What's Required in Corpus Christi

  • Only one detached ADU is allowed per lot, in a residential zoning district.
  • The owner must live in the main house or the ADU.
  • The ADU may not exceed the house's gross floor area or the district cap of 500, 800 or 1,000 square feet.
  • The house and ADU together must stay within the district's building coverage and height.
  • The ADU must meet all principal-structure yard requirements.
  • Separate utility meters are prohibited except for irrigation.
  • Plans need a sealed foundation plan, energy compliance, a WPI-1 form and sealed windstorm drawings.
  • The lot must be platted before a building permit can be issued.

Can you build an ADU in Corpus Christi?

Yes. Under Section 5.3.2.A of the Unified Development Code (UDC), a detached accessory dwelling unit may be permitted in any residential zoning district, and it may include a full kitchen. Only one ADU is allowed per lot, and the property owner must live in either the main house or the ADU. ADUs are not permitted within a Cottage Housing Development or a mixed-use development. Separate meters are prohibited except for irrigation, so the ADU shares the lot's utility meters.

How big can an ADU be in Corpus Christi?

The ADU's floor area may not exceed the lesser of the main house's gross floor area or the cap for your zoning district: 1,000 square feet of habitable space in the FR, RE and RS-22 districts; 800 square feet in RS-15 and RS-10; and 500 square feet in RS-6 and RS-4.5, rising to 800 square feet on lots over 10,000 square feet. An existing, legally conforming garage built before 1980 may be converted to one ADU with no floor-area maximum, including an upper-story unit over the garage. The house and ADU together must stay within the district's building coverage, the ADU must meet all principal-structure yard requirements, and it may not exceed the district's height limit.

How much does an ADU permit cost in Corpus Christi?

Residential permits are priced on square footage, since Texas Local Government Code 214.907 (H.B. 852) bars value-based residential fees. The FY 2026 Development Fee Schedule, effective October 1, 2025 to September 30, 2026, charges plan review at $0.146 per square foot, the building permit at $0.461 per square foot (minimum $146.41), and each electrical, mechanical and plumbing permit at $0.075 per square foot with a $146.41 minimum. A 500 sq ft ADU is $73.00 plus $230.50, or $303.50, and, if all three trades are needed, three trade permits at the $146.41 floor add $439.23, for $742.73. The schedule prints a $146.41 Minimum Permit Fee line under each trade permit, below the commercial row; we read it as the residential floor too, so confirm with Development Services before budgeting. The schedule does not say which area it uses for trade permits; we used the work area. An 800 sq ft unit comes to $924.83 and a 1,000 sq ft unit to $1,046.23. Starred fees add a 4.5% surcharge (about $33 if applied to the whole $742.73), a $100.00 residential floodplain review applies where needed, and water and sewer taps are separate. The schedule's period has ended and it is still the newest posted, so confirm.

What you are doingCity filingRule
Detached ADU in an RS-6 or RS-4.5 districtBuilding plus three trade permitsUp to 500 sq ft, or 800 sq ft on lots over 10,000 sq ft
Detached ADU in RS-15 or RS-10Building plus three trade permitsUp to 800 sq ft
Detached ADU in FR, RE or RS-22Building plus three trade permitsUp to 1,000 sq ft of habitable space
Converting a garage built before 1980Building permitNo floor-area maximum if legally conforming
Second ADU on the same lotNot allowedOne ADU per lot
Owner living elsewhereNot allowedOwner lives in the house or the ADU
Separate electric or water meter for the ADUNot allowedIrrigation meters only

What does an ADU application need?

Treat it as a new residential building. The city's new-construction submission includes the building permit application, a site plan, floor plan, exterior elevations, roof plan and building section, a foundation plan sealed by a Texas professional engineer, an energy compliance certificate, the Texas Department of Insurance WPI-1 windstorm form and windstorm drawings sealed by a Texas professional engineer, plus an elevation certificate in a floodplain. The residential checklist adds a Manual J and duct layout and a tap application. File everything in the Dynamic Portal, the city's online permit portal; trade permits follow once the building permit is issued, and the property must be platted.

How to Get a ADU Permit in Corpus Christi

1

Confirm your district

Look up your zoning district to find the 500, 800 or 1,000 square foot cap and the yard and height limits.

2

Hire the engineer and designer

Get sealed foundation and windstorm drawings, the WPI-1 form, energy compliance and a Manual J.

3

Apply in the Dynamic Portal

Upload the full new-residential package, with an elevation certificate if the lot is in a floodplain.

4

Pay fees and add trades

Pay the square-foot building fees and the electrical, mechanical and plumbing permits as they are added.

5

Build and pass inspections

Schedule each inspection in the portal and have the windstorm engineer inspect for the TDI certificate.

Frequently Asked Questions

Yes. The Unified Development Code allows one detached accessory dwelling unit per lot in any residential zoning district, with a full kitchen if you want one. The owner must live in the main house or the ADU, and ADUs are not allowed in cottage housing or mixed-use developments.
It depends on the district and is never more than the main house's gross floor area: 1,000 square feet in FR, RE and RS-22, 800 in RS-15 and RS-10, and 500 in RS-6 and RS-4.5, or 800 on lots over 10,000 square feet. A legally conforming garage built before 1980 can be converted with no size cap.
Under the FY 2026 schedule, plan review is $0.146 and the building permit $0.461 per square foot, plus electrical, mechanical and plumbing permits, if all three are needed, at the $146.41 floor we read in the schedule. That is about $742.73 for a 500 square foot unit and $1,046.23 for 1,000 square feet, before the 4.5 percent surcharge and any water or sewer tap charges.
No. The Unified Development Code prohibits separate meters for an ADU except for irrigation, so the unit is served through the lot's existing meters. The new-residential checklist still asks for a tap application where new service is needed.
Yes. The Unified Development Code requires the property owner to occupy either the principal dwelling or the accessory dwelling unit. The code does not discuss renting, so ask Development Services how the rule applies to your plans.