

Record the declaration of restrictive covenants with the Bureau of Conveyances using DPP's template.

4

Run CivCheck and apply

Complete CivCheck, then apply in HNL Build with the CivCheck ID and upload plans to ePlans; pay the plan review fee.

5

Build and inspect

Pay the permit fee at issuance, pass the required inspections, and have the inspector close the permit.

Frequently Asked Questions

The Land Use Ordinance caps the total floor area at 500 square feet on zoning lots up to 4,999 square feet and 1,000 square feet on lots of 5,000 square feet or more. The ADU must also fit the floor area ratio and yards of the main house's district.
No. The recorded covenant must state that the ADU may only be used for long-term residential occupancy and may not be used as a bed and breakfast home or transient vacation unit. The lot also cannot be condominiumized to sell the ADU separately.
Usually one off-street space in addition to the house's. It is waived within 0.5 mile of a rail station, and in the Primary Urban Center and Ewa plan areas within 800 feet of a city bus stop, unless a waiver was already used for an ohana unit on the lot.
It is the form the infrastructure agencies sign to confirm there is enough sewer, water and access capacity for the unit. DPP requires an approved pre-check and a recorded restrictive covenant before you submit the building permit application, and the pre-check approval is valid for 210 days after the first agency approves it.
An ohana dwelling is a second unit that can only be occupied by people related by blood, marriage or adoption to the family in the main house, with its own zoning limits. An ADU has no family requirement but may only be used for long-term residential occupancy.