What's Required in Tulsa
- ADUs need a special exception in RE, RS, AG and AG-R districts and are allowed by right elsewhere.
- Only one ADU is allowed per lot, inside an accessory building.
- The ADU must be at least 10 feet behind the principal building.
- The ADU building's size limit is the accessory building limit plus 500 square feet.
- Exterior finish materials and roof pitch must match the house.
- Second-story windows within 10 feet of a side or rear lot line need translucent glazing or a 6-foot sill.
- Electrical, plumbing and mechanical permits are pulled by licensed, registered contractors.
Are ADUs allowed in Tulsa?
Yes, with a zoning catch. Section 45.031 of the Tulsa Zoning Code defines an ADU as a dwelling unit in an accessory building on the same lot as the house, such as a garage apartment. ADUs are allowed by special exception in RE, RS, AG and AG-R districts and by right in all other districts when accessory to a household living use. They are also allowed by right in the Neighborhood Infill Overlay and the neighborhood character overlays. Check your district and any overlay on the city's zoning map first: lots zoned RE, RS, AG or AG-R need the special exception, which goes to the Board of Adjustment.
What are Tulsa's ADU rules?
One ADU per lot, new or converted from an existing accessory building. The ADU must sit at least 10 feet behind the house. Size follows the accessory building limit (500 square feet or 40% of the house in most RS districts, 750 square feet or 40% in RE and RS-1) increased by 500 square feet. In the rear setback, a building with a second-floor ADU may be two stories or 25 feet tall, 18 feet to the top plate, and 3 feet from interior lot lines. Exterior materials and roof pitch must match the house. Second-story windows within 10 feet of a side or rear lot line need translucent glass or a 6-foot sill.
How much does an ADU permit cost in Tulsa?
Title 49 builds the total from several permits. Worked example for a 600 square foot detached ADU with $120,000 of structure-only value (the declared valuation leaves out electrical, mechanical and plumbing): building permit 120 x $6 per $1,000 = $720 (the application fee, $0.97 per $1,000 above $100,000, is credited). This reads Section 302.B as $6 per $1,000 of the whole valuation; the ordinance gives no worked example, so confirm the total with the Permit Center. Then electrical $230 base for up to 2,000 square feet plus $116 for 200-amp service ($98 for the first 100 amps plus $18) = $346; plumbing for four fixtures $81 + 3 x $3.31 = $90.93 plus a $35 water heater; mechanical for a furnace, condenser and ducts at $35 each = $105; certificate of occupancy: $34 for a new single-family home, duplex or townhouse and $70 for a new building with a building permit (Section 303); the city does not say which an ADU is. Using $70 the example is $1,366.93 ($2,316.93 with the $950 use-related special exception), before zoning, surcharges and utility fees. Every permit also carries the $5 system surcharge (Section 103) and a system development fee of $5.50 plus 8 percent of the permit fee (Section 117); building permits add the $4 state code fee plus 50 cents (Section 100), which may also apply to trade permits because Section 100 covers every permit for work under the state codes. Title 49 also lists a $75.50 residential zoning clearance fee (Section 303.G) and watershed fees, $64 for a watershed permit application (Section 1201) and $207 for a residential stormwater impact review (Section 1202); Section 306 exempts only storm shelters from zoning and watershed fees, so these are normally added to a building permit. Ask the Permit Center which apply to your job.
A Title 49 amendment on the City Council's May 2026 agendas raises the per-$1,000 rate to $6.18, which would make the building fee $741.60. The posted copy is an unsigned packet with blank adoption lines. Ask the Permit Center which schedule applies before you pay. A separate Council item (50074, June to July 2026) proposed a new Section 328 waiving the Section 301 and 302 building fees for qualifying affordable housing; we could not confirm whether it passed or whether an ADU could qualify, so ask.
| What you are doing | City filing | Rule |
|---|---|---|
| ADU in RM, RT, RD or a mixed-use district | Building permit | Allowed by right |
| ADU in an RS or RE district | Special exception + building permit | Board of Adjustment, $950 |
| ADU in the Neighborhood Infill Overlay | Building permit | Allowed by right |
| Second ADU on the lot | Not allowed | One ADU per lot |
| ADU above a garage in the rear setback | Building permit | Two stories, 25 ft, 18 ft to top plate |
| Larger ADU than the size limit allows | Special exception | Board of Adjustment |
| Using a pre-approved plan set | Site-specific review | City T-Town HOME catalog |
Is there a faster way to permit an ADU in Tulsa?
The city's T-Town HOME catalog offers 18 sets of pre-approved plans, including accessory dwelling units; a site-specific review is still required. Residential building reviews averaged 7 business days for a first review in May 2026; a special exception adds a Board of Adjustment hearing; ask the Permit Center whether the building permit can be filed first.
How to Get a ADU Permit in Tulsa
Check zoning and overlays
Find your district on the city's zoning map. In RE or RS, plan a Board of Adjustment special exception first.
Pick or draw a plan
Use a T-Town HOME pre-approved set or your own plans meeting the size, setback and design rules.
Apply in the Self-Service Portal
Submit the building application with site, floor, foundation, roof and elevation plans and drainage and erosion control plans.
Trades pull their permits
After the building permit issues, your electrician, plumber and mechanical contractor pull and link their permits.
Inspections and occupancy
Pass foundation, rough and final inspections, then get the certificate of occupancy before anyone moves in.