Permit Required? Required
Typical Fee Range $175–$250 A $100 trade application fee plus standard inspection fees ($70+).
Fee Method Flat rate

What's Required in Tampa

  • Electrical permit mandatory for panel replacements or service upgrades
  • Work must comply with the 2026 Florida Electrical Code/NEC
  • Proper grounding and bonding is required for all service replacements
  • Notice of Commencement required if project value exceeds $2,500
  • Electrical 'Release' from CSD is required before TECO can restore power
  • Final electrical inspection required to close the permit and authorize power

How to Get a Electrical Panel Permit in Tampa

1

Step 1: Portal Login

Access Accela Citizen Access and select 'Electrical Residential'.

2

Step 2: Detail Service

Specify amperage (e.g. 200 Amp) and current TECO service details.

3

Step 3: Fee Payment

Pay the total permit fee ($175 minimum) online.

4

Step 4: Installation

Complete the work according to 2026 NEC standards.

5

Step 5: Inspection & Release

Schedule inspection; CSD notifies TECO for service restoration after passing.

Frequently Asked Questions

Yes, an electrical permit is always required for panel and service work.
Standard fees start at approximately $175 including application.
Yes, for their primary residence if they perform the work themselves.