Title 24 - TECHNICAL CODES | Code of Ordinances | San Jose, CA | Municode Library
  • Title 24 - TECHNICAL CODES

  • Chapter 24.01 - ADMINISTRATION

  • Part 1 - GENERAL


  • 24.01.100 - Purpose.

    The purpose of this title is to provide for the administration and enforcement of the building, residential, plumbing, mechanical, electrical, wildland-urban interface, existing building, energy, green building standards, and historical codes adopted by the City of San José.

    (Ords. 28166, 28838, 29806, 31256.)

  • 24.01.110 - Scope.

    The provisions of this title shall serve as the administrative, organizational and enforcement rules and regulations for the technical codes which regulate site preparation and construction, alteration, moving, demolition, repair, use and occupancy of buildings, structures and building service equipment within the city.

    (Ord. 28166.)

  • 24.01.120 - Exemption for pending applications.

    A.

    The provisions of the 2025 California Building, Residential, Plumbing, Mechanical, Electrical, Wildland-Urban Interface Codes, California Existing Building Code, California Historical Building Code, California Energy Code, California Green Building Standards Code and California Existing Building Code as adopted and amended herein, shall not apply to any building or structure for which application for a building permit was made prior to January 1, 2026. Such buildings or structure shall be erected, constructed, enlarged, altered or repaired in accordance with the provisions of this chapter in effect at the date of said application.

    B.

    All other applications shall be processed in accordance with the provisions of the 2025 edition of the California Building Code, the California Residential Code, the California Plumbing Code, the California Mechanical Code, the California Existing Building Code, the California Electrical Code, the California Historical Building Code, the California Energy Code, the California Green Building Standards Code, the California Existing Building Code, and the California Wildland-Urban Interface Code as adopted and amended herein.

    (Ords. 28166, 28838, 29334, 29806, 30326, 30837, 31256.7.)

  • 24.01.130 - Compliance with title provisions required.

    It shall be unlawful for any person to erect, construct, enlarge, alter, repair, move, improve, remove, convert, demolish, equip, use, occupy or maintain any building or structure in the city, or cause or permit or suffer the same to be done, in violation of this title or in violation of any of the provisions of the Codes adopted hereunder.

    (Ord. 28166.)

  • Part 2 - DEFINITIONS


  • 24.01.200 - Definitions.

    The definitions set forth in this part shall govern the application and interpretation of this title.

    (Ord. 28166.)

  • 24.01.208 - Alter or alteration.

    "Alter" or "alteration" means any construction or renovation to an existing structure other than repair or addition.

    (Ords. 28166, 28838.)

  • 24.01.211 - Administrative authority.

    "Administrative authority" is the chief building official or a regularly authorized deputy.

    (Ord. 28166.)

  • 24.01.215 - Approved.

    "Approved," as to materials, types of construction, equipment and systems, refers to approval by the building official as the result of investigation and tests conducted by the building official, or by reason of accepted principles or tests by recognized authorities, technical or scientific organizations.

    (Ord. 28166.)

  • 24.01.218 - Approved agency.

    "Approved agency" means an established and recognized organization regularly engaged in conducting tests, furnishing inspection services or furnishing product evaluation or certification where such organization has been approved by the building official.

    (Ords. 28166, 31256.)

  • 24.01.224 - Building code.

    "Building code" means the California Building Code, or CBC, 2025 edition, based on 2024 International Building Code promulgated by the International Code Council, including the appendix thereto, together with those omissions, amendments, exceptions and additions thereto as amended in Title 24 of the California Code of Regulations and in this title.

    (Ords. 28166, 28838, 29334, 29806, 30326, 30837, 31256.)

  • 24.01.227 - Building official.

    "Building Official" means the Chief Building Official, or a regularly authorized deputy.

    (Ord. 28166.)

  • 24.01.230 - Building service equipment.

    "Building service equipment" refers to the plumbing, mechanical, electrical and elevator equipment including piping, wiring, fixtures and other accessories which provide sanitation, lighting, heating, ventilation, cooling, refrigeration, fire-fighting and transportation facilities essential to the occupancy of the building or structure for its designated use.

    (Ord. 28166.)

  • 24.01.231 - Department.

    "Department" means the department of planning, building and code enforcement.

    (Ord. 28166.)

  • 24.01.232 - Director.

    "Director" means the director of planning, building and code enforcement.

    (Ord. 28166.)

  • 24.01.233 - Electrical code.

    "Electrical code" means the California Electric Code or CEC, 2025 edition, based on 2023 National Electric Code promulgated by the National Fire Protection Association, as amended and set forth in the California Building Standards Code, Title 24, Part 3 and in this title.

    (Ords. 28166, 28838, 29334, 29806, 30326, 30837, 31256.)

  • 24.01.236 - Existing building.

    "Existing building" means a building legally erected prior to January 1, 2026 or one for which a legal building permit has been issued.

    (Ords. 28166, 28838, 29334, 29806, 30326, 30837, 31256.)

  • 24.01.237 - Existing building code.

    "Existing building code" means the California Existing Building Code, or CEBC, 2025 edition, based on 2024 International Existing Building Code promulgated by the International Code Council, including the appendix thereto, together with those omissions, amendments, exceptions and additions thereto as amended in Title 24 of the California Code of Regulations and in this title.

    (Ords. 28838, 29334, 29806, 30326, 30837, 31256.)

  • 24.01.238 - Fire code.

    "Fire code" is the California Fire Code or CFC, 2025 edition, based on 2024 International Fire Code promulgated by the International Code Council, including the appendix thereto, together with those omissions, amendments, exceptions and additions thereto as amended in the California Code of Regulations and in this title.

    (Ords. 28166, 28838, 29334, 29806, 30326, 30837, 31256.)

  • 24.01.239 - Green building standards code.

    "Green Building Standards Code" means the California Green Building Standards Code, or CAL Green, 2025 edition, including the appendix thereto, together with those omissions, amendments, exceptions and additions thereto as amended in Title 24 of the California Code of Regulations and in this Title.

    (Ords. 28838, 29334, 29806, 30311, 30834, 31256.)

  • 24.01.240 - Historical building code.

    "Historical building code" means the California Historical Building Code, or CHBC, 2025 edition, including the appendix thereto in Title 24 of the California Code of Regulations, together with those omissions, amendments, exceptions and additions thereto as amended in this title.

    (Ords. 28838, 29334, 29806, 30326, 30837, 31256.)

  • 24.01.241 - Reserved.

    Editor's note— Ord. 30326, § 8, adopted Nov. 5, 2019, repealed § 24.01.241, which pertained to the International Existing Building Code and derived from Ords. 28838, 29334, and 29806.

  • 24.01.242 - Listed and listing.

    "Listed" and "listing" are terms referring to equipment and materials which are shown in a list published by an approved testing agency, qualified and equipped for experimental testing and maintaining an adequate periodic inspection of current productions and which listing states that the material or equipment complies with accepted national standards which are approved, or standards which have been evaluated for conformity with approved standards. Terms that are used to identify listed equipment, products or materials include "listed," "certified," "classified" or other terms as determined by the listing organization.

    (Ords. 28166, 31256.)

  • 24.01.243 - Energy code.

    "Energy code" means the California Energy Code, 2025 edition, including the appendix thereto in Title 24 of the California Code of Regulations, together with those omissions, amendments, exceptions and additions thereto as amended in this Title.

    (Ord. 31256.)

    Editor's note— Ord. 31256, § 12, adopted Nov. 18, 2025, amended § 24.01.243 in its entirety, in effect repealing and reenacting said § 24.01.243 to read as set out herein. The former § 24.01.243 pertained to building energy efficiency standards and derived from Ords. 29806, 30311, 30834.

  • 24.01.245 - Mechanical code.

    "Mechanical code" is the California Mechanical Code or CMC, 2025 edition, based on 2024 Uniform Mechanical Code promulgated by the International Association of Plumbing and Mechanical Officials, together with those omissions, amendments, exceptions and additions thereto as amended in Title 24 of the California Code of Regulations and in this title.

    (Ords. 28166, 28838, 29334, 29806, 30326, 30837, 31256.)

  • 24.01.251 - Occupancy.

    "Occupancy" is the purpose for which a building, or part thereof, is used or intended to be used.

    (Ord. 28166.)

  • 24.01.257 - Permit.

    "Permit" is an official document or certificate issued by the building official authorizing performance of a specified building, plumbing, mechanical, or electrical activity or any combination of such permits issued jointly by the building official.

    (Ord. 28166.)

  • 24.01.260 - Plumbing code.

    "Plumbing code" is the California Plumbing Code, or CPC, 2022 edition, based on 2021 Uniform Plumbing Code promulgated by the International Association of Plumbing and Mechanical Officials, including the appendix thereto, together with those omissions, amendments, exceptions and additions thereto as amended in Title 24 of the California Code of Regulations and in this title.

    (Ords. 28166, 28838, 29334, 29806, 30326, 30837, 31256.)

  • 24.01.263 - Repair.

    "Repair" is the reconstruction, replacement or renewal of any part of an existing building, structure or building service equipment for the purpose of its maintenance and/or sustained damage.

    (Ords. 28166, 31256.)

  • 24.01.265 - Residential code.

    "Residential code" means the California Residential Code, or CRC, 2025 edition, based on 2024 International Residential Code promulgated by the International Code Council, including the appendix thereto, together with those omissions, amendments, exceptions and additions thereto as amended in Title 24 of the California Code of Regulations and in this title.

    (Ords. 28838, 29334, 29806, 30326, 30837, 31256.)

  • 24.01.266 - Structural observation.

    "Structural observation" means the visual observation of the structural system by a registered design professional for general conformance to the approved construction documents. Structural observation does not include or waive the responsibility for the inspections required by Part 5 of this chapter, CBC Section 1704, and other sections of the Building Code.

    (Ords. 28166, 28838.)

  • 24.01.269 - Structure.

    "Structure" is that which is built or constructed, an edifice or building of any kind, or any piece of work artificially built up or composed of parts joined together in some definite manner.

    (Ord. 28166.)

  • 24.01.272 - Technical codes.

    "Technical codes" refer to those codes adopted by this chapter containing the provisions for design, construction, alteration, addition, repair, removal, demolition, use, location, occupancy and maintenance of buildings and structures and building service equipment as herein defined which include but are not limited to California Building Code, California Residential Code, California Plumbing Code, California Mechanical Code, California Electrical Code, California Existing Building Code, California Historical Building Code, California Energy Code, California Wildland-Urban Interface Code, and California Green Building Standards Code.

    (Ords. 28166, 28838, 29806, 30326, 31256.)

  • 24.01.273 - Wildland-urban interface code.

    "Wildland-Urban Interface code" means the California Wildland-Urban Interface Code, or CWUIC, 2025 edition, based on 2024 International Wildland-Urban Interface Code promulgated by the International Code Council, including the appendix thereto, together with those omissions, amendments, exceptions and additions thereto as amended in Title 24 of the California Code of Regulations and in this title.

    (Ord. 31256.)

  • Part 3 - EXISTING BUILDINGS AND BUILDING SERVICE EQUIPMENT


  • 24.01.300 - Application of technical provisions to existing buildings and building service equipment.

    The provisions of this part govern the application of the technical codes to existing buildings and building service equipment.

    (Ord. 28166.)

  • 24.01.310 - General.

    Buildings, structures and their building service equipment to which additions, alterations or repairs are made shall comply with all the requirements of the technical codes for new facilities, except as specifically provided in this part.

    (Ord. 28166.)

  • 24.01.320 - Additions, alterations or repairs.

    Additions, alterations or repairs may be made to a building or its building service equipment without requiring the existing building or its building service equipment to comply with all the requirements of the technical codes, provided the addition, alteration or repair conforms to that required for a new building or building service equipment.

    (Ord. 28166.)

  • 24.01.322 - Additions, alteration or repairs: unsafe conditions.

    A.

    Additions or alterations shall not be made to an existing building or building service equipment which will cause the existing building or building service equipment to be in violation of the provisions of the technical codes nor shall such additions or alterations cause the existing building or building service equipment to become unsafe.

    B.

    An unsafe condition shall be deemed to have been created if an addition or alteration may cause the existing building or building service equipment to become structurally unsafe or overloaded; may not provide adequate egress in compliance with the provisions of the Building Code or may obstruct existing exits; may create a fire hazard; may reduce required fire resistance; may cause building service equipment to become overloaded or exceed their rated capacities; may create a health hazard or may otherwise create conditions dangerous to human life.

    (Ord. 28166.)

  • 24.01.324 - Additions, alteration or repairs: height, number of stories and area.

    A.

    A building altered pursuant to a repair or alteration permit, which involves a change in use or occupancy, shall not exceed the height, number of stories and area permitted by the Building Code for new buildings.

    B.

    A building plus new additions, shall not exceed the height, number of stories and area specified by the Building Code for new buildings.

    (Ord. 28166.)

  • 24.01.326 - Additions, alteration or repairs: compliance with code requirements.

    A.

    Additions or alterations shall not be made to an existing building or structure when the existing building or structure is not in full compliance with the provisions of the Building Code, except when the addition or alteration will result in the existing building or structure being no more hazardous, based on life safety, fire safety and sanitation, than before such additions or alterations are undertaken.

    B.

    Exception: Alterations of existing structural elements, or additions of new structural elements which are not required by Section 24.01.340 of this chapter and Section 24.01.350 of this chapter and which are initiated for the purpose of increasing the lateral-force-resisting strength or stiffness of an existing structure need not be designed for forces conforming to these regulations provided that an engineering analysis is submitted to show that:

    1.

    The capacity of existing structural elements required to resist forces is not reduced, and

    2.

    The lateral loading to required existing structural elements is not increased beyond their capacity, and

    3.

    New structural elements are detailed and connected to the existing structural elements as required by these regulations, and

    4.

