What's Required in Aurora
- A permit is required for any deck more than 30 inches above grade.
- A deck under 30 inches above grade needs a permit if it is attached to the house.
- Submit a project plan and a plot plan showing setbacks and utility easements.
- Design for the city's listed 40 psf deck load and 36 inches frost depth; ask the inspector how deep footings must go.
- Pass footing, framing rough and framing final inspections.
- Hired builders must hold an Aurora contractor license.
- Owner-builders must finish exterior work within one year of permit issuance.
Do I need a permit for a deck in Aurora?
Almost always. The City of Aurora Building Division's permit chart says a deck more than 30 inches above grade always needs a permit, and a deck less than 30 inches above grade needs one if it is attached to the house. The only deck the chart leaves out is a low, freestanding platform under 30 inches that is not fastened to the home. Replacing an existing deck counts as building one: the handbook treats new and replacement decks alike. Aurora's deck rule comes from its Do It Right home improvement handbook, dated March 2019; confirm it still applies at 303.739.7420.
How much is a deck permit in Aurora?
Aurora charges a flat fee for this job. The city's 2026 flat-rate fee sheet lists a single family residential deck at $402, the same as a single family patio cover, and the sheet's promise is "same project type = same permit fee", so a small deck and a large one pay the same. Two things come on top:
- The use tax deposit. The flat fee does not change city use tax, so you still report materials cost; the city collects 3.75% of materials cost, plus 0.25% for Arapahoe County open space if your home is in that county. On $8,000 of decking materials that is $300 in city use tax.
- A card fee of at least 2.25% if you pay online by credit card.
Deck scenarios
| What you are doing | City filing | Rule |
|---|---|---|
| Freestanding deck under 30 inches, not attached | None listed | Chart only requires a permit for low decks attached to the house; confirm, since the Permit column of the chart reads Yes for every deck row |
| Low deck attached to the house | Deck permit, $402 | Attached decks under 30 inches still need a permit |
| Deck more than 30 inches above grade | Deck permit, $402 | Always requires a permit; plans and plot plan |
| Tearing out and rebuilding a deck | Deck permit, $402 | New or replacement decks go through the same process |
| Adding a roof over the deck | Patio cover permit, $402 | Patio covers always need a permit |
| Ground-level concrete patio | None | No permit unless over 30 inches above grade |
What do I need to submit?
The handbook asks for a project plan and a plot plan. The plot plan is reviewed for setbacks to property lines and utility easements. The city also hands out a Colorado Chapter ICC building guide for uncovered decks and porches that you can fill in as your plan. Design numbers the city lists: a 40 psf deck load and a 36 inches frost depth; ask the inspector how deep your footings must go.
What inspections will I get?
For decks, patio covers and pergolas the city's homeowner sheet lists a caisson or footing inspection (do not pour or fill until it passes), then framing rough and framing final inspections. Request them online through Aurora4Biz, by email, or at 303.739.7420. Inspectors also offer free consultations during construction.
Can I build the deck myself?
Yes. Homeowners can obtain permits for work on their primary home, and owners of up to three single family detached structures can act as their own contractor after signing the city's Statement of Understanding. An owner-builder has one year from issuance to finish exterior work. If you hire a builder, the company needs an Aurora contractor license; check it with the city's online contractor lookup before you sign.
How to Get a Deck Permit in Aurora
Decide if your deck is covered
Measure the height above grade and note whether it attaches to the house; most decks need the $402 permit.
Draw the plan and plot plan
Use the city's uncovered deck building guide for framing details and draw the deck's distance to lot lines and easements.
Apply online or in person
Submit through the Aurora4Biz building portal or at the Permit Center, 15151 E. Alameda Parkway, and report your materials cost for use tax.
Pay and start work
Pay the $402 flat fee plus the use tax deposit once plans are approved, then begin construction.
Call for inspections
Request the footing inspection before filling holes, then the framing rough and final inspections.