What's Required in Stockton
- Every ADU and JADU needs a building permit, issued ministerially.
- A detached ADU may be up to 1,200 sq ft; an attached one up to 50 percent of the home or 850 sq ft.
- A JADU must be within the house, no more than 500 sq ft, with the owner living on site.
- New ADUs need at least 3 ft side and rear setbacks.
- No off-street parking is required, including for garage conversions.
- Fire sprinklers are required only if the main house is sprinklered.
- The application must include the ADU Survey and a scaled site plan.
- School district fees apply to ADUs of 750 sq ft or more.
Do You Need a Permit for an ADU in Stockton?
Yes. The city's ADU Guide (June 2026) says a building permit is required to build any accessory dwelling unit, and Planning approval is part of it. Under California ADU law and Stockton Municipal Code 16.80.310, as reprinted in the guide, the city must issue the permit ministerially, without discretionary review or a hearing, and the state housing department's ADU Handbook (March 2026) says an agency must approve or deny a complete application within 60 days. Design Review comes first only for an ADU with exterior changes in the Magnolia historic district or accessory to a landmark, in a design review overlay district where it is visible from a public right-of-way, or in the Channel Area overlay.
How Big Can an ADU Be in Stockton?
- Detached: up to 1,200 square feet.
- Attached: up to 50 percent of the existing home or 850 square feet, whichever is greater.
- Conversion of existing space or an accessory structure: no size limit in the guide.
- JADU: no more than 500 square feet, inside the house, with the owner living on site.
New ADUs may sit 3 feet from side and rear lot lines, need 5 feet from other structures, and need no off-street parking, even when a garage is converted. The owner need not live on the lot unless there is a JADU. Fire sprinklers are required only if the main house has them.
Stockton ADU Rules by Scenario
| What you are doing | City filing | Rule |
|---|---|---|
| Detached ADU up to 1,200 sq ft | Building permit, ministerial | SMC 16.80.310 via ADU Guide |
| Attached ADU | Building permit | 50 percent of home or 850 sq ft |
| Garage conversion | Building permit | No replacement parking |
| JADU inside the house | Building permit; Express Review eligible | 500 sq ft; owner occupancy; deed restriction |
| City pre-approved studio, 1- or 2-bedroom plan | Building permit with site plan | Free plans; not in a FEMA flood zone |
| ADU built without permits before 2020 | Legalization permit | AB 2533; impact fees waived |
How Much Does an ADU Permit Cost in Stockton?
An ADU is priced by valuation under the FY 2026-27 Adopted Fee Schedule, effective July 1, 2026, with valuation set from the ICC valuation table. Over $99,999 the building permit is $1,078 plus $0.006787 for each dollar over $100,000, and plan check is 42% of the permit fee:
- Valuation $150,000: $1,078 + $339.35 = $1,417.35 permit, plus $595.29 plan check, $2,013.
- Valuation $250,000: $1,078 + $1,018.05 = $2,096.05 permit, plus $880.34 plan check, $2,976.
If the city applies its Master Plan rate (21% plan check) to its pre-approved plans, the plan check would be lower; ask the Permit Center.
The schedule also lists add-ons and does not say which of them land on a given permit: a building technology fee of 7.5% of the permit fee, a Community Rating System admin fee of 6% of the permit fee, a General Plan fee of 0.15% of valuation, a capital preservation fee of 0.1% of valuation, and two state pass-throughs, the strong-motion fee (0.013% of valuation for homes) and the green building fee ($1 up to $25,000 of valuation). Our ranges show the table fees only.
Impact fees are where ADUs save: the city does not apply its Public Facilities Fees to ADU permits, and state law bars impact fees on an ADU of 750 square feet of interior livable space or less. The guide says school district fees and pass-through fees apply to ADUs of 750 square feet or greater, and separate water and sewer connections bring connection fees.
How Do You Get an ADU Permit in Stockton?
The city offers three pre-approved plans free of charge, all-electric: a 469 SF studio, a 625 SF one-bedroom and a 746 SF two-bedroom. With one, you submit the application, a scaled site plan, the Hold Harmless Agreement, the ADU Survey and, if you are the builder, the Owner/Builder form. No vendor plans are pre-approved yet. A custom ADU follows the ADU/JADU submittal checklist (BLDG-0103), with plans as PDF files. A new ADU may need rooftop solar on a separate permit.
How to Get a ADU Permit in Stockton
Check your lot
Call Planning at (209) 937-8266 or use the Virtual Assistant to confirm zoning, flood zone and any overlay district.
Pick a plan
Choose a free city pre-approved plan or have a custom design drawn to the BLDG-0103 checklist.
Submit the package
Send the application, site plan, plans, ADU Survey and Hold Harmless Agreement as PDF files in person or by email.
Pay fees
Pay permit and plan check fees and any school fees, bringing the school fee compliance form and receipt to the city.
Build and inspect
Schedule inspections online or at (209) 937-8560; any required solar permit must be finaled before the ADU final.