    New or relocated nonstructural elements are detailed and connected to existing or new structural elements as required by these regulations, and

    5.

    An unsafe condition as defined above is not created.

    (Ord. 28166.)

  • 24.01.330 - Additions, alteration or repairs: use of same materials.

    Alterations or repairs to an existing building or structure which are nonstructural and do not adversely affect a structural member or a part of the building or structure having required fire resistance may be made with the same materials of which the building or structure is constructed, subject to approval by the building official. Installation or replacement of glass shall be as required for new installations.

    (Ord. 28166.)

  • 24.01.332 - Minor additions, alterations and repairs.

    Minor additions, alterations and repairs to existing building service equipment installations may be made in accordance with the technical code in effect at the time the original installation was made, subject to approval of the building official, and provided such additions, alterations and repairs will not cause the existing building service equipment to become unsafe, unsanitary or overloaded.

    (Ord. 28166.)

  • 24.01.340 - Existing building service installations.

    Building service equipment lawfully in existence at the time of the adoption of the technical codes may have their use, maintenance or repair continued if the use, maintenance or repair is in accordance with the original design and a hazard to life, health or property has not been created by such building service equipment.

    (Ord. 28166.)

  • 24.01.350 - Existing occupancy.

    A.

    Buildings in existence on December 31, 2025 may have their existing use or occupancy continued if the use or occupancy was legal at the time of the adoption of the building code, and provided continued use is not dangerous to life, health and safety.

    B.

    A change in the use or occupancy of any existing building or structure shall comply with the provisions of Part 6 of Chapter 24.02 and Chapter 24.07.

    (Ords. 28166, 28838, 29334, 29806, 30326, 30837, 31256.)

  • 24.01.355 - Maintenance.

    A.

    Buildings, structures and building service equipment, existing and new, and parts thereof shall be maintained in a safe and sanitary condition.

    B.

    Devices or safeguards which are required by the technical codes shall be maintained in conformance with the technical code under which installed.

    C.

    The owner or the owner's designated agent shall be responsible for the maintenance of buildings, structures and their building service equipment.

    D.

    The building official may cause a structure to be reinspected to determine compliance with this subsection.

    (Ord. 28166.)

  • 24.01.360 - Moved buildings.

    Buildings, structures and their building service equipment moved into or within the city shall comply with the provisions of the technical codes for new buildings or structures and their building service equipment.

    (Ord. 28166.)

  • 24.01.365 - Temporary structures.

    A.

    Temporary structures such as reviewing stands and other miscellaneous structures, sheds, canopies or fences used for the protection of the public around and in conjunction with construction work may be erected by a permit issued pursuant to CBC 3103.

    B.

    Buildings or structures erected under a temporary structure permit shall comply with CBC 3103.

    C.

    Temporary buildings or structures shall be completely removed upon the expiration of the time limit stated in the permit.

    (Ords. 28166, 29334.)

  • 24.01.370 - Historic buildings.

    Repairs, alterations and additions necessary for the preservation, restoration, rehabilitation or continued use of a building, structure, or its building service equipment may be made without conforming to the requirements of the technical codes when authorized by the building official, provided:

    A.

    The building or structure has been designated by official action of the legally constituted authority of the city as having special historical or architectural significance.

    B.

    Unsafe conditions as described in this title are corrected.

    C.

    The restored building or structure and its building service equipment will be no more hazardous based on life safety, fire safety and sanitation than the existing building.

    (Ord. 28166.)

  • Part 4 - INTERPRETATION


  • 24.01.410 - Conflicting provisions.

    A.

    When conflicting provisions or requirements relating to building standards occur between this title, the technical codes and other codes or laws, the most restrictive shall govern.

    B.

    When conflicts occur between building standards in the technical codes, those provisions providing the greater safety to life shall govern. Where sanitation, life safety, or fire safety are not involved, the most restrictive building standards provisions shall govern.

    C.

    Where in a specific case different sections of the technical codes specify different materials, methods of construction or other building standard requirements, the most restrictive shall govern. When there is a conflict between the general building standard requirement and a specific requirements, the specific requirement shall be applicable.

    D.

    Where conflicts occur between administrative provisions in this Code and administrative provisions in the technical codes, the provisions in this Code shall govern.

    (Ords. 28166, 29334.)

  • 24.01.420 - Alternate materials, methods of design and methods of construction.

    A.

    The provisions of the technical codes are not intended to prevent the use of any material, appliance, installation, device, arrangement, design or method of construction not specifically prescribed by the technical codes, provided an alternate has been approved and its use authorized by the building official.

    B.

    The building official may approve an alternate, provided the building official finds that the proposed design is satisfactory and complies with the provisions of the technical codes and that the material, method or work offered is, for the purpose intended, at least the equivalent of that prescribed in the technical codes in suitability, strength, effectiveness, fire resistance, durability, safety and sanitation.

    C.

    The building official shall require that sufficient evidence or proof be submitted to substantiate claims that may be made regarding its use.

    D.

    The details of an action granting approval of an alternate shall be recorded and entered in the department's files.

    E.

    The building official may require the applicant to arrange for the proposed alternate materials, methods of design and methods of construction be reviewed and evaluated by an outside agency designated by the building official at the applicant's expense.

    (Ords. 28166, 28838.)

  • 24.01.430 - Modifications.

    A.

    Whenever there are practical difficulties involved in carrying out the provisions of the technical codes, the building official may grant modifications for individual cases.

    B.

    The building official shall first find that:

    1.

    A special individual reason makes the strict letter of the technical code impractical;

    2.

    The modification is in conformity with the intent and purpose of the technical code, and

    3.

    Such modification does not lessen health, life safety and fire safety requirements or any degree of structural integrity.

    C.

    The details of actions granting modifications shall be recorded and entered in the department's files.

    D.

    The building official may require the applicant to arrange for the proposed modification be reviewed by an outside agency designated by the building official at the applicant's expense.

    (Ord. 28166.)

  • 24.01.440 - Tests.

    A.

    Whenever there is insufficient evidence for determining compliance with the provisions of the technical codes or evidence that materials or construction do not conform to the requirements of the technical codes, the building official may require tests as evidence of compliance to be made at the applicant's expense.

    B.

    Test methods shall be as specified by the technical codes or by other recognized test standards. In the absence of recognized and accepted test methods, the building official shall determine test procedures.

    C.

    Tests shall be made by an approved agency.

    D.

    Reports of such tests shall be entered in the department's files.

    E.

    The building official may require the applicant to arrange for the test procedures, methodology, results, reports, etc. to be reviewed and evaluated by an outside agency designated by the building official at the applicant's expense.

    (Ord. 28166.)

  • Part 5 - AUTHORITY


  • 24.01.500 - Building official powers and duties.

    A.

    The building official is authorized and directed to enforce all of the provisions of this title, and the technical codes, excepting that the provisions of Chapter 9 of building code and part 7 California Wildland-Urban Interface code shall be enforced jointly with the chief of the fire department. For such purposes, the building official and the chief of the fire department, respectively, and their respective authorized representatives, shall each have the powers of a peace officer.

    B.

    The building official shall have all of the following powers and authority subject to the direction and supervisory authority of the director with regard to:

    1.

    The authority granted to the "building official" by this title and the CBC.

    2.

    The authority granted to the "administrative authority" by this title, the CPC and CMC.

    3.

    The authority required to enforce the CEC.

    4.

    The authority required to enforce the CRC.

    5.

    The authority required to enforce the CALGreen.

    6.

    The authority required to enforce the CHBC.

    7.

    The authority required to enforce the CEBC.

    8.

    The authority required to enforce the California Energy Code.

    (Ords. 28166, 28838, 29806, 30326, 31256.)

  • 24.01.510 - Interpretations and policies.

    The building official shall have the power and authority to render interpretations of this title and the technical codes and to adopt and enforce rules, policies, procedures and supplemental regulations in order to clarify the application of its provisions. Such interpretations, policies, procedures, rules and regulations shall be in conformance with the intent and purpose of this title.

    (Ord. 28166.)

  • 24.01.520 - Deputies.

    In accordance with department procedures, the building official may appoint such number of technical officers and inspectors and other employees as shall be authorized from time to time. The building official may deputize such inspectors or employees as may be necessary to carry out the functions of the department.

    (Ord. 28166.)

  • 24.01.530 - Right of entry.

    A.

    The building official may enter the building or premises at all reasonable times to inspect or to perform the duties imposed by this title:

    1.

    When necessary to make an inspection to enforce any of the provisions of this Title and the technical codes, or

    2.

    When the building official has reasonable cause to believe that there exists in any building or upon a premises a condition which is contrary to or in violation of this title which makes the building or premises unsafe, dangerous or hazardous.

    B.

    The building official shall adhere to the following procedures in making an entry:

    1.

    If such building or premises be occupied, the building official shall present credentials to the occupant and request entry.

    2.

    If such building or premises be unoccupied, the building official shall first make a reasonable effort to locate the owner or other persons having charge or control of the building or premises and request entry.

    3.

    Should entry be refused, the building official shall have recourse to the remedies provided by law to secure entry.

    (Ord. 28166.)

  • 24.01.540 - Stop orders.

    When work is being done contrary to the provisions of this title, the technical codes, or other pertinent laws or ordinances implemented through the enforcement of this title, the building official may order the work stopped by notice in writing served on persons engaged in the doing or causing such work to be done, and such persons shall forthwith stop the work until authorized by the building official to proceed with the work.

    (Ord. 28166.)

  • 24.01.550 - Occupancy violations.

    When a building or structure or building service equipment therein regulated by this title and the technical codes is being used contrary to the provisions of such codes, the building official may order such use discontinued by written notice served on any person causing such use to be continued. Such person shall discontinue the use within the time prescribed by the building official after receipt of such notice to make the structure, or portion thereof, comply with the requirements of such codes.

    (Ord. 28166.)

  • 24.01.560 - Authority to disconnect utilities.

    The building official or the building official's authorized representative shall have the authority to disconnect a utility service or energy supplied to the building, structure or building service equipment therein regulated by this title or the technical codes in case of emergency where necessary to eliminate an immediate hazard to life or property. The building official shall whenever possible notify the serving utility, the owner and occupant of the building, structure or building service equipment of the decision to disconnect prior to taking such action, and shall notify such serving utility, owner and occupant of the building, structure or building service equipment, in writing, of such disconnection immediately thereafter.

    (Ord. 28166.)

  • 24.01.570 - Authority to condemn building service equipment.

    A.

    When the building official ascertains that building service equipment regulated in the technical codes has become hazardous to life, health or property, or has become unsanitary, the building official shall order, in writing, that such equipment either be removed or restored to a safe or sanitary condition, as appropriate.

    B.

    The written notice itself shall fix a time limit for compliance with such order. Defective building service equipment shall not be maintained after receiving such notice.

    C.

    When such equipment or installation is to be disconnected, a written notice of such disconnection and causes therefor shall be given within twenty-four (24) hours to the serving utility, the owner and occupant of such building, structure or premises.

    D.

    When any building service equipment is maintained in violation of the technical codes and in violation of a notice issued pursuant to the provisions of this title, the building official shall institute appropriate action to prevent, restrain, correct or abate the violation.

    (Ord. 28166.)

  • 24.01.580 - Connection after order to disconnect.

    No person shall make or suffer the connection from an energy, fuel or power supply nor supply energy or fuel to building service equipment which has been disconnected or ordered to be disconnected by the building official or the use of which has been ordered to be discontinued by the building official until the building official authorizes the reconnection and use of such equipment.

    (Ord. 28166.)

  • Chapter 24.02 - PERMITS

  • Part 1 - GENERAL


  • 24.02.100 - Permits required.

    Except as specified in this part, no building, structure or building service equipment regulated by this title and the technical codes shall be erected, constructed, enlarged, altered, repaired, moved, improved, removed, converted or demolished unless a separate, appropriate permit for each building, structure or building service equipment has first been obtained from the building official.

    (Ord. 28166.)

  • 24.02.110 - Work exempt from permit.

    A.

    A permit shall not be required for the types of work in each of the separate classes of permit as set forth in this part.

    B.

    Exemption from the permit requirements of this title shall not be deemed to grant authorization for any work to be done in violation of the provisions of the technical codes or any other laws or city ordinances.

    (Ord. 28166.)

  • 24.02.120 - Building permit exemptions.

    A.

    A building permit shall not be required for the following:

    1.

    One-story detached accessory buildings used as tool and storage sheds, playhouses and similar uses, provided the floor area does not exceed 120 square feet (11.15 m2). It is permissible that these structures still be regulated by Part 7 California Wildland-Urban Interface Code despite exemption from permit.

    2.

    Fences, other than swimming pool barriers, not over seven feet (2,134 mm) high.

    3.

    Oil derricks.

    4.

    Nonfixed and movable fixtures cases, racks, counters and partitions not over five feet nine inches (1,753 mm) high.

    5.

    Retaining walls which are not over four feet (1,219 mm) in height measured from the bottom of the footing to the top of the wall, unless supporting a surcharge or impounding Class I, II or III-A liquids.

    6.

    Water tanks supported directly upon grade if the capacity does not exceed five thousand gallons (18,925 liters) and the ratio of height to diameter or width does not exceed two to one.

    7.

    Sidewalks and driveways not more than thirty inches (762 mm) above adjacent grade and not over any basement or story below and are not part of an accessible route.

    8.

    Decks, in Group R-3 occupancy, not exceeding 200 square feet in area, that are not more than 30 inches above grade at any point, are not attached to a dwelling and do not serve the required exit door.

    9.

    Painting, papering, tiling, carpeting, cabinets, counter tops and similar finish work.

    10.

    Temporary motion picture, television and theater stage sets and scenery.

    11.

    Window awnings, in Group R-3 and U occupancies, supported by an exterior wall that do not project more than fifty-four inches from the exterior wall and do not require additional support.

    12.

