Permit Required?
Required
Typical Fee Range
$133–$217
Boiler/Furnace replacement (Level 2) is $132.40; entire system (Level 3) is $216.60.
Fee Method
Flat rate
What's Required in Minneapolis
- Permit required for replacement or installation of any heating or cooling unit
- Proper secondary drain pan and safety switches required for all attic units
- Duct sealing and insulation must meet current MN Energy Code requirements
- Manual J load calculations required for new system sizing
- Contractors must be licensed with the City of Minneapolis
- Final mechanical inspection mandatory upon unit installation
How to Get a HVAC Permit in Minneapolis
1
Step 1: Unit Identification
Determine if your project is a unit swap (Level 2) or entire system (Level 3).
2
Step 2: Portal Application
Submit a 'Mechanical Permit' application through the online portal.
3
Step 3: Fee Payment
Pay the flat fee ($132.40 or $216.60) online.
4
Step 4: Installation
Complete the install following the 2024 MN Mechanical Code.
5
Step 5: Inspection
Schedule a final mechanical inspection via ProjectDox.
Frequently Asked Questions
Yes, a mechanical permit is mandatory for any HVAC replacement.
A boiler or furnace replacement costs $132.40, while a full system is $216.60.
Yes, if it is their primary residence and they perform the work themselves.