Permit Required?
Required
Typical Fee Range
$1,000–$2,000
New residential construction fees apply based on total square footage.
Fee Method
Valuation-based
Apply Online
Apply at Planning and Development Services →
What's Required in El Paso
- New construction fee for first 10,000 SF is $3,785.
- Must include full kitchen and bathroom facilities for habitation.
- Separate utility connections or approved shared capacity required.
- Site plan showing placement and zoning setbacks.
- Must meet all standard building, electrical, and plumbing codes.
- Trade application fee of $100 per required trade.
How to Get a ADU Permit in El Paso
1
Step 1: Zoning Check
Verify if your lot allows for secondary dwelling units.
2
Step 2: Submit Plans
Provide architectural sets for the mandatory city review.
3
Step 3: Pay Fees
Submit initial application and plan review fees.
4
Step 4: Multi-stage Inspections
Schedule from foundation to final occupancy through Accela.
5
Step 5: Certificate of Occupancy
A final check ensures the unit is safe for habitation.
Frequently Asked Questions
New construction starts at $3,785 for the first 10,000 SF.
Yes, each trade has a $100 application fee.
Failure to pass an inspection results in a $70 fee.