What's Required in Albuquerque
- Permit required for all complete roof replacements.
- Maximum of two layers of shingles allowed.
- Ice and water shield mandatory in valleys and at eaves.
- Drip edge must be installed per building code.
- Attic ventilation must be maintained or upgraded to code.
- Flashing must be replaced or repaired at wall intersections.
Do You Need a Permit to Replace a Roof in Albuquerque
In almost every case, yes β a full roof replacement (a tear-off and re-cover, or a complete reroof) requires a building permit in Albuquerque, issued by the Planning Department - Building Safety Division. Replacing the roof covering is regulated work because it affects the structureβs weather envelope and, on a tear-off, exposes the sheathing for inspection. A licensed roofing contractor usually pulls the permit, and an inspection may be required after the old material is removed and again at completion. Permit-free roofing is generally limited to minor repairs β not a whole-roof replacement.
Roof Repair vs. Replacement: When You Need a Permit in Albuquerque
The dividing line in Albuquerque is usually the scope of work. Small repairs β patching a leak, swapping a few damaged shingles, or fixing flashing β often donβt require a permit. A full replacement, a tear-off down to the deck, adding a second layer over the old shingles, or any change to the roof structure (rafters, trusses, sheathing) generally does. Some cities also cap how much roof area you can repair before it counts as a replacement. Because that threshold and any wind- or fire-zone rules vary, confirm the cutoff with the Planning Department - Building Safety Division β the requirements above list what Albuquerque expects.
How to Get a Roof Replacement Permit in Albuquerque
Step 1: Hire Roofer
Ensure the contractor is licensed and registered.
Step 2: Apply Online
File for the roofing permit via the city's web portal.
Step 3: Pay Fees
Submit the flat residential re-roofing fee.
Step 4: Installation
Execute the tear-off and replacement according to code.
Step 5: Final Inspection
Inspector checks the flashing, venting, and material layers.