    Prefabricated swimming pools accessory to a Group R-3 occupancy that are less than 24 inches deep, are not greater than 5,000 gallons and are installed entirely above ground.

    13.

    Replacement, repair or overlay of less than twenty-five percent of an existing roof within any twelve-month period.

    14.

    Swings and other playground equipment accessory to detached one- and two-family dwellings.

    15.

    Taping joints and sheetrock installations for unrated walls and ceilings.

    B.

    Unless otherwise exempted by this title, separate plumbing, electrical and mechanical permits will be required for the above exempted items.

    (Ords. 28166, 28838, 29334, 30326, 31256.)

  • 24.02.130 - Plumbing permit exemptions.

    A plumbing permit shall not be required for the following:

    A.

    The stopping of leaks in drains, soil, waste or vent pipe, provided, however, that should any concealed trap, drainpipe, soil, waste or vent pipe become defective and it becomes necessary to remove and replace the same with new material, such work shall be considered as new work and a permit shall be obtained and inspection made as provided in this title.

    B.

    The clearing of stoppages or the repairing of leaks in pipes, valves or fixtures, and the removal and reinstallation of water closets, provided such repairs do not involve or require the replacement or rearrangement of valves, pipes or fixtures.

    C.

    Reserved.

    (Ords. 28166, 29334, 30326, 31256.)

  • 24.02.140 - Mechanical permit exemptions.

    A mechanical permit shall not be required for the following:

    1.

    A portable heating appliance.

    2.

    Portable ventilating equipment.

    3.

    A portable cooling unit.

    4.

    A portable evaporative cooler.

    5.

    A closed system of steam, hot or chilled water piping within heating or cooling equipment regulated by the Mechanical Code.

    6.

    Replacement of any component part of assembly of an appliance which does not alter its original approval and complies with other applicable requirements of the technical codes.

    7.

    Refrigerating equipment which is part of the equipment for which a permit has been issued pursuant to the requirements of the technical codes.

    8.

    A unit refrigerating system as defined in the Mechanical Code.

    9.

    Self-contained refrigeration system containing 10 pounds (4.54kg) or less of refrigerant and actuated by motors of 1 horsepower (0.75kW) or less.

    (Ords. 28166, 31256.)

  • 24.02.150 - Electrical permit exemptions.

    An electrical permit shall not be required for the following:

    1.

    Minor repair work, including the replacement of lamps or the connection of approved portable electrical equipment to approved permanently installed receptacles.

    2.

    Reserved.

    3.

    Listed cord and plug connected temporary decorative lighting.

    4.

    Reserved.

    5.

    Reinstallation of attachment plug receptacles, but not the outlets.

    6.

    Replacement of any branch circuit overcurrent device of the required capacity in the same location, in one- and two-family dwellings.

    7.

    Reserved.

    8.

    Installation or maintenance of communications wiring, devices, appliances, apparatus, or equipment.

    9.

    Reserved.

    10.

    Installation of any temporary system required for the testing or servicing of electrical equipment or apparatus.

    11.

    Electrical equipment used for radio and television transmissions. This exemption does not apply to equipment and wiring for the power supply and the installations of towers and antennas.

    12.

    Electrical wiring, devices, appliances, apparatus or equipment operating at less than twenty-five (25) volts and not capable of supplying more than fifty (50) watts of energy, except in hazardous (classified) locations, emergency systems, standby systems, energy storage systems, and energy management systems.

    13.

    Reserved.

    14.

    A permit shall not be required for the installation, alteration or repair of electrical wiring, apparatus or equipment or the generation, transmission, distribution or metering of electrical energy or in the operation of signals or the transmission of intelligence that is under the ownership and control of public service agencies by established right.

    (Ords. 28166, 30326, 31256.)

  • Part 2 - APPLICATION REQUIREMENTS


  • 24.02.210 - Application.

    A.

    To obtain a permit an applicant shall file a completed application, in writing, on a form furnished by the building official for that purpose.

    B.

    Every such application shall:

    1.

    Identify and describe the work to be covered by the permit for which application is made.

    2.

    Describe the land on which the proposed work is to be done by legal description, street address or similar description that will readily identify and definitely locate the proposed building or work.

    3.

    Indicate the use or occupancy for which the proposed work is intended.

    4.

    Be accompanied by plans, diagrams, computations and specifications and other data as required in 24.02.220.

    5.

    State the valuation of any new building or structure or any addition, remodeling or alteration to an existing building.

    6.

    Be signed by the applicant, or the applicant's authorized agent.

    7.

    Give such other data and information as may be required by the building official.

    (Ord. 28166.)

  • 24.02.220 - Submittal documents.

    A.

    Plans, specifications, engineering calculations, diagrams, soil investigation reports, special inspection and structural observation programs and other data shall constitute the submittal documents and shall be submitted in one (1) or more sets with each application for a permit.

    B.

    When such plans are not prepared by an architect or engineer, the building official may require the applicant submitting such plans or other data to demonstrate that state law does not require that the plans be prepared by a licensed architect or engineer.

    C.

    The building official may require plans, computations and specifications to be prepared and designed by an engineer or architect licensed by the state to practice as such even if not required by state law.

    D.

    Exception: The building official may waive the submission of plans, calculations, construction inspection requirements and other data if it is found that the nature of the work applied for is such that reviewing of plans is not necessary to obtain compliance with this title.

    (Ord. 28166.)

  • 24.02.230 - Information on plans and specifications.

    A.

    Plans and specifications shall be drawn to scale on electronic document or substantial paper and shall be of sufficient clarity to indicate the location, nature and extent of the work proposed and show in detail that it will conform to the provisions of this title and all relevant laws, ordinances, rules and regulations.

    B.

    Plans for buildings of other than Group R, Division 3 and Group U occupancies shall indicate how required structural and fire-resistive integrity will be maintained when a penetration will be made for electrical, mechanical, plumbing and communication conduits, pipes and similar systems.

    (Ords. 28166, 28838, 29806.)

  • 24.02.240 - Architect or engineer of record.

    A.

    When it is required that documents be prepared by an architect or engineer, the building official may require the owner to engage and designate on the building permit application an architect or engineer who shall act as the architect or engineer of record.

    B.

    If the circumstances require, the owner may designate a substitute architect or engineer of record who shall perform all of the duties required of the original architect or engineer of record.

    C.

    The building official shall be notified, in writing, by the owner if the architect or engineer of record is changed or is unable to continue to perform the duties.

    D.

    The architect or engineer of record shall be responsible for reviewing and coordinating all submittal documents prepared by others, including deferred submittal items, for compatibility with the design of the building.

    (Ord. 28166.)

  • 24.02.245 - Deferred submittals.

    A.

    For the purposes of this chapter, deferred submittals are defined as those portions of the design which are not submitted at the time of the application and which are to be submitted to the building official within a specified period.

    B.

    Deferral of any submittal items shall have prior approval of the building official. The architect or engineer of record shall list the deferred submittals on the plans and shall submit the deferred submittal documents together with any required additional fees for review by the building official prior to their installation.

    C.

    Submittal documents for deferred submittal items shall be submitted to the architect or engineer of record who shall review them and forward them to the building official with a notation indicating that the deferred submittal documents have been reviewed and that they have been found to be in general conformance with the design of the building.

    D.

    The deferred submittal items shall not be installed until their design and submittal documents have been approved by the building official.

    (Ord. 28166.)

  • 24.02.250 - Special inspection and observation program.

    A.

    When special inspection is required by CBC Chapter 17, the architect or engineer of record shall prepare an inspection program which shall be submitted to the building official for approval prior to issuance of the permit.

    B.

    The inspection program shall designate the portions of the work to have special inspection, the name or names of the individuals or firms who are to perform the special inspections and indicate the duties of the special inspectors.

    C.

    The special inspector shall be employed by the owner, the engineer or architect of record, or an agent of the owner, but not the contractor or any other person responsible for the work.

    D.

    When structural observation is required by CBC Chapter 17, the inspection program shall name the individuals or firms who are to perform structural observation and describe the stages of construction at which structural observation is to occur.

    E.

    The inspection program shall include samples of inspection reports and provide time limits for submission of reports.

    (Ords. 28166, 29806.)

  • Part 3 - PERMIT ISSUANCE


  • 24.02.310 - Issuance.

    A.

    The application, plans, specifications, computations and other data filed by an applicant for permit shall be reviewed by the building official as deemed appropriate. Such plans may be reviewed by other city departments to verify compliance with other applicable laws.

    B.

    If the building official finds that the work described in an application for a permit and the plans, specifications and other data filed therewith conform to the requirements of this title and the technical codes and other pertinent laws and ordinances, and that the required fees have been paid, the building official shall issue a permit therefor to the applicant.

    C.

    The building official shall endorse, in writing or stamp, the required plans and specifications.

    D.

    Approved plans and specifications shall not be changed, modified or altered without authorizations from the building official, and all work regulated by this title shall be done in accordance with the approved plans.

    (Ord. 28166.)

  • 24.02.315 - Permits for partial construction.

    A.

    The building official may issue a permit for the construction of part of a building, structure or building service equipment before the entire plans and specifications for the whole building, structure or building service equipment have been submitted or approved, provided adequate information and detailed statements have been filed complying with all pertinent requirements of the technical codes.

    B.

    The holder of a permit for partial construction shall proceed without assurance that the permit for the entire building, structure or building service will be granted.

    (Ord. 28166.)

  • 24.02.320 - Retention of plans.

    A.

    One set of approved plans, specifications and computations shall be retained by the building official for a period of not less than one hundred eighty days from the date of the completion of the work covered therein;

    B.

    One set of approved plans and specifications shall be returned to the applicant and shall be kept in the site of the building or work at all times during which the work authorized thereby is in progress.

    (Ords. 28166, 29806.)

  • 24.02.330 - Validity of permit.

    A.

    The issuance of a permit or approval of plans, specifications and computations shall not be construed to be a permit for, or an approval of any violation of, any of the provisions of this title or the technical codes, or of any other law or ordinance.

    B.

    Permits presuming to give authority to violate or cancel the provisions of this title or of other city ordinances shall not be valid.

    C.

    The issuance of a permit based on plans, specifications and other data shall not prevent the building official from thereafter requiring the correction of errors in the plans, specifications and other data, or from preventing building operations being carried on thereunder when there is a violation of this title or of any other city ordinances.

    (Ord. 28166.)

  • 24.02.340 - Permit expiration.

    A.

    Every permit issued by the building official under the provisions of the technical codes shall expire by limitation and become null and void, if the building or work authorized by such permit is not commenced within twelve (12) months from the date of such permit, or if the building or work authorized by such permit is suspended or abandoned at any time after the work is commenced for a period of one hundred eighty (180) days.

    B.

    All permits shall expire by limitation of time and become null and void unless an inspection indicating substantial progress in construction has been requested and performed every one hundred eighty (180) days or sooner.

    C.

    Before work terminated pursuant to Subsection B. above can be recommenced, a new permit shall be first obtained, and the permittee shall pay new full permit fees.

    (Ords. 28166, 30326.)

  • 24.02.345 - Permit time extensions.

    A.

    A permittee holding an unexpired permit may apply for an extension of the time within which work may commence under that permit, if the permittee can demonstrate that, for good and satisfactory reasons, it is not feasible to commence the work within the required time.

    B.

    The building official may extend the time for action by the permittee for a period not exceeding one hundred eighty (180) days upon payment of appropriate fees and a written request by the permittee showing that circumstances beyond the control of the permittee have prevented action from being taken.

    C.

    Permits shall not be extended more than once, except that, the Building Official may approve a maximum of one additional extension of three hundred sixty days when the applicant demonstrates that special unusual circumstances exist. In this case, the chief building official may require that additional fees be paid and plans be revised to partially or fully comply with the current codes.

    D.

    Permit time extension when there are multiple permits on a single project must comply with all of the following:

    1.

    For the purpose of permit expiration, all permits associated with a single project (i.e., same address, suite, portion of building) will be considered as one project. If an inspection has been performed on any of the permits for the project, all permits will be considered to have been extended for an additional one hundred eighty days. However, no permit more than three years old may be extended by the extension of another permit on the same project.

    2.

    In order to extend a permit described in Subsection 1., above, one of the permits must be extended subject to aforementioned limitations and payment of required fees. Additionally, an inspection indicating that the applicant has made substantial progress must be requested and performed on the permit that has been extended within one hundred eighty days, from the date of permit issuance.

    (Ords. 28166, 28595.)

  • 24.02.350 - Plan check expiration.

    A.

    All plan check submittals for which a permit is not issued shall expire by limitation and become null and void if the application is suspended or abandoned one hundred eighty (180) days after the plan review has commenced.

    B.

    Plans which have approvals for permit issuance that have expired may thereafter be returned to the permittee or destroyed by building official.

    (Ords. 28166, 30326.)

  • 24.02.355 - Plan check renewals and extensions.

    A.

    All plan check submittals and approvals must be updated to meet this title when the permit is issued two or more code cycles after the application date.

    B.

    When a plan check submittal or approval has expired, then it must be resubmitted and appropriate fees paid for review for conformance with the current codes.

    C.

    Plan check time extensions for one-building projects must comply with the following:

    1.

    A plan check submittal or approval may be extended one time for an additional one hundred eighty days by applicant making a written request to building official and paying appropriate fee.

    2.

    Plan check submittal or approval for one-building projects shall not be extended more than once, except that, the building official may approve an extension of not more than three hundred sixty days when the applicant demonstrates that circumstances beyond the control of applicant have prevented action from being taken. In this case, the chief building official may require that additional fees be paid and plans be revised to partially or fully comply with the current codes.

    D.

    Plan check time extensions for ongoing multi-building projects must comply with all of the following:

    1.

    A plan check submittal or approval may be extended one time for an additional one hundred eighty days by applicant making written request to building official and paying appropriate fees.

    2.

