What's Required in Aurora

  • A building permit is required for a shed larger than 120 square feet of floor area.
  • Sheds under the permit size must still meet the city's zoning rules on placement.
  • Submit a project plan and a plot plan showing distances to property lines and utility easements.
  • Pay the permit fee after plan approval and before construction starts.
  • Expect a framing inspection; new wiring needs its own electrical permit and inspection.
  • A hired builder must hold an Aurora contractor license; owners may file for their own home.
  • The permit expires if work does not start within six months or finish within one year.

Do I need a permit for a shed in Aurora?

Only if it is big. The City of Aurora Building Division's home improvement handbook says a building permit is required for sheds larger than 120 square feet of floor area, and that smaller sheds need no building permit. Its permit chart puts it the other way round: storage sheds need a permit unless the shed is less than 120 sq. feet. Either way, a typical 8x10 shed is exempt and a 10x14 shed is not. Aurora's shed rule comes from its Do It Right home improvement handbook, dated March 2019; confirm it still applies at 303.739.7420.

No permit does not mean no rules. The handbook warns that a small shed must still comply with the city's zoning regulations on where it may be placed on your property. Those placement rules live in the Unified Development Ordinance, which we could not open from the city's code host, so ask the Permit Center or check the city's Zoning Navigator for your lot before you pick a spot.

What does a shed permit cost in Aurora?

Sheds are not on Aurora's flat-rate fee sheet, so the fee follows the city's permit fee calculator, which works from the job's valuation. Two runs of the calculator (Adams County):

  • A $3,000 shed: permit fee $166 plus plan review $166 = $332, plus about $56.25 in estimated taxes.
  • A $10,000 shed: permit fee $334 plus plan review $334 = $668, plus about $187.50 in estimated taxes.

The calculator labels the plan review fee "if applicable". The handbook's chart marks sheds as needing a plan submittal, and our reading is that this triggers the plan review line, so the examples include both. The tax line is a deposit of the city's use tax, 3.75% of materials cost, plus 0.25% for Arapahoe County open space where that applies. One caution: the city also publishes a new-building fee table that charges utility (U) buildings $3.40 per square foot with a $2,000 minimum. It does not say whether that table or the calculator governs a backyard shed, so confirm with the Permit Center before you budget.

Shed scenarios at a glance

What you are doingCity filingRule
8x10 shedNoneUnder the 120 square feet line; zoning placement still applies
10x12 shed, exactly at the lineAsk firstThe handbook and chart word the 120 line differently; confirm
12x16 shedBuilding permitPlan and plot plan reviewed; framing inspection
Gazebo or pergolaBuilding permitGazebo permit unless less than 120 sq. feet; pergolas need one
PlayhouseUsually nonePermit if over 120 sq. ft. or more than one story tall
Shed with new wiringElectrical permit tooNew electrical work is a separate permit and inspection

What do I submit?

The handbook asks for a project plan and a plot plan. The plot plan is reviewed for setbacks to property lines and utility easements, so draw the shed to scale with its distance to each lot line and any easement. After approval you pay the permit fee before building, and an inspector checks the framing. The city lists a 36 inch frost depth for design, which matters if your shed sits on piers.

Who can build it?

You can pull the permit yourself for your own home: the city lets owners of up to three single family detached structures act as their own contractor after signing a Statement of Understanding. A hired builder must hold an Aurora contractor license. Apply online through the Aurora4Biz building portal or in person at the Permit Center, 15151 E. Alameda Parkway.

How to Get a Shed Permit in Aurora

1

Measure the floor area

Multiply length by width. Over 120 square feet needs a building permit; smaller sheds only need a zoning-compliant spot.

2

Check placement on your lot

Use the city's Zoning Navigator or ask the Permit Center about setbacks and easements before you choose a location.

3

Draw the plan and plot plan

Show the shed's size and framing, and on the plot plan its distance to every property line and easement.

4

Apply and pay

Submit through the Aurora4Biz building portal or at the Permit Center; the fee is estimated with the city's valuation calculator.

5

Build and call for inspection

Keep the approved plans on site and request the framing inspection online, by email or at 303.739.7420.

Frequently Asked Questions

The Building Division's handbook says a building permit is required for sheds larger than 120 square feet of floor area. An 8x10 or 10x10 shed is under that line. A shed of exactly 120 square feet sits where the handbook and the permit chart word the rule differently, so confirm it with the Permit Center at 303.739.7420.
Yes. The handbook says sheds below the permit size must still comply with the city's zoning regulations on where the shed may be placed on your property. Setbacks are in the Unified Development Ordinance; check your lot with the Zoning Navigator or ask the Permit Center before you build.
Sheds are not on the flat-rate list, so the city's valuation calculator applies. It returned $332 (permit plus plan review) for a $3,000 shed and $668 for a $10,000 shed, plus a use tax deposit on materials. The city's new-building table for utility buildings has a $2,000 minimum; ask which method the Permit Center uses for your shed.
Yes. Homeowners can obtain permits for work on their primary home, and the city's Statement of Understanding lets owners of up to three single family detached structures act as their own contractor. Anyone you hire must hold an Aurora contractor license.
The city's permit chart lists a framing inspection for storage sheds that need a permit, and the handbook says inspectors check that the work matches the approved plans. If you run power to the shed, the electrical work adds its own inspection.