Permit Required? Depends on fuel and scope
Typical Fee Range $81–$320 Gas and oil equipment always need a permit; electric swaps may be exempt
Fee Method Flat per unit: $55 heating, $60 AC + $25 processing

What's Required in Milwaukee

  • Gas- and oil-fueled furnaces and boilers need an HVAC permit even for a like-for-like replacement.
  • New air conditioning, heat pumps and ductwork need an HVAC permit.
  • Plan review is not required for equipment replacement, AC-only systems or duct alterations of $10,000 or less.
  • Permit applications must list the manufacturer, capacity, efficiency rating, model and location of the equipment.
  • HVAC businesses must register with the State of Wisconsin, and contractors need a City Home Improvement Contractor License.
  • New wiring for HVAC equipment needs an electrical permit by a state-licensed electrical contractor.
  • Air-conditioning condensers must sit in side or rear yards outside the required setbacks.

Do you need a permit to replace a furnace or AC in Milwaukee?

For a gas furnace or boiler, yes. Milwaukee's code exempts the replacement of mechanical appliances in one- and two-family homes only when the equipment is not fueled by gas or oil (MCO 200-24-1.5-f-4), so a gas furnace, gas boiler or oil burner swap needs an HVAC permit even when it is like-for-like. The Department of Neighborhood Services (DNS) checklist lists Furnace: Yes.

Electric equipment is less clear. The same code exemption covers non-gas appliances, and DNS's homeowner page lists replacing air conditioners among work that needs no permit. But the DNS checklist lists Air conditioner: Yes. A new central AC where there was none, a heat pump added to a furnace, or new ductwork is installation, not replacement, and needs a permit. For a straight condenser swap, call the Permit and Development Center at (414) 286-8210 before relying on the exemption. Window units need no permit.

How much is an HVAC permit in Milwaukee?

Mechanical permits are flat per item under MCO 200-33-23: $55 per heating unit up to 150,000 BTU input (plus $25 per extra 50,000 BTU), $60 per air conditioning unit up to 3 tons (plus $10 per extra ton), boilers $60 per unit up to 150,000 BTU, and ductwork at $2 per 100 sq ft of conditioned area with a $50 minimum. Each permit adds a $25 processing fee, and DNS adds its 1.6% training and technology surcharge.

  • Like-for-like 80,000 BTU gas furnace: $55 + $0.88 + $25 = $80.88.
  • New 4-ton central AC: $60 + $10 = $70, plus $1.12 and $25 = $96.12, and the AC circuit needs an electrical permit.
  • New furnace, 3-ton AC and new ductwork in a 2,000 sq ft house: $55 + $60 + $50 = $165, plus $2.64 and $25 = $192.64; electrical for the AC outlet and furnace at the $100 minimum, plus $1.60 and $25 = $126.60. Total $319.24.

Plan review is not needed for equipment replacement only, air-conditioning-only systems, or duct alterations costing $10,000 or less; for those jobs DNS still requires the permit itself.

What you are doingCity filingRule
Replacing a gas furnace or boilerHVAC permit, $55 or $60 per unitGas and oil equipment not exempt
Replacing an electric AC condenser in kindConfirm with DNSCode exempts non-gas appliances; checklist says AC: Yes
Installing new central AC or a heat pumpHVAC permit, $60 up to 3 tonsPlus electrical permit for the circuit
New or altered ductworkHVAC permit, $2/100 sq ft, $50 minNo plans if the job is $10,000 or less
Window air conditionerNo permitDNS homeowner list
Condenser placementSide or rear yard outside setbacksMCO 295-505-3-L
Outdoor wood-burning furnaceProhibitedAll residential districts

Who can pull an HVAC permit in Milwaukee?

Apply on the Development Center alterations permit form, listing the manufacturer, capacity in BTU/hr or tons, efficiency rating (AFUE or SEER), model and location. Wisconsin requires any business that installs or services HVAC equipment to register with the state (Wis. Stat. 101.178), and the city requires a Home Improvement Contractor License of contractors doing heating and cooling work at one- and two-family homes. DNS lets owners who live in the home pull permits for their own work. Any new wiring for the equipment must be done by a licensed electrical contractor.

How to Get a HVAC Permit in Milwaukee

1

Check the fuel and scope

Gas or oil equipment, new systems and ductwork need a permit; ask DNS about a straight electric condenser swap.

2

Choose a registered contractor

Hire an HVAC business registered with the state and holding a City Home Improvement Contractor License, or pull the permit as an owner-occupant.

3

Gather equipment data

Collect the manufacturer, BTU/hr or tonnage, AFUE or SEER rating, model numbers and installation location.

4

Apply and pay

File the Development Center alterations permit form or apply through the Land Management System; pay the per-unit fee, surcharge and $25 processing.

5

Inspect

Have the installation inspected, plus the electrical permit inspection if a new circuit was run; start within 180 days of issue.

Frequently Asked Questions

Yes, if it burns gas or oil. Milwaukee's code exempts only the replacement of mechanical appliances that are not fueled by gas or oil, and DNS's checklist lists furnaces as needing a permit. The fee is $55 per unit up to 150,000 BTU, plus $25 processing and a 1.6% surcharge, about $80.88.
The code and DNS's homeowner page exempt like-for-like replacement of non-gas appliances, including air conditioners, but the DNS checklist says air conditioners need a permit. Confirm with the Permit and Development Center. A new system is installation and needs a $60 permit for units up to 3 tons plus processing.
Heating units are $55 up to 150,000 BTU, AC units $60 up to 3 tons with $10 per extra ton, and ductwork $2 per 100 sq ft with a $50 minimum. Every permit adds a $25 processing fee and the 1.6% surcharge. A furnace, AC and duct job comes to about $192.64 before the electrical permit.
Not for equipment replacement only, air-conditioning-only systems, or alterations to existing ductwork costing $10,000 or less. Other HVAC work in new construction, additions and alterations needs a plan submittal, and in buildings of 50,000 cubic feet or more a Wisconsin registered engineer or designer must design it.
Zoning allows air-conditioning condensers only in side and rear yards outside the required setback areas, with some placement in a principal building's setback where table 295-505-2-f allows it. Plan to put the condenser beside or behind the house, and note that outdoor wood-burning furnaces are banned in all residential districts.