    If a permit for at least one building has been issued, then the plan check approval is valid for one hundred eighty days from the latest permit issuance date, subject to the above limitations. The plan check approval may be extended for an additional three hundred sixty-day period by applicant making a written request to building official and paying appropriate fees, subject to the above limitations.

    3.

    Plan check submittal or approval for multi-building projects shall not be extended more than once, except that, the building official may approve an extension of not more than three hundred sixty days when the applicant demonstrates that circumstances beyond the control of applicant have prevented action from being taken. In this case, the building official may require that additional fees be paid.

    (Ords. 28166, 28595, 28838, 29334, 29806, 30326.)

  • 24.02.360 - Suspension or revocation.

    The building official may, in writing, suspend or revoke a permit issued under the provisions of this title and the technical codes when the permit is issued in error or on the basis of incorrect information supplied, or in violation of an ordinance or regulation or the provisions of this title.

    (Ord. 28166.)

  • Part 4 - FEES


  • 24.02.400 - Fees established by city council resolution.

    All fees required pursuant to this title shall be paid in the amount established set forth in the schedule of fees established by resolution of the city council.

    (Ord. 28166.)

  • 24.02.410 - Permit fees.

    The fee for each building permit shall be paid as set forth in the schedule of fees established by resolution of council.

    (Ord. 28166.)

  • 24.02.420 - Plan review fees.

    A.

    When a plan or other data is required to be submitted, a plan review fee shall be paid at the time of submitting plans and specifications for checking. The plan review fee is separate and in addition to the building permit fee.

    B.

    The plan review fee shall be as set forth in the schedule of fees established by council.

    C.

    Whenever a permit is requested for the construction of a single-family or duplex structure as part of a subdivision previously plan-checked and approved under Section 24.02.310.B, a fee as set forth in the schedule of fees established by council for each such structure shall be paid at the time of application for each such building permit.

    D.

    Upon request to review plans on file, a fee as set forth in the schedule of fees established by council shall be paid, if the plans for such building or structure must be obtained from the city records center.

    (Ord. 28166.)

  • 24.02.430 - Plan review time extension and renewal fees.

    A.

    An applicant shall pay appropriate fees when requesting a plan review or approval time extension.

    B.

    In order to renew action on an application after expiration, the applicant shall resubmit plans and pay full new plan review fees. However, where said plans are resubmitted without change and there has been no substantial intervening change in codes, law or circumstance, as determined by building official, applicant shall only pay a refiling fee in the amount stated in the schedule of fees.

    (Ord. 28166.)

  • 24.02.440 - Investigation fees for work without a permit.

    A.

    Whenever any work for which a permit is required by this title has been commenced without first obtaining the proper permits, a special investigation shall be made before any permit may be issued for such work.

    B.

    The investigation fee in an amount set forth in the schedule of fees, in addition to the permit fee, shall be collected whether or not a permit is then or subsequently issued.

    C.

    The payment of such investigation fee shall not exempt any person from compliance with all other provisions of this title nor from any penalty prescribed by law.

    (Ord. 28166.)

  • 24.02.450 - Fee refunds.

    A.

    The building official may authorize and initiate the refunding of the overpayment of any fee paid hereunder when such overpayment was made because of a clerical error, system error or arithmetic miscalculation and such error or miscalculation has been demonstrated to the satisfaction of the building official or designee.

    B.

    The building official may authorize the refunding of not more than eighty percent of the permit fee paid when no work has been done under a permit issued in accordance with this title.

    C.

    The building official may authorize the refunding of not more than eighty percent of the plan review fee paid when an application is withdrawn or canceled before any plan reviewing has been started.

    D.

    Other than refunds identified in Subsection A, the building official shall not authorize the refunding of any fee paid except upon written application filed by the original permittee not later than three hundred sixty-five days after the date of the fee payment.

    (Ords. 28166, 29749, 29806.)

  • 24.02.460 - Fee exceptions.

    A.

    Fees shall not be required for buildings erected for and owned by the United States of America, the State of California, or any of its political subdivisions, or by any school district or hospitals, where the city has no jurisdiction for issuance of permits.

    B.

    However, if an applicant requests a plan review or permit for any of the aforementioned projects, full fees are charged.

    (Ord. 28166.)

  • Part 5 - INSPECTIONS


  • 24.02.500 - General provisions.

    A.

    Construction or work for which a permit is required shall be subject to inspection by the building official and the construction or work shall remain accessible and exposed for inspection purposes until approved by the building official. In addition, certain types of construction shall have continuous inspection and structural observation as specified in Chapter 17 of Building Code.

    B.

    Approval as a result of an inspection shall not be construed to be an approval of a violation of the provisions of this title or of other ordinances of the jurisdiction. Inspections presuming to give authority to violate or cancel the provisions of this title or of other ordinances of the jurisdiction shall not be valid.

    C.

    It shall be the duty of the permit applicant to cause the work to remain accessible and exposed for inspection purposes. Neither the building official nor the city shall be liable for expense entailed in the removal or replacement of any material required to allow inspection.

    D.

    A survey of the lot may be required by the building official to verify that the structure is located in accordance with the approved plans.

    E.

    All inspections specified herein shall be at the discretion of the building official and nothing in the technical codes or in this chapter shall be construed as requiring the city to conduct such inspection nor shall any actual inspection made imply a duty to conduct any other inspection. Furthermore, neither the technical codes nor this section shall be construed to hold the city or any officer, employee or representative of the city, responsible for any damage to persons or property by reason of making inadequate or negligent inspection or by reason of any failure to make an inspection or reinspection.

    (Ords. 28166, 28838.)

  • 24.02.505 - Inspection record card.

    A.

    Work requiring a permit shall not be commenced until the permit holder or the agent of the permit holder shall have posted or otherwise made available an inspection record card such as to allow the building official to conveniently make the required entries thereon regarding inspection of the work.

    B.

    The inspection record card shall be maintained and made readily available by the permit holder until final approval has been granted by the building official.

    (Ord. 28166.)

  • 24.02.510 - Inspection requests.

    A.

    It shall be the duty of the person doing the work authorized by a permit to notify the building official that such work is ready for inspection.

    B.

    The building official may require that every request for inspection be filed at least one (1) working day before such inspection is desired. Such request may be in writing or by telephone at the option of the building official.

    C.

    It shall be the duty of the person requesting any inspections required either by this title or the technical codes to provide access to and means for inspection of the work.

    (Ord. 28166.)

  • 24.02.515 - Approval required.

    A.

    Work shall not be done beyond the point indicated in each successive inspection without first obtaining the approval of the building official.

    B.

    Reinforcing steel or structural framework of a part of a building or structure shall not be covered or concealed without first obtaining the approval of the building official.

    C.

    The building official, upon notification, shall make the requested inspections and shall either indicate that portion of the construction is satisfactory as completed or shall notify the permit holder or an agent of the permit holder wherein the same fails to comply with this title.

    D.

    Any portions of work which do not comply shall be corrected and such portion shall not be covered or concealed until authorized by the building official.

    E.

    There shall be a final inspection and approval of all buildings and structures when completed and ready for occupancy and use.

    (Ord. 28166.)

  • 24.02.520 - Required building inspections.

    The building official, upon notification, shall make the following inspections:

    A.

    Foundation inspection. To be made after excavations for footings are complete and required reinforcing steel is in place. For concrete foundations, required forms shall be in place prior to inspection. All materials for the foundation shall be on the job, except when concrete is ready-mixed in accordance with approved nationally recognized standards, the concrete need not be on the job. When the foundation is to be constructed of approved treated wood, additional inspections may be required by the building official.

    B.

    Concrete slab or under-floor inspection. To be made after in-slab or under-floor reinforcing steel and building service equipment, conduit, piping accessories and other ancillary equipment items are in place but before any concrete is placed or floor sheathing installed, including the subfloor.

    C.

    Protection of joints and penetrations in fire resistive assemblies, smoke barriers, and smoke partitions shall not be concealed from view until inspected and approved.

    D.

    Rough inspection of plumbing, mechanical, gas and electrical systems shall be made prior to covering or concealment, before fixtures or appliances are set or installed, and prior to framing inspection.

    E.

    Frame inspection. To be made after the roof deck or sheathing, all framing, fire blocking and bracing are in place and all pipes, chimneys and vents are complete and the rough electrical, plumbing, heating wires, pipes, and ducts are approved.

    F.

    Lath and/or gypsum panel product inspections shall be made after lathing and gypsum panel products, interior and exterior, are in place but before plaster is applied or before gypsum panel product joints and fasteners are taped and finished.

    G.

    Final inspection. To be made after finish grading and the building is completed and ready for occupancy or use.

    (Ords. 28166, 30837, 31256.)

  • 24.02.525 - Required building service equipment inspections.

    A.

    General. Building service equipment for which a permit is required by this Title shall be inspected by the building official. Building service equipment intended to be concealed by a permanent portion of the building shall not be concealed until inspected and approved. When the installation of building service equipment is complete, an additional and final inspection shall be made. Building service equipment regulated by the technical codes shall not be connected to the water, fuel or power supply or sewer system until authorized by the building official.

    B.

    Operation of building service equipment. The requirements of this section shall not be considered to prohibit the operation of building service equipment installed to replace existing building service equipment serving an occupied portion of the building in the event a request for inspection of such building service equipment has been filed with the building official not more than forty-eight (48) hours after the replacement work is completed, and before any portion of such building service equipment is concealed by permanent portions of the building.

    (Ord. 28166.)

  • 24.02.530 - Other inspections.

    In addition to the called inspections specified above, the building official may make or require other inspections of construction work to ascertain compliance with the provisions of this title or technical codes and other laws which are enforced by the department.

    (Ord. 28166.)

  • 24.02.535 - Reinspections.

    A.

    A reinspection fee may be assessed for each inspection or reinspection when such portion of work for which inspection is called is not complete or when corrections called for are not made.

    B.

    This section is not to be interpreted as requiring reinspection fees the first time a job is rejected for failure to comply with the requirements of the technical codes, but as controlling the practice of calling for inspections before the job is ready for such inspection or reinspection.

    C.

    Reinspection fees may be assessed when the inspection record card is not posted or otherwise available on the work site, the approved plans are not readily available to the inspector, for failure to provide access on the date for which inspection is requested, or for deviating from plans requiring the approval of the building official.

    D.

    To obtain a reinspection, the applicant shall file an application therefor in writing upon a form furnished for that purpose, and pay the reinspection fee in accordance with the schedule of fees.

    E.

    In instances where reinspection fees have been assessed, additional inspection of the work will not be performed until the required fees have been paid.

    (Ord. 28166.)

  • 24.02.540 - Special inspections.

    Special inspection shall be provided in accordance with Section 1704 of the Building Code. Additional special inspections may be required when deemed necessary by the building official.

    (Ord. 28166.)

  • 24.02.545 - Structural observation.

    Structural observation shall be provided in accordance with Section 1704 of the Building Code. Additional structural observation may be required when deemed necessary by the building official.

    (Ords. 28166, 28838, 29334.)

  • 24.02.550 - Connection to utilities.

    A.

    Energy connections. Persons shall not make connections from a source of energy, fuel or power to building service equipment which is regulated by the technical codes and for which a permit is required by this title, until approved by the building official.

    B.

    Temporary connections. The building official may authorize the temporary connection of the building service equipment to the source of energy, fuel or power for the purpose of testing building service equipment, or for use under a temporary certificate of occupancy.

    (Ord. 28166.)

  • Part 6 - CERTIFICATE OF OCCUPANCY


  • 24.02.610 - Use or occupancy.

    A.

    Buildings or structures shall not be used or occupied nor shall a change in the existing occupancy classification of a building or structure or portion thereof be made until the building official has issued a certificate of occupancy therefor as provided herein.

    B.

    Exception: The following occupancies shall not require a certificate of occupancy:

    1.

    Group R, Division 3,

    2.

    Group U Occupancies.

    C.

    Issuance of a certificate of occupancy shall not be construed as an approval of a violation of the provisions of this title or of other city ordinances.

    D.

    Certificates presuming to give authority to violate or cancel the provisions of this title or of other city ordinances shall not be valid.

    (Ord. 28166.)

  • 24.02.620 - Change in use.

    Changes in the character or use of a building shall not be made except as specified in the Building Code.

    (Ord. 28166.)

  • 24.02.630 - Issuance of certificate of occupancy.

    After the building official inspects the building or structure and finds no violations of the provisions of this title or other laws, the building official shall issue a certificate of occupancy which shall contain the following:

    A.

    The building permit number.

    B.

    The address of the building.

    C.

    The name and address of the owner.

    D.

    A description of that portion of the building for which the certificate is issued.

    E.

    A statement that the described portion of the building has been inspected for compliance with the requirements of this title for the group and division of occupancy and the use for which the proposed occupancy is classified.

    F.

    The name of the building official.

    G.

    The edition of the code under which the permit was issued.

    H.

    The use and occupancy, in accordance with the provision of CBC Chapter 3.

    I.

    The type of construction as defined in CBC Chapter 6.

    J.

    If an automatic sprinkler system is provided.

    (Ords. 28166, 29334, 30326.)

  • 24.02.640 - Temporary certificate of occupancy.

    A.

    If the building official finds that substantial hazard will not result from occupancy of a building or portion thereof before the same is completed, a temporary certificate of occupancy for the use of a portion or portions of a building or structure may be issued prior to the completion of the entire building or structure.

    B.

    Applicant shall pay required fees prior to issuance of temporary certificate of occupancy.

    (Ords. 28166, 30326.)

  • 24.02.650 - Posting.

    The certificate of occupancy shall be posted in a conspicuous place on the premises and shall not be removed except by the building official.

    (Ord. 28166.)

  • 24.02.670 - Revocation.

    The building official may, in writing, suspend or revoke a certificate of occupancy issued under the provisions of this title when the certificate is issued in error, or on the basis of incorrect information, or when it is determined that the building or structure or portion thereof is in violation of an ordinance, regulation or the provisions of this title.

