What's Required in Irvine
- Get a plumbing permit for any moved or added fixture, drain or supply line.
- Get an electrical permit for new lights, outlets or circuits, and use high-efficacy or occupant-sensor lighting.
- Stay within 4 plumbing fixtures, 10 electrical items and 5 grilles to use the online combo permit.
- Submit a remodel permit with plans through IrvineReady! when walls, structure or room size change.
- Meet current smoke and carbon monoxide alarm requirements before final inspection.
- Meet Bulletin 321's water-conserving fixture rules if the home was built before 1994.
- Get HOA board written permission for condo work affecting a common area.
Do You Need a Permit to Remodel a Bathroom in Irvine?
For most real remodels, yes. Irvine requires a building permit for an interior remodel or alteration and separate plumbing, electrical and mechanical permits for new piping, wiring and ventilation. Small jobs can skip the permit: no plumbing permit is needed to remove and reinstall or replace a toilet or sink when the work does not involve replacing or rearranging valves, pipes or fixtures, and painting, papering and similar finish work is exempt.
In between is the small combination permit, which PermitsDIRECT! lists as Miscellaneous Residential Work. The city's minor-permit page sets its limits: up to four (4) plumbing fixtures (a toilet, sink, drain or faucet each count), up to 10 electrical fixtures and/or outlets and up to five (5) grilles and ducting, with no plans. Lighting in bathrooms must be high efficacy or controlled by an occupant sensor. Moving walls, enlarging the room or changing structure means a remodel permit with plans on IrvineReady!. These conditions come from the city's pages for its older Automated Online Permit system, which PermitsDIRECT! replaced on September 14; confirm eligibility when you apply.
Irvine Bathroom Remodel Rules by Scenario
| What you are doing | City filing | Rule |
|---|---|---|
| Paint or wallpaper only | None | Painting, papering and similar finish work; the list does not name tile, so confirm at (949) 724-6313 |
| Replace a toilet or sink in the same place | None | No plumbing permit if pipes and valves stay |
| Move the toilet, add a shower or new drain | Small combo permit online | Up to 4 plumbing fixtures, no plans |
| New lights, outlets or circuits | Small combo permit online | Up to 10 fixtures and outlets |
| Move walls or enlarge the bathroom | Remodel permit with plans | IrvineReady! plan check |
| Bathroom in a condo with shared walls | Remodel permit with stamped plans | Licensed design professional |
How Much Does a Bathroom Remodel Permit Cost in Irvine?
Schedule II, effective August 15, 2026, item 7 sets remodel plan check at $0.86 per square foot with a $95.67 minimum, covering plumbing, electrical and mechanical review, and inspection at $398.39 per bathroom or kitchen remodeled. Add the $31.88 residential issuance fee. Residential remodels are exempt from the 10% automation fee. The schedule also lists a general remodel inspection of $1.33 per square foot; we read the per-room line as the bathroom price, so confirm with the Permit Processing Counter. These totals do not include electrical, plumbing or mechanical permit items priced on Schedule V; ask the Permit Processing Counter for an estimate.
- One bathroom, 60 sq ft: plan check $51.60 rises to the $95.67 minimum, plus $398.39 and $31.88, about $526.
- Two bathrooms, 120 sq ft total: $103.20 plan check plus two inspections at $398.39 plus $31.88, about $932.
- Small online combo: three plumbing fixtures at $24.08 and four light or outlet items at $1.96 is $80.08, plus $8.01 automation and $31.88 issuance, about $120. That is item fees plus one issuance fee only; Schedule V's $63.77 minimum inspection fee may raise it. We charge the 10% on the item fees only (our reading of item 21), because the remodel exemption is not stated for online combo permits.
Each separate electrical, plumbing or mechanical permit adds its own $31.88 issuance fee. Not included: the state-mandated energy and access surcharge on Schedule II ($73.75 per 1,000 square feet for inspection plus 65% of that for plan check) and the state SMIP fee ($13.00 per $100,000 of valuation), because the schedule does not say which small jobs they apply to. If the surcharge applies, it adds about $122, which would take a 150 sq ft shed from about $246 to about $368.
Homes built in or before 1980 may qualify for the One Irvine Permit Fee Holiday, which waives permit or plan check fees for certain projects up to $1,500 (the IrvineReady! page still prints 1975).
What Does Irvine Check on a Bathroom?
At final inspection the home must meet current smoke and carbon monoxide detector requirements. Homes built before 1994 fall under Bulletin 321's water-conserving fixture verification and retrofit rules.
Who Can Pull the Permit?
Irvine's Bulletin 222 says work on homes, pools and equipment such as water heaters and HVAC is permitted to a state-licensed contractor, with one very limited exception: an owner-builder, who signs the city's Property Owner's Package. Contractors show a City of Irvine business license, CSLB pocket card and workers' compensation certificate. In a condo, work that affects a common area, such as an attic or underfloor area, needs written permission from the HOA board and may only be permitted to a licensed contractor. Plan-check remodels get a completeness review in about two business days and about five business days for the first plan check; online combo permits are issued in real time.
How to Get a Bathroom Remodel Permit in Irvine
List what moves
Count the plumbing fixtures, lights, outlets and vents you are adding or moving, and note any wall changes.
Pick the permit route
Use the PermitsDIRECT! combo permit for small trade work or prepare remodel plans for IrvineReady!.
Check condo and HOA rules
In a condo, confirm whether work touches a common area and get board permission if it does.
Pay and get approval
Pay online; plan-check remodels usually get a first review in about five business days.
Inspect before closing walls
Schedule rough inspections before drywall and tile, then the final with smoke and CO alarms installed.