Permit Required? Depends on the work
Typical Fee Range $43–$526 Remodel: $119 per trade + $33.08 + $16.87; plumbing-only job: $33.08 + $10.34
Fee Method Per trade ($119 each) plus $49.95

What's Required in Fort Worth

  • Cabinets, countertops, flooring, tile and paint need no permit.
  • Replacing 16 sq ft or more of drywall on a wall or ceiling requires a building permit.
  • Moving or adding plumbing, wiring or ductwork requires the matching trade permit.
  • Water heater replacement always requires a plumbing permit.
  • Remodel fees are $119 per trade plus a $33.08 application fee and a $16.87 technology fee.
  • Mechanical, electrical and plumbing permits go only to Texas license holders or homestead owner-occupants.
  • Submit existing and proposed floor plans, plus MEP plans for any system you alter.
  • Each trade permit is inspected separately from the building permit.

Do you need a permit to remodel a kitchen in Fort Worth?

It depends on what you touch. Fort Worth's residential permitting page says permits are not required for cosmetic remodels. That includes floor or wall covering, cabinets, countertops and shelving. It also includes plumbing fixture replacement. The Administrative Code exempts painting, tiling, cabinet replacement and countertop replacement. It also exempts swapping a faucet, sink, garbage disposal or dishwasher, as long as no pipes or valves are replaced or rearranged.

A permit is required once the work changes, moves or repairs walls, floors, ceilings, windows, doors, or the electrical, mechanical or plumbing systems. One specific trigger catches many kitchen jobs: replacing 16 square feet or more of drywall on any wall or ceiling needs a building permit. Moving the sink to an island, adding circuits for new appliances or venting a range hood outside all need trade permits. Replacing a water heater also needs a plumbing permit.

How much does a kitchen remodel permit cost in Fort Worth?

Fort Worth charges a residential remodel by the number of trades involved, not by the size or cost of the kitchen. Texas Local Government Code 214.907 bars value-based residential fees. Under Fee Ordinance 26-28781, effective October 1, 2026, the per-trade schedule is:

  • 1 trade: $119.00
  • 2 trades: $238.00
  • 3 trades: $357.00
  • 4 trades: $476.00

Every building permit adds a $33.08 application fee and a $16.87 technology fee. A remodel with drywall, new circuits and a relocated sink (building, electrical and plumbing) comes to $357.00 + $49.95 = $406.95. Add a ducted hood or HVAC change as a fourth trade and it is $525.95. If the only work is plumbing, such as adding a sink, a standalone plumbing permit can be used. That is a $33.08 application fee plus $10.34 for the first fixture, or $43.42. Trade permits also carry small per-item fees, such as $0.54 per outlet and $4.22 per additional plumbing fixture.

What you are doingCity filingRule
New cabinets, countertops, backsplash and flooringNo permitCosmetic finish work is exempt
Swap the sink faucet, disposal or dishwasher in placeNo permitExempt if no pipes or valves are moved
Add a second sink, with no other workStandalone plumbing permit, $43.42$33.08 application fee + $10.34 first fixture
Replace the water heater during the remodelPlumbing permitWater heaters always need a permit
New circuits, relocated sink, new drywallRemodel permit, 3 trades, $406.95$357.00 + $49.95, plus trade items
Open a wall, move plumbing, rewire, vent a hood outsideRemodel permit, 4 trades, $525.95$476.00 + $49.95, plus trade items
Replace 16 sq ft or more of drywallBuilding permitThe city's drywall trigger

Who can do the work?

Mechanical, electrical and plumbing permits are issued only to holders of the required Texas state licenses. The exception is a homeowner working on the house they own and live in as a primary residence. That homestead exception also lets owners pull the building permit. Otherwise the remodel permit goes to a building contractor registered with the city. Each trade still needs its own permit and inspections. A building permit does not cover the trades.

What to submit

The remodel packet asks for existing and proposed floor plans with every room labeled. It also asks for mechanical, electrical and plumbing plans if you are altering those systems. Apply in Accela Citizen Access. Residential plans get first review comments within 7 business days. If you start without a permit, the investigation fee equals the permit fee.

How to Get a Kitchen Remodel Permit in Fort Worth

1

Define the scope

List which trades the job touches (building, electrical, plumbing, mechanical). Cosmetic-only work needs no permit.

2

Draw the plans

Prepare existing and proposed floor plans, plus MEP plans for any system being altered.

3

Apply in Accela Citizen Access

A registered contractor or homestead owner files a Residential Remodel permit. Licensed trades pull their own trade permits.

4

Pay per trade

Pay $119 per trade plus the $33.08 application fee and $16.87 technology fee. First review comments come within 7 business days.

5

Pass rough and final inspections

Schedule each trade's rough-in before walls close, then the finals. A permit expires after 180 days without an approved inspection.

Frequently Asked Questions

No. Cabinet and countertop replacement, flooring, backsplash tile and paint are cosmetic work that Fort Worth exempts from permits. You need a permit only if the job also changes walls, plumbing, wiring or ductwork, or replaces 16 square feet or more of drywall.
Fort Worth charges $119.00 per trade for a residential remodel, plus a $33.08 application fee and a $16.87 technology fee. A kitchen with building, electrical and plumbing work is $406.95. With a fourth trade, such as mechanical, it is $525.95. A plumbing-only job can use a standalone plumbing permit for about $43.42.
Yes. Swapping a sink in the same spot is exempt, but relocating it means replacing or rearranging pipes, and that needs a plumbing permit. The permit must be pulled by a Texas-licensed plumber, unless you own the house and live in it and use a homestead permit.
Only in a house you own and occupy as your primary residence. Fort Worth issues homestead permits for building, mechanical, plumbing and electrical work to owner-occupants. Homeowners may not work on the service or the main breaker. Everyone else needs a Texas-licensed electrician to pull the electrical permit.
Yes, when it needs a permit. The residential remodel packet asks for existing and proposed floor plans with all rooms labeled. You also need mechanical, electrical and plumbing plans for the systems you are altering, showing outlet and switch locations, supply and drain sizes, and vent locations.