    (Ord. 28166.)

  • Part 7 - APPEALS


  • 24.02.710 - Appeals jurisdiction.

    An applicant for or holder of a permit whose proposed solution for meeting the requirements of Title 24 of the California Code of Regulations is not approved or authorized by the building official may file an appeal with the appeals hearing board.

    (Ords. 28166, 29334, 30326.)

  • 24.02.720 - Notice of appeal.

    A.

    A request for appeal may be taken only by filing a written notice of appeal with the secretary of the board no later than the fifteenth (15th) day after the date the building official makes a written determination accepting, denying or modifying a proposed design solution regarding Building Code and/or disabled access requirements.

    B.

    Each notice of appeal shall include:

    1.

    A description of the work or improvements proposed to be made or done;

    2.

    A description of the proposed location of the work or improvements;

    3.

    The reasons, in detail, why

    a.

    The decision of the building official should not be sustained; and

    b.

    The relief prayed for should be granted.

    (Ord. 28166.)

  • 24.02.730 - Request for ratification.

    A.

    For purposes of this chapter, "request for ratification" means a written request by the building official that the board approve a proposed solution based upon a finding of "unreasonable hardship" as that term is used in Title 24 of the California Code of Regulations.

    B.

    The board must have approved a request for ratification, prior to the approval of plans or issuance of a permit which requires a finding of unreasonable hardship.

    C.

    The building official shall place any request for ratification of a determination of unreasonable hardship on the board's agenda in accordance with the provisions of Section 24.02.750.

    (Ord. 28166.)

  • 24.02.740 - Filing fee.

    No notice of appeal or request for ratification shall be accepted by the secretary of the board unless the appellant shall have first paid a filing fee as set forth in the schedule of fees established by resolution of the city council.

    (Ord. 28166.)

  • 24.02.750 - Hearings.

    A.

    The building official shall place all matters for hearing on the board's agenda no later than ten (10) days prior to the meeting date on which the matter is set to be heard.

    B.

    All requests for ratification and for appeal shall be in writing and shall contain sufficient information to allow the board to make a determination on the request.

    C.

    An appeal shall be heard the next regular meeting of the board which is held not more than seventy-five (75) days after the notice of appeal is filed.

    D.

    At such meeting, or at such later time as the matter may be continued by the board, the appellant and the building official or any of his or her authorized representatives, shall be given a reasonable opportunity to be heard on the matter and to present relevant evidence.

    (Ord. 28166.)

  • 24.02.760 - Decisions.

    A.

    The board shall not render any decision allowing a proposed design solution unless, after the hearing, it finds on the basis of substantial evidence that:

    1.

    The proposed design is satisfactory and complies with the intent of this chapter; and

    2.

    The proposed design meets the requirements of Title 24.

    B.

    Board decisions overruling the building official's decisions shall require four (4) votes.

    C.

    Board decisions ratifying the building official's requests for ratification shall require three (3) votes.

    D.

    Should the board render a decision contrary to that of the building official, then the decision of board shall be deemed the decision of the building official.

    (Ord. 28166.)

  • 24.02.770 - Findings and order.

    A.

    Within thirty (30) days following the conclusion of the hearing, the board shall make written findings of fact, based upon the evidence received at the hearing to support its decision and shall issue an order affirming, modifying, or overruling the determination or order of the building official under appeal.

    B.

    The decision of the board shall be final and conclusive.

    C.

    The findings and order of the board shall include the following notice:

    Notice to Parties

    The time within which judicial review must be sought to review this decision is governed by the provisions of California Code of Civil Procedure Section 1094.6.

    D.

    The findings and order of the board shall either be personally delivered or mailed to the appellant within thirty (30) days following the conclusion of the hearing.

    (Ord. 28166.)

  • Part 8 - RESPONSIBLE CONSTRUCTION


  • 24.02.810 - Definitions.

    The following words and phrases, whenever used in this Part, shall be construed as defined in this section:

    A.

    "Certificate of occupancy" means the building official's certification under Chapter 24.02.630 of this code that the project complies with all applicable requirements for occupancy. The building official's signature on the final inspection card may serve as the certificate of occupancy.

    B.

    "Contractor" means the prime contractor for the project.

    C.

    "Subcontractor" means any business or person that carries out work of the prime contractor or another contractor for the project, provides labor to the project, and whose portion of the work exceeds one hundred thousand dollars or one percent of the value of the construction cost of the project, whichever is greater.

    D.

    "Hearing officer" means the City Manager or designee.

    E.

    "Labor Code Section 226(a)" is a provision of the California Labor Code that requires the employer to provide each employee, either bimonthly or at the time of payment of wages, an itemized wage statement that contains certain specified information concerning the employee's wages and deductions.

    F.

    "Labor Code Section 2810.5" is a provision of the California Labor Code that requires the employer, at the time of hiring, to provide each employee a written notice containing certain specified information about the employer, the employee's rate of pay, worker's compensation insurance, and sick leave.

    G.

    "Mail" means to deposit in United States mail, postage prepaid, unless the parties have agreed in writing to receive notifications by email in lieu of United States mail.

    H.

    "New construction" means construction of new buildings or structures including additions to existing buildings and structures.

    I.

    "Outstanding judgments list" means a list of contractors who have any unpaid wage theft judgment(s) against them generated by the owner from the California Department of Industrial Relations Judgment Search database, or any succeeding database, as of the date of the building permit application.

    J.

    "Owner" means the person or persons, firm, corporation, partnership or other legal entity exercising ownership of the project.

    K.

    "Remodeling" means internal or external reconstruction, renovation, or improvements to an existing building or structure that does not constitute complete replacement of the existing building or structure.

    L.

    "Project" means a construction project that requires a building permit from the City of San José.

    M.

    "Project construction employees" means employees of the contractor or subcontractor.

    N.

    "Representative" means a person authorized to legally bind the owner and/or contractor (for example, a corporate officer, general partner, or managing member of a limited liability company).

    O.

    "Unpaid wage theft judgment" means a judgment, decision or order, for which all appeals have been exhausted or the time to appeal has expired, that was issued by a court of law or an investigatory government agency authorized to enforce applicable California state and local wage and hour laws, including the California Labor Code and the City of San José Minimum Wage Ordinance, which has not been fully paid or satisfied, and which can be verified by reference to the California Department of Industrial Relations Judgment Search database, or any succeeding database. As used in this subsection, "investigatory government agency" includes the California Division of Labor Standards Enforcement, the city of San José, or any other governmental entity or division authorized to investigate and enforce state and local wage and hour laws.

    (Ord. 31100.)

  • 24.02.820 - Exemptions.

    A project that consists of less than ten thousand square feet of new construction or remodeling is exempt from the requirements of this Part.

    (Ord. 31100.)

  • 24.02.830 - Acknowledgement of responsibility.

    As a condition of approval for any building permit required for a project, an applicant shall sign an acknowledgement that:

    A.

    The owner, contractor, and subcontractors on the project will comply with all applicable provisions of this chapter and the California Labor Code, including Labor Code Sections 2810.5 and 226a.

    B.

    The owner and contractor are responsible for verifying that the contractor and subcontractors hired on the project do not, as of the date of the building permit application, have any unpaid wage theft judgment(s) entered against them.

    C.

    After approval of the building permit, the owner and contractor are responsible for verifying, prior to hiring any new contractor or subcontractor, that the contractor or subcontractor does not appear on the outstanding judgments list.

    D.

    The owner is responsible for ensuring that, if a contractor or subcontractor has an unpaid wage theft judgment entered against them that appears on the outstanding judgments list, the contractor or subcontractor has provided proof demonstrating that the unpaid wage theft judgment has been satisfied prior to being hired onto the project.

    E.

    The owner is responsible for ensuring that any unpaid wage theft judgment(s) entered against the owner, contractor, or subcontractor for labor provided to the project are satisfied prior to application for a certificate of occupancy on the project.

    F.

    A violation under Section 24.02.860 will result in withholding of the certificate of occupancy.

    (Ord. 31100.)

  • 24.02.840 - Posting.

    Each day that work is performed on the project, the contractor shall post, in a conspicuous place at each job site where work takes place, the notice published each year by the city informing employees of their rights under this chapter. The notice shall be written in the top three languages spoken in the city based on the latest available census information for the city.

    (Ord. 31100.)

  • 24.02.850 - Pay transparency certification.

    With the request for issuance of a certificate of occupancy for a project, for each contractor and subcontractor whose portion of the work exceeds one hundred thousand dollars or one percent of the value of the construction cost of the project, whichever is greater, the owner shall provide to the city a pay transparency certification ("certification"), signed by a representative of the owner, under penalty of perjury under the laws of the state of California. The certification required under this section shall be in a form approved by the city and contain a statement that:

    A.

    The owner did not have any unpaid wage theft judgment(s) entered against them dated prior to application for the building permit;

    B.

    No contractor or subcontractors have any unpaid wage theft judgment(s) entered against them dated prior to application for the building permit;

    C.

    No contractor or subcontractors have any unpaid wage theft judgment(s) entered against them for labor provided to the project; and

    D.

    A statement that:

    (1)

    Contractor and any subcontractors who provided labor to the project were obligated to provide written notice to project construction employees of the employers' pay practices as required by Labor Code Section 2810.5 and wage statements under Labor Code Section 226(a); or

    (2)

    Project construction employees of the contractor and subcontractors are covered by a valid collective bargaining agreement that expressly provides for the wages, hours of work, and working conditions of the employee, and the agreement provides premium wage rates for all overtime hours worked and a regular hourly rate of pay for those employees of not less than thirty percent more than the state minimum wage (see Labor Code Section 2810.5(c)).

    (Ord. 31100.)

  • 24.02.860 - Violations.

    The building official shall not issue a certificate of occupancy under either of the following circumstances:

    A.

    The owner has failed to submit the pay transparency certification required by Section 24.02.850.

    B.

    The Director of Public Works has sustained a complaint of an unpaid wage theft judgment pursuant to Section 24.02.870, and the owner or contractor has neither cured the unpaid wage theft judgment nor reversed the Director of Public Works' determination by appeal pursuant to Section 24.02.880.

    (Ord. 31100.)

  • 24.02.870 - Unpaid wage theft judgment - Complaint.

    A.

    Any person who is aware of an unpaid wage theft judgment against the contractor or a subcontractor on a project whose portion of the work exceeds one hundred thousand dollars or one percent of the value of the construction cost of the project, whichever is greater, may submit a complaint to the building official. The complaint must include: (1) a copy of the Labor Commissioner's order, decision or award; (2) a copy of the judgment entered by a court of law that the specified contractor or subcontractor is the subject of an unpaid wage theft judgment; and (3) a declaration signed under penalty of perjury from the person that is owed the unpaid wages under the final wage theft judgment against the specified contractor or subcontractor that the judgment has not been satisfied.

    B.

    The complaint must be received by the building official before the building official has issued a certificate of occupancy. After receiving a complaint, the building official shall withhold the certificate of occupancy until the Director of Public Works has verified the complaint and has determined whether the complaint is sustained, not sustained or incomplete. In the event the Director of Public Works finds that the complaint is sustained, the building official shall continue to withhold the certificate of occupancy unless the owner, contractor, or subcontractor provides proof demonstrating that the unpaid wage theft judgment is satisfied, or the Director of Public Works' determination is reversed by appeal pursuant to Section 24.02.880.

    C.

    The Director of Public Works shall, within 10 working days of receiving the complaint, determine whether the unpaid wage theft judgment appeared on the California Department of Industrial Relations Judgment Search database as of the date of the building permit application, or whether the unpaid wage theft judgment was for labor provided to the project, and verify that the complaint includes all the documentation required by Section 24.02.870(A).

    (1)

    If the complaint is verified, the Director of Public Works shall mail written notice of violation to the owner and contractor at the address(es) on file with the city for the project. The notice of violation shall inform the owner and contractor of their opportunity to provide a written response to the complaint. The certificate of occupancy shall be withheld until the owner, contractor, or subcontractor provides proof demonstrating that the wage theft judgment has been satisfied.

    (2)

    If the complaint does not include all required documentation, the Director of Public Works shall mail written notice to the complaining party that the complaint is incomplete or not sustained.

    D.

    The owner or contractor may provide a written response to the notice of violation within 30 working days of the mailing of the notice. Failure to respond may be deemed an admission to the truth of the facts alleged in the complaint.

    E.

    Within 10 working days of receiving the owner or contractor's response, or if no response is received, after 30 working days of mailing written notice to the owner and contractor, the Director of Public Works shall make a finding that the complaint is either sustained or not sustained. The Director of Public Works' decision shall be mailed to owner, contractor, complaining party, and the person that is owed the unpaid wages under the final wage theft judgment. If the complaint is sustained, the certificate of occupancy shall be withheld until the owner, contractor, or subcontractor provides proof demonstrating that the unpaid wage theft judgment is satisfied, or until an appeal pursuant to Section 24.02.880 reverses the Director of Public Works' finding.

    (Ord. 31100.)

  • 24.02.880 - Unpaid wage theft judgment - Appeal.

    A.

    Notwithstanding Part 7 of this Chapter, if an owner or contractor is aggrieved by a decision of the Director of Public Works pursuant to Section 24.02.870, the aggrieved owner or contractor may appeal the decision by submitting a written appeal with the hearing officer within 10 working days of the mailing of the Director of Public Works' decision. The appeal shall contain the facts and basis for the appeal. The appeal shall be accompanied by payment of the appeal fee as set forth in a resolution adopted by the city council.

    B.

    The hearing shall be heard by the hearing officer within 60 working days of receipt of the appeal, or at a date and time agreed to by the parties.

    C.

