What's Required in Aurora
- Furnace, central air conditioner and evaporative cooler replacements always need a permit.
- No plan submittal is required for a residential replacement.
- Gas piping work always needs a permit.
- HVAC contractors need an Aurora Mechanical Systems Contractor license.
- Electricians and plumbers you hire need State of Colorado master's and contractor's licenses.
- Report equipment and materials cost so the city can collect use tax.
- Air conditioners and swamp coolers need mechanical and electrical final inspections.
Do I need a permit to replace a furnace or AC in Aurora?
Yes. The City of Aurora Building Division's permit chart says furnace replacements and central air conditioning always need a permit, with no plan submittal. Swamp (evaporative) coolers always need one too, and so does gas piping. A window air conditioner needs no permit unless it is hard-wired. Like-for-like swaps count: the chart does not exempt a replacement unit of the same size. Aurora's chart rule comes from its Do It Right home improvement handbook, dated March 2019; confirm it still applies at 303.739.7420.
How much is an HVAC permit in Aurora?
Aurora prices common HVAC jobs with flat fees. From the city's 2026 flat-rate fee sheet:
- Furnace replacement: $201.
- Air conditioner replacement: $201.
- Evaporative cooler replacement: $201.
- Furnace and air conditioner replacement together: $300.
- Boiler replacement: $300.
- Furnace and water heater replacement: $292.
- Furnace, air conditioner and water heater replacement: $336.
Bundling saves money: a furnace and AC on one $300 permit cost less than two $201 permits. Use tax is separate. The flat fee does not change it, so you report materials cost and the city collects 3.75% of it, plus 0.25% in Arapahoe County; on $7,000 of equipment that is $262.50 to the city. Card payments online add at least 2.25%.
HVAC scenarios
| What you are doing | City filing | Rule |
|---|---|---|
| Furnace swap | Furnace permit, $201 | Mechanical inspection |
| Central AC replacement | AC permit, $201 | Mechanical and electrical final inspections |
| Furnace and AC at the same time | Combined permit, $300 | One flat fee for both |
| Furnace, AC and water heater | Combined permit, $336 | One flat fee for all three |
| Swamp cooler replacement | Evaporative cooler permit, $201 | Always needs a permit |
| Heat pump or ductless mini-split | Ask the Permit Center | Not named on the flat sheet; may use the valuation calculator |
Who can install it?
A heating and cooling company working in Aurora needs a city Mechanical Systems Contractor license, which requires an ICC Master Mechanical Contractor certification. Electricians and plumbers you hire need State of Colorado master's and contractor's licenses; Aurora issues no separate license. Ask the Permit Center whether an owner may do their own electrical or plumbing under the Statement of Understanding. Homeowners can obtain permits for work on their primary home; to act as your own contractor you sign the city's Statement of Understanding.
What inspections are required?
For an air conditioner or swamp cooler, the city's homeowner sheet lists mechanical and electrical final inspections. A furnace replacement gets a mechanical inspection, and a water heater replaced at the same time adds a plumbing final (plus an electrical final for an electric unit). Request inspections online through Aurora4Biz, by email, or at 303.739.7420.
What about new systems?
The flat fees are listed for replacements. The sheet does not name new installations, so ask the Permit Center how a new system or new ductwork is priced; the valuation calculator returns a $214 permit fee for a $5,000 job. The chart says a boiler over 400K btu needs plans.
How to Get a HVAC Permit in Aurora
Pick the right flat fee
Match your job to the 2026 flat-rate sheet; bundle furnace, AC and water heater on one permit to save.
Check the installer
Look up the company in the city's contractor lookup for a Mechanical Systems Contractor license.
Apply and pay
File through the Aurora4Biz building portal or at the Permit Center and pay the flat fee plus use tax.
Install the equipment
Keep the permit on site and follow the manufacturer's instructions and the adopted 2021 mechanical and fuel gas codes.
Pass the finals
Request mechanical and electrical final inspections online, by email or at 303.739.7420.