What's Required in Irvine

  • Get the ADU Verification Form from the Planning Team before you submit.
  • Submit the Residential ADU application, plans and calculations through IrvineReady!.
  • Keep at least 4 feet from side and rear property lines and 6 feet from other buildings.
  • Keep a detached ADU to 1,200 square feet and a JADU to 500 square feet.
  • Confirm the height limit with the Planning Counter; state law requires the city to allow at least 16 feet for a detached ADU (18 feet near major transit).
  • Sign the hold harmless affidavit and record the notarized covenant with the County of Orange when told.
  • Pay school fees to the district before issuance if the ADU is over 749 square feet.
  • Set mechanical equipment two feet from the property line and screen it from off-site views.

How Do ADU Permits Work in Irvine?

Irvine says it reviews Accessory Dwelling Unit and Junior ADU applications per state statute. Every ADU and JADU needs a completed Residential Accessory Dwelling Unit application and an ADU Verification Form, which you get from the Planning Team at [email protected] or 949-724-6308. The IrvineReady! package adds plans and calculations, a hold harmless affidavit, a notarized covenant recorded with the County of Orange, a deposit case form and school, TCA and address forms.

The city's Pre-Approved ADU Plans program is set up, but its list of approved standard plans still reads coming soon.

Irvine ADU Rules by Scenario

What you are doingCity filingRule
Detached ADUBuilding permit and ADU applicationUp to 1,200 sq ft; 4 ft side and rear setbacks
Attached ADUBuilding permit and ADU applicationUp to 1,200 sq ft or 50% of the house, whichever is less
Junior ADU inside the houseBuilding permit and ADU applicationUp to 500 sq ft, one per single-family home
ADU of 800 sq ft or less with 4 ft setbacksCannot be blocked by lot coverageGov. Code 66321 per the HCD Handbook
ADU of 750 sq ft or lessNo impact feesState law; school fees waived to 749 sq ft
ADU within a half mile of transitNo parking can be requiredGov. Code 66322
Garage converted to or demolished for an ADUBuilding permit and ADU applicationLost parking need not be replaced: Gov. Code 66314(d)(11)

What Size and Height Can an Irvine ADU Be?

The city's Pre-Approved ADU Development Standards Checklist (form 67-01) allows a detached ADU up to 1,200 SF, an attached ADU up to 1,200 square feet or 50% of the primary residence, whichever is less, and a JADU up to 500 SF of the existing house. It requires a minimum 4-foot setback from side and rear property lines and a 6-foot building-to-building separation, and lets an ADU exceed lot coverage to reach 800 square feet. Irvine's own ADU height limit was not found, so confirm it with the Planning Counter; state law, per the HCD ADU Handbook (March 2026), requires the city to allow at least 16 feet for a detached ADU (18 feet near major transit), and bars owner-occupancy requirements except for ADUs sold separately.

How Much Does an ADU Permit Cost in Irvine?

Planning bills ADU review at $217.64 per hour against a $1,500.00 initial deposit (minimum balance $300.00), so the final planning cost may differ from the deposit. Building fees come from Schedule II, effective August 15, 2026. A detached ADU is most likely priced on item 3, single family dwellings: plan check $0.68 and inspection $0.56 per square foot, plus the $73.08 new residential construction issuance fee and the 10% automation fee. We apply the 10% to plan check and inspection only, our reading of item 21; if it also applies to the issuance fee, add about $7.

  • 600 sq ft detached ADU: $408.00 plus $336.00 is $744.00; with $73.08 and $74.40 automation, $891.48, plus the $1,500 deposit, about $2,391.
  • 1,000 sq ft detached ADU: $680.00 plus $560.00 is $1,240.00; with $73.08 and $124.00, $1,437.08, plus the deposit, about $2,937.

Not included: the state-mandated energy and access surcharge on Schedule II ($73.75 per 1,000 square feet for inspection plus 65% of that for plan check) and the state SMIP fee ($13.00 per $100,000 of valuation), because the schedule does not say which small jobs they apply to. If the surcharge applies, it adds about $122, which would take a 150 sq ft shed from about $246 to about $368. School fees apply to an ADU over 749 square feet. Confirm the fee line with the plan checker, because an attached ADU may be priced as an addition.

Homes built in or before 1980 may qualify for the One Irvine Permit Fee Holiday, which waives permit or plan check fees for certain projects up to $1,500 (the IrvineReady! page still prints 1975).

How Long Does Approval Take?

State law requires the city to approve or deny a complete ADU application within 60 days when there is an existing house on the lot. Review starts after payment.

City Rules Versus HOA Rules

Your HOA may have its own approval process, and the city tells applicants to review it. State law (Civil Code 714.3 and 4751, per the HCD Handbook) voids CC&Rs that effectively prohibit or unreasonably restrict an ADU on a single-family lot, though an HOA may still apply limited objective design standards. Irvine's Bulletin 222 says work on homes, pools and equipment such as water heaters and HVAC is permitted to a state-licensed contractor, with one very limited exception: an owner-builder, who signs the city's Property Owner's Package.

How to Get a ADU Permit in Irvine

1

Request the ADU Verification Form

Email [email protected] to confirm your property is eligible and get the ADU Verification Form.

2

Design to the standards

Have plans drawn to the city checklist and state limits on size, setbacks, height and parking.

3

Submit through IrvineReady!

Upload the ADU application package, plans, affidavit, deposit form and the school, TCA and address forms.

4

Pay and go through review

Pay the emailed fees and the planning deposit; the city must act on a complete application within 60 days.

5

Record, build and inspect

Record the covenant when the planner asks, pay school fees if due, then build and schedule inspections.

Frequently Asked Questions

The city's Pre-Approved ADU Development Standards Checklist (form 67-01) allows a detached ADU up to 1,200 square feet and an attached ADU up to 1,200 square feet or 50 percent of the main house, whichever is less. A Junior ADU can be up to 500 square feet inside the existing home. Lot coverage cannot stop an 800 square foot unit with 4-foot setbacks.
Planning review is billed at $217.64 an hour against a $1,500 deposit. Building fees for a detached ADU run about $0.68 plan check and $0.56 inspection per square foot, plus a $73.08 issuance fee and a 10% automation fee. That totals about $2,391 for 600 square feet and $2,937 for 1,000, before school and state fees.
Under state law, an ADU of 750 square feet of interior livable space or less is exempt from impact fees, and larger ADUs pay in proportion to the main house. Irvine's school fee form exempts an ADU of 749 square feet or less; above that, the school district calculates and collects the fee before the permit issues.
The program exists, but the city's list of pre-approved ADU standard plans currently says coming soon. When plans are listed they will be bought from the design firms, submitted with a building permit application and reviewed for site-specific zoning and foundation requirements.
State law requires a city to approve or deny a complete ADU application within 60 days when there is an existing single-family or multifamily dwelling on the lot, and to return a full list of deficiencies if it denies. Irvine checks completeness in about two business days and starts review once fees are paid.
Often not. Irvine's checklist asks for one space for an ADU with one or more bedrooms, but state law bars parking requirements for ADUs within a half-mile walk of public transit, ADUs inside the existing house or an accessory structure, and several other cases, so check those exemptions first.