    All parties involved shall have the right to offer testimonial, documentary, and tangible evidence bearing on the issues, to be represented by counsel, and to confront and cross-examine witnesses. Testimony may be taken on oath or affirmation. The hearing shall not be conducted according to formal rules of evidence. Any relevant evidence may be admitted if it is the sort of evidence upon which reasonable persons are accustomed to rely in the conduct of serious affairs.

    D.

    The hearing shall be de novo. The complaining party shall be the respondent at the appeal hearing. The complaining party must prove by a preponderance of the evidence that the contractor or a subcontractor on the project is the subject of an unpaid wage theft judgment.

    E.

    The hearing officer shall issue a written decision within 10 working days of the hearing. The decision shall be final and shall be subject to judicial review according to the provisions and time limits set forth in Code of Civil Procedure Section 1094.6.

    (Ord. 31100.)

  • 24.02.890 - Cure of violation.

    The owner, contractor, or subcontractor may cure a violation of this Part at any time, including a violation related to an unpaid wage theft judgment, by providing proof demonstrating that the judgment has been satisfied, or that it has been secured by a labor payment bond, lien release bond, or similar security instrument in a form and amount sufficient to ensure that any wage claims and penalties can be fully paid. A violation for failure to submit a pay transparency certification may be cured immediately upon submittal of the pay transparency certification to the city.

    (Ord. 31100.)

  • 24.02.900 - No private right of action.

    Nothing in this Part shall be interpreted to authorize a right of action against the city.

    (Ord. 31100.)

  • 24.02.910 - Effective date.

    This Part shall become effective on December 1, 2024.

    (Ord. 31100.)

  • Chapter 24.03 - BUILDING CODE

  • Part 1 - ADOPTION OF CBC PROVISIONS


  • 24.03.100 - Adoption of technical provisions of California Building Code.

    A.

    Except as otherwise provided for in this chapter, the California Building Code, 2025 edition (CBC) is hereby incorporated in this chapter by reference and made a part hereof the same as if fully set forth herein.

    B.

    One copy of the CBC has been filed for use and examination of the public in the office of the city clerk of the City of San José.

    (Ords. 28166, 28838, 29334, 29806, 30326, 30837, 31256.)

  • 24.03.110 - Portions of California Building Code which are not approved, adopted or incorporated by reference.

    A.

    The following portions of the California Building Code, 2025 edition are not approved or adopted or incorporated in this chapter by reference, and shall not be deemed to be a part of this chapter nor a part of the building code of the City of San José:

    1.

    Section 1.8.4

    2.

    Section 1.8.5

    3.

    Section 1.8.7

    4.

    Section 1.8.8

    5.

    Section 1.8.9

    6.

    Section 2505

    (Ords. 28166, 28838, 29334, 29806, 30326, 30837, 31256.)

  • 24.03.115 - Portions of California Building Code Appendices are approved, adopted, or incorporated by reference.

    A.

    The following portions of the California Building Code, 2025 edition, of the appendices are approved, adopted, or incorporated by reference.

    1.

    CBC Appendix C, Agricultural Buildings.

    2.

    CBC Appendix J, Grading.

    3.

    CBC Appendix Q, Emergency Housing.

    (Ords. 29806, 30326, 30837, 31256.)

  • 24.03.120 - Cross-references to California Building Code.

    The provisions of this chapter contain cross-references to the provisions of the CBC, 2025 edition, in order to facilitate reference and comparison to those provisions.

    (Ords. 28166, 28838, 29334, 29806, 30326, 30837, 31256.)

  • 24.03.130 - Local amendments.

    The provisions of this chapter shall constitute local amendments to the cross-referenced provisions of the CBC and shall be deemed to replace the cross-referenced section of the CBC with the respective provisions set forth in this chapter.

    (Ords. 28166, 28838, 31256.)

  • Part 2 - SPECIAL DETAILED REQUIREMENTS BASED ON USE AND OCCUPANCY (CBC CHAPTER 4)


  • 24.03.210 - Findings.

    The amendments set forth in this part are reasonably necessary because of the following local geological, topographical and climatic conditions:

    A.

    San José is within a very active seismic area. Severe seismic action could disrupt communications, damage gas and water mains, cause extensive electrical hazards, and place extreme demands on the limited and widely dispersed resources of the fire department, resulting in failure of the Fire Department to meet and provide the fire protection and life safety needs of the community.

    B.

    The local geographic, topographic, and climatic conditions pose an increased hazard in the acceleration, spread, magnitude, and severity of potential fires in the City of San José, and may cause disruptions in the operation of fire protection systems, equipment, and a delayed fire response time, allowing further growth of the fire.

    C.

    If not amended, Sections 402.5, 403.3, 404.3, 410.6 of the CBC would allow omission of fire sprinkler coverage in certain areas of covered malls, high-rise buildings, buildings with atriums, stages, and platforms.

    D.

    The requirement for total fire sprinkler coverage set forth in the amendment is a more restrictive standard which will better prevent fire damage which can result from local conditions.

    (Ords. 28166, 28838, 29334, 30326, 31256.)

  • 24.03.220 - Covered mall buildings (CBC 402).

    Subsection 402.5 of CBC Section 402 is deleted and replaced with the following:

    402.5 Automatic sprinkler system. Covered and open mall buildings and buildings connected shall be equipped throughout with an automatic sprinkler system in accordance with Section 903.3.1.1, which shall comply with all of the following:

    1.

    The automatic sprinkler system shall be complete and operative throughout occupied space in the covered mall building prior to occupancy of any of the tenant spaces. Unoccupied tenant spaces shall be similarly protected unless provided with approved alternate protection.

    2.

    Sprinkler protection for the mall of a covered mall building shall be independent from that provided for tenant spaces or anchors buildings.

    3.

    Sprinkler protection for the tenant spaces of an open mall building shall be independent from that provided for the anchor buildings.

    4.

    Sprinkler protection shall be provided beneath exterior circulation balconies located adjacent to an open mall.

    5.

    Where tenant spaces are supplied by the same system, they shall be independently controlled.

    Exception: Deleted

    402.5.1 Standpipe system. The covered mall building shall be equipped throughout with a standpipe system as required by Section 905.3.3.

    (Ords. 28166, 28838, 29334, 30326, 31256.)

  • 24.03.230 - High-rise buildings (CBC 403).

    Subsection 403.3 of CBC Section 403 is amended and replaced with the following:

    403.3 Automatic sprinkler system. Buildings and structures shall be equipped throughout with an automatic sprinkler system in accordance with Section 903.3.1.1 and a secondary water supply where required by Section 403.3.3. A sprinkler water-flow alarm-initiating device and a control valve with a supervisory signal-initiating device shall be provided at the lateral connection to the riser for each floor.

    Exception: Deleted

    (Ords. 28166, 28838, 29334, 29806, 31256.)

  • 24.03.240 - Atriums (CBC 404).

    Subsection 404.3 of CBC Section 404 is deleted and replaced with the following:

    404.3 Automatic sprinkler protection. An approved automatic sprinkler system shall be installed throughout the entire building.

    Exceptions: Deleted

    (Ords. 28166, 28838, 31256.)

  • 24.03.250 - Stages and platforms (CBC 410).

    Subsection 410.6 of CBC Section 410 is deleted and replaced with the following:

    410.6 Automatic sprinkler system. Stages shall be equipped with an automatic sprinkler system in accordance with Section 903.3.1.1. Sprinklers shall be installed under the roof and gridiron and under all catwalks and galleries over the stage. Sprinklers shall be installed in dressing rooms, performer lounges, shops, and storerooms accessory to such stages.

    Exceptions: Sprinklers are not required under catwalks and galleries where they are permitted to be omitted in accordance with Section 903.3.1.1.

    (Ords. 28166, 28838, 29334, 29806, 30326, 31256.)

  • Part 3 - FIRE RESISTANCE-RATED CONSTRUCTION (CBC CHAPTER 7)


  • 24.03.310 - Findings.

    The amendment set forth in this part is necessary because California Mechanical Code does not address dampers in hazardous exhaust ducts. Hazardous exhaust systems are designed to capture and control hazardous emission generated from product handling or process, and convey those emissions to the outdoors.

    (Ords. 28166, 28838.)

  • 24.03.311 - Section 717.2.2.

    CBC Section 717.2.2 is deleted and replaced with the following:

    717.2.2 Hazardous exhaust ducts. Penetrations of structural elements by a hazardous exhaust system shall conform to Sections 717.2.2.1 through 717.2.2.4.

    717.2.2.1 Fire dampers and smoke dampers. Fire dampers and smoke dampers are prohibited in hazardous exhaust ducts.

    717.2.2.2 Floors. Hazardous exhaust systems that penetrate a floor/ceiling assembly shall be enclosed in a fire-resistance-rated shaft constructed in accordance with Section 713.

    717.2.2.3 Wall assemblies. Hazardous exhaust duct systems that penetrate fire-resistance-rated construction shall be enclosed in a fire-resistance-rated shaft from the point of penetration to the outlet terminal, except where the interior of the duct is equipped with an approved automatic fire suppression system. Ducts shall be enclosed in accordance with Section 713 requirements for shaft construction and such enclosure shall have a minimum fire-resistance-rating of not less than the highest fire-resistance-rated wall assembly penetrated.

    717.2.2.4 Fire walls. Ducts shall not penetrate a fire wall.

    (Ords. 28166, 28838, 29334, 30326.)

  • Part 4 - AUTOMATIC FIRE SPRINKLER SYSTEMS (CBC CHAPTER 9)


  • 24.03.410 - Findings.

    The amendments set forth in Parts 1 and 4 of this chapter are reasonably necessary because of the following local geological, topographical and climatic conditions:

    A.

    San José is within a very active seismic area. Severe seismic action could disrupt communications, damage gas and water mains, cause extensive electrical hazards, and place extreme demands on the limited and widely dispersed resources of the fire department, resulting in failure of the Fire Department to meet and provide the fire protection and life safety needs of the community.

    B.

    The local geographic, topographic, and climatic conditions pose an increased hazard in the acceleration, spread, magnitude, and severity of potential fires in the City of San José, and may cause disruptions in the operation of fire protection systems, equipment, and a delayed fire response time, allowing further growth of the fire.

    C.

    This section adopts the latest standards currently listed by the State of California Fire Marshal's Office for automatic fire protection systems and includes references to the amendments to the standards made in the California Fire Code.

    D.

    The type of automatic fire sprinkler systems set forth in the amendment is a more restrictive standard, which will better prevent fire damage that can result from local conditions.

    (Ords. 28166, 28838, 31256.)

  • 24.03.415 - Cross-references to California Fire Code.

    The provisions of this part contain cross-references to the provisions of the California Fire Code or CFC, 2025 edition, in order to facilitate reference and comparison to those provisions.

    (Ords. 28166, 28838, 29334, 29806, 30326, 30837, 31256.)

  • 24.03.425 - Automatic sprinkler systems (CBC 903).

    A.

    CBC Section 903 is deleted and replaced with the 2025 fire code amendments as amended by the San José Municipal Code Section 17.12.640.

    (Ords. 28166, 28838, 29334, 29806, 30326, 31256.)

  • Part 5 - RESERVED[1]

    Footnotes:
    --- (1) ---

    Editor's note— Part 5 of Chapter 24.03, being Sections 24.03.510 and 24.03.520, pertaining to Single Room Occupancy Units (CBC section 1208.4), was repealed by Ordinance 29334, adopted November 5, 2013.


  • Part 6 - STRUCTURAL DESIGN (CHAPTER 16)


  • 24.03.610 - Findings.

    The amendments set forth in this part are reasonably necessary because of the following local geological, topographical and climatic conditions:

    A.

    Local geological conditions - The San Francisco/Bay Area region is densely populated and/or located in an area of high seismic activities. San José is bound by two major faults such as Hayward and San Andreas faults capable of producing major earthquakes.

    B.

    Considering that certain important and critical buildings and structures must be operational in the event of an emergency, the need to incorporate this modification into the code will help to assure that new buildings and additions to existing buildings are designed and constructed in accordance with the scope and objectives of the California Building Code.

    C.

    The seismic separation is necessary to permit adjacent buildings, or parts thereof, to respond to earthquake ground motion independently and preclude possible structural damage due to pounding between buildings and other structures. The need to incorporate this modification into the code will help to assure that new buildings and additions to existing buildings are designed and constructed in accordance with the scope and objectives of the California Building Code.

    (Ords. 28166, 28838, 29806.)

  • 24.03.620 - Reserved.

    Editor's note— Section 24.03.620, pertaining to Modification to ASCE 7-05, Section 12.8.1.1, was repealed by Ordinance 29334, adopted November 5, 2013.

  • 24.03.630 - Reserved.

    Editor's note— Section 24.03.630, pertaining to Modification to ASCE 7-05, Table 12.8-2, was repealed by Ordinance 29334, adopted November 5, 2013.

  • 24.03.640 - Reserved.

    Editor's note— Section 24.03.630, pertaining to Modification to ASCE 7-05, Table 12.8.7, was repealed by Ordinance 29334, adopted November 5, 2013.

  • 24.03.650 - Reserved.

    Editor's note— Ord. 31256, § 29, adopted Nov. 18, 2025, repealed § 24.03.650, which pertained to modification to ASCE 7-16, Section 12.12.3 and derived from Ords. 28166, 28838, 29334, 30326.

  • 24.03.660 - Reserved.

    Editor's note— Section 23.03.660, pertaining to Modification to ACI 318 Section 14.8.3 and 14.8.4, was repealed by Ordinance 29334, adopted November 5, 2013.

  • Part 7 - STRUCTURAL TEST AND SPECIAL INSPECTIONS (CHAPTER 17)


  • 24.03.710 - Findings.

    Local geological conditions - The San Francisco/Bay Area region is densely populated and located in an area of high seismic activities. San José is bound by two major faults, the Hayward and San Andreas faults, that are capable of producing major earthquakes. Results from studies after the Northridge Earthquake indicated that a lot of the damages were attributed to lack of quality control during construction resulting in low construction quality. The proposed modification to improve quality control during construction need to be incorporated into the code to assure that new buildings and additions to existing buildings are designed and constructed in accordance with the scope and objectives of the California Building Code.

