Deferred Submittal: A portion of the design, often roof trusses or a fire sprinkler system, that the building department allows to be submitted for review after the permit is issued because a manufacturer or specialist prepares it later.
Why Some Parts Are Deferred
Some parts of a building cannot be drawn until the project is further along. Prefabricated roof trusses are designed by the truss manufacturer once the framing layout is fixed. Fire sprinkler layouts are drawn by a sprinkler contractor. Waiting for those drawings would delay the whole permit, so model codes such as the IBC and IRC allow the building official to accept them later.
Whether a city uses the option, and which items qualify, is a local decision.
Deferral is a favour from the building official, not an entitlement. The list of items that may be deferred is normally written on the plans and approved when the permit is issued.
How the Process Works
The main plans list each deferred item. The designer in charge of the project usually reviews the later drawings first and confirms they fit the overall design. Then the package goes to the city for approval. Work on that item generally cannot start, or at least cannot be inspected, until the city has approved the deferred drawings.
- The permit is issued without the deferred item.
- The specialist drawings are submitted later.
- The city approves them before installation.
Keep the approved deferred drawings with the permit set. Inspectors commonly compare what is installed with the approved deferred package, not the original plan set.
What It Changes for You
For a homeowner, a deferred submittal is mostly a scheduling matter. Ask your contractor or supplier when the drawings will be ready, because an inspection can be held up if the approved set is not on site. Truss drawings, for example, often need to be at the job when the inspector arrives.
The deferred item is not exempt from review. It is only reviewed on a different timeline, and the building department can still require corrections.
If a deferred item changes the design, for example a truss layout that loads the walls differently, the designer may need to revise the main plans and the city may ask for a resubmittal.
Where It Comes Up on This Site
Deferred items appear most often on larger work: additions, ADUs, and new roofs framed with trusses. Our home addition guide and ADU permit guide cover that kind of project. For how long review takes before and after issuance, see how long a building permit takes in 30 cities.
Large and engineered work is where deferred items matter most. For a simple deck, fence or like-for-like swap, deferred submittals are rarely part of the process, because there is nothing manufactured separately to wait for.