Permit Required?
Required
Typical Fee Range
$175–$250
A $100 trade application fee plus standard inspection fees ($70+).
Fee Method
Flat rate
What's Required in Tampa
- Electrical permit mandatory for panel replacements or service upgrades
- Work must comply with the 2026 Florida Electrical Code/NEC
- Proper grounding and bonding is required for all service replacements
- Notice of Commencement required if project value exceeds $2,500
- Electrical 'Release' from CSD is required before TECO can restore power
- Final electrical inspection required to close the permit and authorize power
How to Get a Electrical Panel Permit in Tampa
1
Step 1: Portal Login
Access Accela Citizen Access and select 'Electrical Residential'.
2
Step 2: Detail Service
Specify amperage (e.g. 200 Amp) and current TECO service details.
3
Step 3: Fee Payment
Pay the total permit fee ($175 minimum) online.
4
Step 4: Installation
Complete the work according to 2026 NEC standards.
5
Step 5: Inspection & Release
Schedule inspection; CSD notifies TECO for service restoration after passing.
Frequently Asked Questions
Yes, an electrical permit is always required for panel and service work.
Standard fees start at approximately $175 including application.
Yes, for their primary residence if they perform the work themselves.