    (Ords. 28166, 28838.)

  • 24.03.720 - Modification to CBC Section 1705.3.

    Section 1705.3 of CBC is amended to read as follows:

    1705.3 Concrete Construction. The special inspections and tests of concrete construction shall be performed in accordance with this section and Table 1705.3.

    Exceptions: Special inspections and tests shall not be required for:

    1.

    Isolated spread concrete footings of buildings three stories or less above grade plane that are fully supported on earth or rock, where the structural design of the footing is based on a specified compressive strength, f'c, no greater than two thousand five hundred pounds per square inch (psi) (17.2 MPa).

    2.

    Continuous concrete footings supporting walls of buildings three stories or less above grade plane that are fully supported on earth or rock where:

    2.1.

    The footings support walls of light-frame construction;

    2.2.

    The footings are designed in accordance with Table 1809.7; or

    2.3.

    The structural design of the footing is based on a specified compressive strength, f'c, no greater than two thousand five hundred pounds per square inch (psi) (17.2 Mpa), regardless of the compressive strength specified in the approved construction documents or used in the footing construction.

    3.

    Nonstructural concrete slabs supported directly on the ground, including prestressed slabs on grade, where the effective prestress in the concrete is less than one hundred fifty psi (1.03 Mpa).

    4.

    Concrete foundation walls constructed in accordance with table 1807.1.6.2.

    5.

    Concrete patios, driveways and sidewalks, on grade.

    (Ords. 28166, 28838, 29334, 29806, 30326.)

  • Part 8 - GYPSUM BOARD, GYPSUM LATH, AND CEMENT PLASTER (CBC CHAPTERS 23 & 25)


  • 24.03.810 - Findings.

    The amendment set forth in Parts 1 and 8 of this chapter is reasonably necessary because of the following local geological and topographical conditions:

    A.

    San José is within a very active seismic area.

    B.

    Gypsum wallboard and exterior Portland cement plaster have performed poorly during recent California seismic events.

    C.

    The shear values for gypsum wallboard and Portland cement stucco contained in the code are based on monodirectional testing.

    D.

    The limitation on the use of these systems as set forth in the amendment until cyclic loading testing are performed and evaluated is a more restrictive standard which will better prevent damage which can result from local conditions.

    (Ords. 28166, 28838.)

  • 24.03.820 - General design requirements (CBC Section 2302.1).

    CBC Section 2302.1, method 4 is amended to read as follows:

    2302.1 General. The design of structural elements or systems, constructed partially or wholly of wood or wood-based products, shall be in accordance with one of the following methods:

    1.

    Allowable stress design in accordance with Sections 2304, 2305 and 2306.

    2.

    Load and resistance factor design in accordance with Sections 2304, 2305 and 2307.

    3.

    Conventional light-frame construction in accordance with Sections 2304 and 2308.

    4.

    Reserved.

    5.

    The design and construction of log structures in accordance with the provisions of ICC 400.

    (30326.)

  • 24.03.830 - Reserved.

    Editor's note— Ord. 30326, § 37, adopted Nov. 5, 2019, repealed § 24.03.830, which pertained to General CBC Section 2308.1 and derived from Ord. 28166 and 28838.

  • 24.03.835 - Braced wall panel method (CBC Section 2308.10.3).

    CBC Section 2308.10.3 is amended to read as follows:

    2308.10.3 Braced Wall Panel Method. Construction of braced wall panels shall be by one or a combination of the methods in Table 2308.10.3(1). Braced wall length shall be in accordance with Section 2308.10.4 or 2308.10.5.

    TABLE 2308.10.1(1) - BRACING METHODS

    (Ord. 31256.)

    Editor's note— Ord. 31256, § 30, adopted Nov. 18, 2025, amended § 24.03.835 in its entirety, in effect repealing and reenacting said § 24.03.835 to read as set out herein. The former § 24.03.835 pertained to Braced wall panel method (CBC Section 2308.6.3) and derived from Ords. 28166, 28838, 29334, 29806.

  • 24.03.840 - Reserved.

    Editor's note— Section 24.03.840, pertaining to Table 2305.3.4, was repealed by Ordinance 29334, adopted November 5, 2013.

  • 24.03.842 - Reserved.

    Editor's note— Ord. 30326, § 38, adopted Nov. 5, 2019, repealed § 24.03.842, which pertained to CBC Section 2306.3 and derived from Ord. 29334.

  • 24.03.845 - Reserved.

    Editor's note— Section 24.03.845, pertaining to Section 2305.3.9, was repealed by Ordinance 29334, adopted November 5, 2013.

  • 24.03.850 - Section 2308.10.4.

    CBC Section 2308.10.4 is amended to read as follows:

    2308.10.4 Braced Wall Panel Construction. For Methods DWB, WSP, SFB, PBS, PCP and HPS, each panel must be not less than 48 inches (1219 mm) in length, covering three stud spaces where studs are spaced at 16 inches (406 mm) on center and covering two stud spaces where studs are spaced at 24 inches (610 mm) on center. Braced wall panels less than 48 inches (1219 mm) in length shall not contribute toward the amount of required bracing.

    Vertical joints of panel sheathing shall occur over studs and adjacent panel joints shall be nailed to common framing members. Horizontal joints shall occur over blocking or other framing equal in size to the studding except where waived by the installation requirements for the specific sheathing materials. Sole plates shall be nailed to the floor framing in accordance with Section 2308.10.7 and top plates shall be connected to the framing above in accordance with Section 2308.10.7.2. Where joists are perpendicular to braced wall lines above, blocking shall be provided under and in line with the braced wall panels.

    (Ord. 31256.)

    Editor's note— Ord. 31256, § 31, adopted Nov. 18, 2025, amended § 24.03.850 in its entirety, in effect repealing and reenacting said § 24.03.850 to read as set out herein. The former § 24.03.850 pertained to Section 2308.6.4 and derived from Ords. 28166, 28838, 29806.

  • 24.03.858 - Section 2308.10.5.

    CBC Section 2308.10.5 is amended to read as follows:

    2308.10.5 Alternative bracing. An alternate braced wall (ABW) or a portal frame with hold-downs (PFH) described in this section is permitted to substitute for a 48 inch (1219 mm) braced wall panel of Methods DWB, WSP, SFB, PBS, PCP or HPS.

    CBC Sections 2308.10.5.1 and 2308.10.5.2 are adopted without amendments.

    (Ord. 31256.)

    Editor's note— Ord. 31256, § 32, adopted Nov. 18, 2025, amended § 24.03.858 in its entirety, in effect repealing and reenacting said § 24.03.858 to read as set out herein. The former § 24.03.858 pertained to Section 2308.6.5 and derived from Ords. 28166, 28838, 29806.

  • 24.03.860 - CBC Table 2308.10.1

    CBC Table 2308.10.1 to be deleted and replaced with the following:

    (Ord. 31256.)

    Editor's note— Ord. 31256, § 33, adopted Nov. 18, 2025, amended § 24.03.860 in its entirety, in effect repealing and reenacting said § 24.03.860 to read as set out herein. The former § 24.03.860 pertained to CBC Table 2308.6.1 and derived from Ords. 28166, 28838, 29334, 29806.

  • 24.03.870 - Section 2308.10.9.

    CBC Section 2308.10.9 is amended to read as follows:

    2308.10.9 Attachment of sheathing. Fastening of braced wall panel sheathing shall not be less than that prescribed in Table 2308.10.1 or 2304.10.2. Wall sheathing shall not be attached to framing members by adhesives.

    All braced wall panels shall extend to the roof sheathing and shall be attached to parallel roof rafters or blocking above with framing clips (eighteen-gauge minimum) spaced at maximum twenty-four inches (6,096 mm) on center with four 8d nails per leg (total eight 8d nails per clip). Braced wall panels shall be laterally braced at each top corner and at maximum twenty-four-inch (6,096 mm) intervals along the top plate of discontinuous vertical framing.

    (Ord. 31256.)

    Editor's note— Ord. 31256, § 34, adopted Nov. 18, 2025, amended § 24.03.870 in its entirety, in effect repealing and reenacting said § 24.03.870 to read as set out herein. The former § 24.03.870 pertained to Section 2308.6.9 and derived from Ords. 28166, 28838, 29806.

  • Part 9 - RESERVED[2]

    Footnotes:
    --- (2) ---

    Editor's note— Ord. 29806, § 39, adopted Nov. 1, 2016, repealed Part 9, §§ 24.03.910 and 24.03.930, which pertained to existing structures (CBC Chapter 34), and derived from Ords. 28166, 28838 and 29334.


  • Part 10 - RESERVED[3]

    Footnotes:
    --- (3) ---

    Editor's note— Ord. 29806, § 40, adopted Nov. 1, 2016, repealed Part 10, § 24.03.1010, which pertained to reference standards (CBC Chapter 35), and derived from Ords. 28838 and 29334.


  • Chapter 24.04 - PLUMBING CODE

  • Part 1 - ADOPTION OF CPC (PROVISIONS)


  • 24.04.100 - Adoption of technical provisions of California Plumbing Code.

    A.

    Except as otherwise provided for in this chapter, the California Plumbing Code, 2025 edition together with those omissions, amendments, exceptions and additions thereto as amended in Title 24 of the California Code of Regulations are approved and adopted, and are hereby incorporated in this chapter by reference and made a part hereof the same as if fully set forth herein.

    B.

    One copy of the CPC has been filed for use and examination of the public in the office of the city clerk of the City of San José.

    (Ords. 28166, 28838, 29334, 29806, 30326, 30837, 31256.)

  • 24.04.110 - Portions of California Plumbing Code which are not approved, adopted or incorporated by reference.

    A.

    The following portions of the California Plumbing Code or CPC, 2025 edition are not approved or adopted or incorporated in this chapter by reference, and shall not be deemed to be a part of this chapter nor a part of the plumbing code of the City of San José:

    1.

    Section 1.8.4

    2.

    Section 1.8.5

    3.

    Section 1.8.7

    4.

    Section 1.8.8

    5.

    Section 1.8.9

    6.

    Section 612

    (Ords. 28166, 28838, 29334, 29806, 30326, 30837, 31256.)

  • 24.04.120 - Portions of California Plumbing Code Appendices are approved, adopted, or incorporated by reference.

    A.

    The following portions of the California Plumbing Code or CPC 2025 Edition appendices are approved, adopted, or incorporated by reference unless otherwise noted.

    1.

    CPC Appendix A, Recommended Rules for Sizing Water Supply Systems.

    2.

    CPC Appendix B, Notes on Combination Waste and Vent Systems.

    3.

    CPC Appendix D, Sizing Stormwater Drainage Systems.

    4.

    CPC Appendix H, Private Sewage Disposal Systems.

    5.

    CPC Appendix G, Sizing of Venting Systems Serving Appliances Equipped with Draft Hoods, Category I Appliances, and Appliances Listed for Use With Type B Vents.

    6.

    Reserved.

    7.

    CPC Appendix I, Installation Standards.

    8.

    CPC Appendix M, Peak Water Demand Calculator.

    (Ords. 29806, 30326, 30837, 31256.)

  • Chapter 24.05 - MECHANICAL CODE

  • Part 1 - ADOPTION OF CMC PROVISIONS


  • 24.05.100 - Adoption of technical provisions of California Mechanical Code.

    A.

    Except as otherwise provided for in this chapter, the California Mechanical Code, 2025 edition, together with those omissions, amendments, exceptions and additions thereto as amended in Title 24 of the California Code of Regulations are approved and adopted, and are hereby incorporated in this chapter by reference and made a part hereof the same as if fully set forth herein.

    B.

    One copy of the CMC has been filed for use and examination of the public in the office of the city clerk of the City of San José.

    (Ords. 28166, 28838, 29334, 29806, 30326, 30837, 31256.)

  • 24.05.110 - Portions of California Mechanical Code which are not approved, adopted or incorporated by reference.

    A.

    The following portions of the California Mechanical Code or CMC, 2025 edition are not approved or adopted or incorporated in this chapter by reference, and shall not be deemed to be a part of this chapter nor a part of the mechanical code of the City of San José:

    1.

    Section 1.8.4

    2.

    Section 1.8.5

    3.

    Section 1.8.7

    4.

    Section 1.8.8

    5.

    Section 1.8.9

    (Ords. 28166, 28838, 29334, 29806, 30326, 30837, 31256.)

  • Chapter 24.06 - ELECTRICAL CODE

  • Part 1 - ADOPTION OF CEC PROVISIONS


  • 24.06.100 - Adoption of technical provisions of California Electrical Code.

    A.

    Except as otherwise provided for in this chapter, the California Electrical Code, 2025 edition, together with those omissions, amendments, exceptions and additions thereto as amended in Title 24 of the California Code of Regulations are approved and adopted, and are hereby incorporated in this chapter by reference and made a part hereof the same as if fully set forth herein.

    B.

    One copy of the CEC has been filed for use and examination of the public in the office of the city clerk of the City of San José.

    (Ords. 28166, 28838, 29334, 29806, 30326, 30837, 31256.)

  • 24.06.110 - Portions of California Electrical Code which are not approved, adopted or incorporated by reference.

    A.

    The following portions of the California Electrical Code or CEC, 2025 edition are not approved or adopted or incorporated in this chapter by reference, and shall not be deemed to be a part of this chapter nor a part of the electrical code of the City of San José:

    1.

    Section 89.108.4

    2.

    Section 89.108.5

    3.

    Section 89.108.7

    4.

    Section 89.108.8

    5.

    Section 89.108.9

    (Ords. 29334, 29806, 30326, 30837, 31256.)

