Permit Required? Required
Typical Fee Range $1,000–$2,000 New residential construction fees apply based on total square footage.
Fee Method Valuation-based

What's Required in El Paso

  • New construction fee for first 10,000 SF is $3,785.
  • Must include full kitchen and bathroom facilities for habitation.
  • Separate utility connections or approved shared capacity required.
  • Site plan showing placement and zoning setbacks.
  • Must meet all standard building, electrical, and plumbing codes.
  • Trade application fee of $100 per required trade.

How to Get a ADU Permit in El Paso

1

Step 1: Zoning Check

Verify if your lot allows for secondary dwelling units.

2

Step 2: Submit Plans

Provide architectural sets for the mandatory city review.

3

Step 3: Pay Fees

Submit initial application and plan review fees.

4

Step 4: Multi-stage Inspections

Schedule from foundation to final occupancy through Accela.

5

Step 5: Certificate of Occupancy

A final check ensures the unit is safe for habitation.

Frequently Asked Questions

New construction starts at $3,785 for the first 10,000 SF.
Yes, each trade has a $100 application fee.
Failure to pass an inspection results in a $70 fee.