What's Required in Fresno
- Get a mechanical permit before replacing or adding a furnace, AC, heat pump, air handler or evaporative cooler.
- List each piece of equipment on the Permit Affidavit Form.
- Support horizontal flexible duct at intervals of 4 feet or less and keep runs to the minimum length needed.
- Install or verify smoke and carbon monoxide alarms when the job exceeds $1,000 in value.
- Pass the city's mechanical inspection before closing the job.
- Pay the permit fees when the permit is issued; Fresno collects them at issuance.
- Start work within 180 days of issuance; an approved inspection extends the expiration to 180 days from that inspection.
Do You Need a Permit to Replace an AC or Furnace in Fresno?
Yes. Fresno quotes the building code rule that anyone who intends to install, alter, repair, remove, convert or replace any mechanical system must obtain the required permit, and none of the heating or cooling work below appears on the city's list of work exempt from a building permit. That covers a like-for-like condenser swap, a new furnace, an evaporative cooler, a new air handler and duct work.
Fresno HVAC Rules by Scenario
| What you are doing | City filing | Rule |
|---|---|---|
| Replace an AC condenser or add a cooling unit | Simple mechanical permit | Fee schedule: cooling unit |
| Install or replace an evaporative cooler | Simple mechanical permit | Fee schedule: evaporative cooler |
| Replace an air handler with its ducts | Simple mechanical permit | Fee schedule: air-handling unit |
| Replace a forced-air furnace | Complex mechanical permit, per item | Fee schedule: FAU |
| Furnace and AC together | Two items, if billed separately | Complex items are per item |
| Replace flexible duct | Ask the counter | Bulletin: full replacement needs an AMMR with added plan check fees (tenant improvement criteria); 50% or less can be like for like |
How Much Does an HVAC Permit Cost in Fresno?
Fresno uses flat fees from the Master Fee Schedule effective July 1, 2026. A cooling unit, evaporative cooler, air-handling unit or vent fan is a simple mechanical item at $111.50, and the schedule says one simple permit covers any item or combination of items on its simple lists. A forced-air unit (FAU) of any size is a complex mechanical item at $177.89, and complex items are issued on a per-item basis. Every stand-alone trade permit adds a $27.08 permit issuance fee.
- AC condenser or evaporative cooler only: $111.50 + $27.08 = $138.58 and up
- Furnace only: $177.89 + $27.08 = $204.97
- Furnace and AC on one job: $177.89 + $111.50 + $27.08 = $316.47 if the city bills them on one permit, or $343.55 if each is issued and charged an issuance fee separately; the schedule does not say
The schedule also lists air conditioners and heat pumps as complex electrical apparatus, per item: $296.90 (up to 1 HP) and $385.85 (over 1 and up to 10 HP). It does not say whether a home condenser is billed there as well, so ask for an estimate.
Fee example: a furnace and AC change-out valued at $14,000. Base $316.47 on the one-permit reading. Stand-alone trade permits also carry the schedule's 12.83% General Plan surcharge and a $23.79 technology surcharge; the schedule names no base for the 12.83%, and its trade-permit section lists no state valuation surcharge. That adds about $37 on the item fees (about $41 if the city also applies it to the $27.08 issuance fee) and $23.79, for about $377 to $381. Doing the work without a permit can cost up to 4 times the permit fee.
What Does the Inspector Check?
Fresno's flexible ductwork bulletin quotes the California Mechanical Code: horizontal flexible duct runs supported at not more than 4 feet intervals, the minimum length needed to make the connection, and bends no tighter than one duct diameter; the 5-foot limit on flexible duct length has an exception for residential occupancies. Its policy requires an AMMR (alternate materials and methods) request, with added plan check review and fees, when an existing flex duct system is completely replaced; 50 percent or less can be like for like. Those rules sit under tenant improvement criteria; ask whether they apply. Permitted work exceeding $1,000 in value requires smoke and carbon monoxide alarms in the house; for exterior change-outs the owner or tenant and contractor can sign the city's verification form instead.
Fresno's Building and Safety page lists same-day express mechanical permits among its in-person services, booked with QLess; ask at the counter whether your job qualifies, or apply in Accela Citizen Access with the Permit Affidavit Form listing the equipment.
Who Can Pull the Permit?
You can, as an owner-builder, if you do the work yourself or with your own employees and the structure is not offered for sale within a year of completion; the city's permit affidavit cites Business and Professions Code 7044 for this. The owner-builder checklist the city posts adds that, for home improvements, the site must be your principal residence, occupied for 12 months before the work is finished, and the exemption cannot be used on more than two structures in any three-year period. When you sign as an owner-builder you take full responsibility for the job, and anyone who contracts for or bids on a project valued at $500 or more (labor and materials) must be licensed by the Contractors State License Board. Apply online through Accela Citizen Access, the city's portal, or with in-person submittal help at City Hall.
How to Get a HVAC Permit in Fresno
List the equipment
Note each unit being replaced or added; a furnace is billed per item, simple items share one fee.
Complete the affidavit
Fill in the Permit Affidavit Form with the equipment and the license or owner-builder declaration.
Get the permit
Book a same-day express permit through QLess, or apply in Accela Citizen Access.
Pay fees at issuance
Pay the item fees, the $27.08 issuance fee and the surcharges when the permit is issued.
Inspect
Book the inspection in Accela Citizen Access or by Voice Permits and sign the alarm verification if needed.