  • Chapter 24.07 - CALIFORNIA EXISTING BUILDING CODE

  • Part 1 - ADOPTION OF CEBC PROVISIONS


  • 24.07.100 - Adoption of technical provisions of the California Existing Building Code.

    A.

    Except as otherwise provided for in this chapter, the California Existing Building Code 2025 edition together with those omissions, amendments, exceptions and additions thereto as amended in Title 24 of the California Code of Regulations are approved and adopted, and are hereby incorporated in this chapter by reference and made a part hereof the same as if fully set forth herein.

    B.

    One copy of the CEBC has been filed for use and examination of the public in the office of the city clerk of the City of San José.

    (Ords. 28166, 28838, 29334, 29806, 30326, 30837, 31256.)

  • 24.07.110 - Portions of California Existing Building Code which are not approved, adopted or incorporated by reference.

    A.

    The following portions of the California Existing Building Code, 2025 edition, are not approved or adopted or incorporated in this chapter by reference, and shall not be deemed to be a part of this chapter nor a part of the building code of the City of San José:

    1.

    Section 1.8.4

    2.

    Section 1.8.5

    3.

    Section 1.8.7

    4.

    Section 1.8.8

    5.

    Section 1.8.9

    6.

    Chapters 6 through 14

    (Ords. 29806, 30326, 30837, 31256.)

  • 24.07.120 - Portions of the California Existing Building Code Appendices are approved, adopted, or incorporated by reference.

    The following portion of the California Existing Building Code 2025 edition appendices are approved, adopted, or incorporated by reference.

    1.

    Appendix A, Chapters A1 through A5

    (Ords. 29806, 30326, 30837, 31256.)

  • Chapter 24.08 - WILDLAND-URBAN INTERFACE CODE

  • Part 1 - ADOPTION OF CWUIC (PROVISIONS)


  • 24.08.100 - Adoption of technical provisions of the California Wildland-Urban Interface Code.

    A.

    Except as otherwise provided for in this chapter, the California Wildland-Urban Interface Code 2025 edition together with those omissions, amendments, exceptions and additions thereto as amended in Title 24 of the California Code of Regulations are approved and adopted, and are hereby incorporated in this chapter by reference and made a part hereof the same as if fully set forth herein.

    B.

    One copy of the CWUIC has been filed for use and examination of the public in the office of the city clerk of the City of San José.

    (Ord. 31256.)

  • Chapter 24.09 - RESIDENTIAL CODE

  • Part 1 - ADOPTION OF CRC (PROVISIONS)


  • 24.09.100 - Adoption of technical provisions of California Residential Code.

    A.

    Except as otherwise provided for in this chapter, the California Residential Code, 2025 edition together with those omissions, amendments, exceptions and additions thereto as amended in Title 24 of the California Code of Regulations are approved and adopted, and are hereby incorporated in this chapter by reference and made a part hereof the same as if fully set forth herein.

    B.

    One copy of the CRC has been filed for use and examination of the public in the office of the city clerk of the City of San José.

    (Ords. 28838, 29334, 29806, 30326, 30837, 31256.)

  • 24.09.110 - Portions of California Residential Code which are not approved, adopted or incorporated by reference.

    A.

    The following portions of the California Residential Code, 2025 edition, are not approved or adopted or incorporated in this chapter by reference, and shall not be deemed to be a part of this chapter nor a part of the residential code of the City of San José:

    1.

    Section 1.8.4

    2.

    Section 1.8.5

    3.

    Section 1.8.7

    4.

    Section 1.8.8

    5.

    Section 1.8.9

    6.

    Chapter 1, Division II

    (Ords. 28838, 29334, 29806, 30326, 30837, 31256.)

  • 24.09.110.5 - Portions of the California Residential Code Appendices are approved, adopted, or incorporated by reference.

    A.

    The following portion of the California Residential Code or CRC 2025 edition appendices are approved, adopted, or incorporated by reference.

    1.

    Reserved.

    2.

    Appendix BF; Patio Covers.

    3.

    Appendix BG; Sound Transmission.

    4.

    Appendix CI; Swimming Pool Safety Act.

    5.

    Appendix BO; Existing Buildings and Structures.

    (Ords. 29806, 30326, 30837, 31256.)

  • 24.09.111 - Cross-references to California Residential Code.

    The provisions of this chapter contain cross-references to the provisions of the California Residential Code (CRC) in order to facilitate reference and comparison to those provisions.

    (Ords. 28838, 31256.)

  • Part 2 - BUILDING PLANNING (CRC CHAPTER 3)


  • 24.09.210 - Findings.

    The amendment set forth in this part is reasonably necessary because of the following local geological and topographical conditions:

    A.

    San José is within a very active seismic area. Severe seismic action could disrupt communications, damage gas mains, cause extensive electrical hazards, and place extreme demands on the limited and widely dispersed resources of the fire department resulting in failure to meet the fire and life safety needs of the community.

    B.

    The local geographic, topographic and climatic conditions pose an increased hazard in the acceleration, spread, magnitude, and severity of potential fires in the City of San José, and may cause a delayed fire response time, allowing further growth of the fire.

    (Ord. 28838.)

  • 24.09.220 - Reserved.

    Editor's note— Ord. 29806, § 55, adopted Nov. 1, 2016, repealed § 24.09.220, which pertained to alternative provisions (CRC Section R301.1.1), and derived from Ord. 28838.

  • 24.09.225 - Climatic and geographic design criteria (CRC Section R301.2).

    CRC Section R301.2 Table R301.2(1) is amended to read as follows:

    TABLE R301.2
    CLIMATIC AND GEOGRAPHIC DESIGN CRITERIA

    Ground Snow
    Load
    Wind Design Seismic Design
    Category
    Subject to Damage from
    Speed (mph) Topographic
    Effects
    Special Wind
    Region
    Windborne
    Debris Zone
    Weathering Frost Line
    Depth (Inches)
    Termite
    0 110 No No No D1 through E Negligible 5 Very High

     

    Winter Design Temp (°F) Ice Barrier
    Underlayment Required
    Flood Hazards Air Freezing Index Mean Annual Temp (°F)
    40 No Refer to Chapter 17.08 of the San José Municipal Code 0 59.7

     

    (Ords. 29334, 29806, 31256.)

  • 24.09.230 - Reserved.

    Editor's note— Ord. 29806, § 58, adopted Nov. 1, 2016, repealed § 24.09.230, which pertained to design criteria (CRC Section R301.2.1.1), and derived from Ords. 28838 and 29334.

  • 24.09.240 - Automatic fire sprinkler systems (CRC Section R309).

    CRC Section R309 is amended as follows

    R309. Design and installation. Automatic residential fire sprinkler systems shall be designed and installed in accordance with NFPA 13D or 13R as amended in Section 17.12 of San José Municipal Code.

    (Ords. 28838, 29806, 31256.)

  • Part 3 - BRACED WALL PANELS (CRC CHAPTER 6)


  • 24.09.310 - Findings.

    The amendment set forth in Parts 1 and 2 of this chapter is reasonably necessary because of the following local geological and topographical conditions:

    A.

    San José is within a very active seismic area.

    B.

    Gypsum wallboard and exterior Portland cement plaster have performed poorly during recent California seismic events.

    C.

    The shear values for gypsum wallboard and Portland cement stucco contained on the code are based on monodirectional testing.

    D.

    The limitation on the use of these systems as set forth in the amendment until cyclic loading testing are performed and evaluated is a more restrictive standard which will better prevent damage which can result from local conditions.

    (Ord. 28838.)

  • 24.09.320 - Reserved.

    Editor's note— Ord. 29806, § 59, adopted Nov. 1, 2016, repealed § 24.09.320, which pertained to seismic reinforcing (CRC Section R403.1.3), and derived from Ords. 28838 and 29334.

  • 24.09.330 - Wall Bracing (CRC Section R602.10 Table R602.10.3(3)).

    CRC Section R602.10 Table R602.10.3(3) is amended to read as follows:

    Table R602.10.3(3)
    BRACING REQUIREMENTS BASED ON SEISMIC DESIGN CATEGORY

    For SI: 1 foot = 304.8 mm, 1 pound per square foot = 47389 Pa.

    NP = Not Permitted

    a.

    Linear interpolation shall be permitted.

    b.

    Interpolation of bracing length between the Sds values associated with the seismic design categories shall be permitted when a site specific Sds value is determined in accordance with Section 1613.2 of the California Building Code.

    c.

    Where the braced wall line length is greater than 50 feet, braced wall lines shall be permitted to be divided into shorter segments having lengths of 50 feet or less, and the amount of bracing within each segment shall be in accordance with this table.

    d.

    Methods PFG and CS-SFB do not apply in Seismic Design Categories D0, D1 and D2.

    e.

    Methods PFH, PFG and ABW are only permitted on a single story or a first of two stories.

    f.

    Where more than one bracing method is used, mixing methods shall be accordance with section R602.10.4.1.

    g.

    One- and two-family dwellings in Seismic Design Category D2 exceeding two stories shall be designed in accordance with accepted engineering practice.

    (Ords. 28838, 29334, 30326, 30837.)

  • 24.09.340 - Section R602.10.8.1.

    CRC Section R602.10.8.1 is amended to read as follows:

    602.10.8.1 Braced wall panel connections for Seismic Design Categories D0, D1, and D2. Braced wall panels shall be fastened to required foundations in accordance with Section R602.11.1, and top plate lap splices shall be face-nailed with not less than eight 16d nails on each side of the splice. Wall sheathing shall not be attached to framing members by adhesives.

    All braced wall panels shall extend to the roof sheathing and shall be attached to parallel roof rafters or blocking above with framing clips (eighteen-gauge minimum) spaced at maximum twenty-four inches (6,096 mm) on center with four 8d nails per leg (total eight 8d nails per clip). Braced wall panels shall be laterally braced at each top corner and at maximum twenty-four-inch (6,096 mm) intervals along the top plate of discontinuous vertical framing.

    (30326.)

  • Chapter 24.10 - CALIFORNIA GREEN BUILDING STANDARDS CODE

  • Part 1 - ADOPTION OF CALGREEN PROVISIONS[4]


    Footnotes:
    --- (4) ---

    Editor's note— Ord. 31257, § 2, adopted Nov. 18, 2025, repealed §§ 24.10.110 - 24.10.130 of Part 1 of Ch. 24.10, which pertained to definitions (Amending CALGreen § 202), cross-references to CALGreen, and local amendments, respectively, and derived from Ords. 30311, 30834, and 31008.


  • 24.10.100 - Adoption of technical provisions of the California Green Building Standard Code.

    A.

    Except as otherwise provided for in this chapter, the residential mandatory measures and nonresidential mandatory measures of the California Green Building Standards (CALGreen) 2025 edition, together with those omissions, amendments, exceptions and additions thereto as amended in Title 24 of the California Code of Regulations are approved and adopted and are hereby incorporated in this chapter by reference and made a part hereof the same as if fully set forth herein.

    B.

    One copy of the CALGreen Code has been filed for use and examination of the public in the office of the City Clerk of the City of San José.

    (Ords. 28838, 29334, 29806, 30311, 30834, 31008, 31257.)

  • Part 2 - RESERVED[5]

    Footnotes:
    --- (5) ---

    Editor's note— Ord. 31257, § 2, adopted Nov. 18, 2025, repealed Part 2 of Ch. 24.10, § 24.10.200, which pertained to residential mandatory measures (CALGreen, Ch. 4) and derived from Ords. 30311, 30834, and 31008.


  • Part 3 - RESERVED[6]

    Footnotes:
    --- (6) ---

    Editor's note— Ord. 31257, § 2, adopted Nov. 18, 2025, repealed Part 3 of Ch. 24.10, § 24.10.300, which pertained to nonresidential mandatory measures (CALGreen, Ch. 5) and derived from Ords. 30311, and 30834.


  • Chapter 24.11 - CALIFORNIA HISTORICAL BUILDING CODE

  • Part 1 - ADOPTION OF CHBC PROVISIONS


  • 24.11.100 - Adoption of technical provisions of the California Historical Building Code.

    A.

    Except as otherwise provided for in this chapter, the California Historical Building Code, 2025 edition, including the appendices thereto, together with those omissions, amendments, exceptions and additions thereto as amended in Title 24 of the California Code of Regulations are approved and adopted, and are hereby incorporated in this chapter by reference and made a part hereof the same as if fully set forth herein.

    B.

    One copy of the CHBC has been filed for use and examination of the public in the office of the city clerk of the City of San José.

    (Ords. 28838, 29334, 29806, 30326, 30837, 31256.)

  • Chapter 24.12 - CALIFORNIA ENERGY CODE[7]

    Footnotes:
    --- (7) ---

    Editor's note— Ord. 31257, §§ 3 - 6, adopted Nov. 18, 2025, amended Ch. 24.12 in its entirety, in effect repealing and reenacting said Ch. 24.12 to read as set out herein. The former Ch. 24.12, Parts 1 - 8, §§ 24.12.100 - 24.12.130, 24.12.200, 24.12.300, 24.12.400, 24.12.410, 24.12.500, 24.12.600, 24.12.700, 24.12.710, and 24.12.800, pertained to California Building Energy Efficiency Standards and derived from Ords. 29806, 30311, 30834, 30950, 31081.


  • Part 1 - ADOPTION OF CALIFORNIA ENERGY CODE


  • 24.12.100 - Adoption of technical provisions of the California Energy Code.

    A.

    Except as otherwise provided for in this Chapter, the California Energy Code 2025 edition, including the appendices thereto, together with those omissions, amendments, exceptions and additions thereto as amended in Title 24 of the California Code of Regulations are approved and adopted, and are hereby incorporated in this Chapter by reference and made a part hereof the same as if fully set forth herein.

    B.

    One copy of the California Energy Code has been filed for use and examination of the public in the Office of the City Clerk of the City of San José.

    (Ord. 31257.)

Loading complete