What's Required in Wichita
- A building permit for bathroom work that moves fixtures, adds circuits or fans, or changes walls or windows.
- The job valuation on the residential building application.
- Plumbing, electrical and mechanical work covered by the building permit, or its own permit if started more than 180 days later.
- Licensed trades unless the owner-occupant passed MABCD's homeowner exam for that trade.
- A plumbing permit for replacing concealed drain, waste or supply piping, even without a remodel.
- The inspection record card on site before work begins.
Do I need a permit to remodel a bathroom in Wichita?
For cosmetic work, no. The Metropolitan Area Building and Construction Department (MABCD) lets you repair or replace existing finish work without a permit: paint, wallpaper, tiling, carpeting, cabinets, countertops, paneling and similar. Swapping a vanity top, retiling a floor or repainting needs nothing. A permit is required when you change something: moving a toilet, tub or shower drain, adding a fixture, adding circuits or an exhaust fan, moving a wall, or enlarging a window.
Plumbing repairs have their own carve-out. Clearing stoppages, fixing leaks in pipes, valves or fixtures, and removing and reinstalling a toilet need no permit, provided no valves, pipes or fixtures are replaced or rearranged. Replacing a defective concealed drain or water pipe counts as new work and needs a permit. Drywall repair is exempt only up to 100 square feet in 12 months with no framing or trade changes. MABCD's owner-occupant plumbing section (3.1.430) also says no permit is required for minor repairs or alterations priced at $200 or less; the work must still meet code. Ask MABCD whether this applies to contractor work.
How much is a bathroom remodel permit in Wichita?
Remodels are priced on the Table B valuation schedule: $70 for the first $2,000 plus $11 for each additional $1,000, or fraction, up to $40,000. Worked examples:
- A $15,000 bathroom: $70 + (13 × $11) = $213.
- A $30,000 bathroom: $70 + (28 × $11) = $378.
Table C lists plan review at 60% of the building permit fee; MABCD's calculator labels that as commercial plan review, and residential review happens at the counter, so ask before budgeting it. The Director may cut Table B fees by up to 20% for a period. If you only replace a water heater, a standalone plumbing permit is $9 plus the $25 issuance fee.
| What you are doing | City filing | Rule |
|---|---|---|
| Retile, repaint, new vanity in the same spot | None | Finish work exempt |
| Fix a leak or reset a toilet | None | Repair exemption; no pipe rearrangement |
| Move a toilet, shower or tub drain | Building permit | Valuation schedule; plumbing covered |
| Add an exhaust fan or new circuit | Building permit | Covered in a one- or two-family remodel |
| Replace a concealed drain or supply pipe | Permit required | New work; covered by the building permit in a remodel |
| Water heater swap only | Plumbing permit | $9 + $25 issuance |
| Plumbing work alone, no remodel | Plumbing permit | $4.50 per waste opening + $25 issuance |
Do I need a separate plumbing permit?
Not when the plumbing is part of a remodel of a one- or two-family house under a building permit: MABCD's plumbing, electrical and mechanical fee tables all say that work is covered by the building permit. A separate trade permit is needed if that work begins more than 180 days after the building permit was issued, or if the job is plumbing only.
Can I do the plumbing myself?
Only in a home you own and live in. Owner-occupants may obtain permits to repair, replace or maintain the plumbing in their own single-family home and must do the work personally. For new installations you first pass MABCD's homeowner exam at 75%: plumbing ($25; MABCD's exam page lists the 2012 Uniform Plumbing Code book), water heater ($25) or electrical ($50). At application you either schedule the exams or name licensed subcontractors; if you do neither, licensed trades must do the work. Rental properties require licensed contractors.
What if I skip the permit?
MABCD's fee Table G sets a civil penalty of twice the permit fee, up to $5,000, for building work without a permit in Wichita, and $150 on top of the fee for trade work. The residential code's own permit section says the penalty is up to the amount of the permit fee, so confirm the amount with MABCD.
How to Get a Bathroom Remodel Permit in Wichita
Sort exempt from permitted work
Finish work and simple repairs are exempt; moving fixtures, drains, wiring or walls is not.
Choose who does the trades
Name licensed subcontractors or schedule homeowner exams at application.
Apply on the MABCD Portal
Submit a residential building application with the valuation, or book an appointment with a permit writer.
Pay the fee
Valuation schedule, for example $213 on a $15,000 job.
Pass inspections
Schedule the inspections MABCD requires on the portal, through final.