What's Required in Riverside
- Get a building permit with plans prepared by a licensed design professional, or use a city pre-approved plan.
- Keep a detached ADU to 1,200 square feet; an attached ADU to 1,200 square feet or 50% of the house, whichever is less.
- Place the ADU in a side or rear yard; ADUs are not allowed in front yards.
- Expect a 4 ft side and rear setback for a new one-story ADU; state law bars the city from requiring more than 4 ft.
- Confirm utility service and connection fees with Riverside Public Utilities.
- Pay plan check, issuance, planning and fire fees, plus any proportional impact fees for an ADU over 750 square feet.
- Start construction within 12 months of permit issuance.
Do You Need a Permit to Build an ADU in Riverside?
Yes, with plans by a licensed design professional, per the Planning Division's ADU FAQ. Under Government Code 66310 and following, as summarized in the state ADU Handbook (March 2026 update), a city must approve or deny a complete ADU application within 60 days when there is an existing home on the lot, may require side and rear setbacks of no more than four feet, may not require owner occupancy for an ADU, and must allow at least 850 square feet (1,000 for more than one bedroom).
Riverside's FAQ, last revised in 2022, says detached ADUs may be up to 1,200 square feet, attached ADUs up to 1,200 square feet or 50% of the house, whichever is less, a JADU up to 500 square feet, and no added parking. It also says ADUs taller than 16 feet must meet the house's side and rear setbacks; state law now caps those setbacks at four feet, so where the two differ, state law controls (we could not read the city ordinance; confirm with Planning).
Riverside ADU Rules by Scenario
| What you are doing | City filing | Rule |
|---|---|---|
| Detached ADU on a pre-approved city plan | Building permit, Dwell Riverside | 3 business day first review |
| Custom detached ADU up to 1,200 sq ft | Building permit with full plans | Tier 2 review, 20 working days |
| Garage converted to an ADU | Building permit | Garage conversion line, $532 first 400 sq ft |
| JADU inside the house, up to 500 sq ft | Building permit | Tier 1 review, 10 working days |
| ADU of 750 sq ft or less | No impact fees | State law, HCD Handbook |
| ADU over 750 sq ft | Proportional impact fees | Scaled to the main house size |
How Much Does an ADU Permit Cost in Riverside?
Riverside prices this work from its FY 2026/27 Schedule of Fees and Charges, in effect since July 1, 2026. Each separate permit carries its own $41 issuance fee. On the 14% surcharge (10% General Plan Maintenance plus 4% Technology), the schedule marks only some lines with a caret, the city's fee sheet applies it to all plan check and permit fees, and our examples follow the fee sheet. We read each fee line as plan check and permit combined, our reading of the division's March 2026 fee sheet; the schedule's separate $341 Building Plan Check line may be added, so ask. The schedule has no ADU building line, so we use the R-3 single-family dwelling rate of $1.14 per square foot for a detached unit; attached units may be priced higher. Planning's zoning plan check for new single-family construction is $332, and the Fire Department's ADU plan check is $152; the Fire line carries no caret, so we do not surcharge it.
Example, an 800 square foot detached ADU: 800 x $1.14 = $912, plus $41 issuance and $332 planning, $1,285, plus 14%, $1,465, plus $152 fire, about $1,617. A 1,200 square foot ADU: $1,368 + $41 + $332 = $1,741, plus 14%, $1,985, plus $152, about $2,137. The schedule marks the $332 both as including and as adding the surcharge; if it is included, the range is about $1,570 to $2,090. The fee sheet lists a 700 square foot minimum for new dwellings, so minimums may apply, and the SMIP fee (residential valuation x $0.00013) and the $1 per $25,000 state fee may be added. Trade permits are priced per item on the schedule; Riverside's older fee handout folded them into the combination building permit for new buildings, so ask which applies. Beyond city permit fees, an ADU of 750 square feet or less pays no impact fees under state law; a larger one pays in proportion to the house, and school districts may charge ADUs over 500 square feet.
What Are Riverside's Pre-Approved ADU Plans?
Under Dwell Riverside, the city offers four single-story plans of 746, 800, 1,020 and 1,200 square feet. Your lot must be zoned single-family (R-1, RE, RR, RC or RA-5), outside a flood hazard area and not a designated or eligible cultural resource. The first plan review takes 3 business days, and rechecks 10 business days.
Who Can Pull an ADU Permit?
Riverside issues many permit types to the property owner, an authorized agent or a licensed contractor; a contractor needs a CSLB license and a City of Riverside business license. Owner-builders sign the city's Property Owner's Package at the counter or before a notary. Apply through the POSSE-based Public Permit Portal or at the One Stop Shop, 3900 Main Street.
How to Get a ADU Permit in Riverside
Check eligibility
Confirm your zone, flood status and historic status; Dwell Riverside plans need a single-family zone.
Choose a plan
Pick a pre-approved plan of 746 to 1,200 square feet, or have a licensed designer draw a custom ADU.
Submit on the portal
Upload plans, the preliminary site plan and the Planning ADU clearance form to the Public Permit Portal.
Clear department conditions
Download the conditions report and meet each department's requirements at the One Stop Shop.
Pay fees and build
Pay all fees to receive the permit, then schedule inspections through the portal.